Professional Documents
Culture Documents
UAF - NUS Lecture Sept 2010
UAF - NUS Lecture Sept 2010
Storage
g Facility
y in Singapore
g p
Dr Zhou Yingxin
Senior Principal
p Engineer
g
Defence Science & Technology Agency
Outline
W can’t
We ’t ttake
k everything
thi ffor G
Granite!
it !
Planning
g for SI
Dependent on objectives of SI work and many
other factors.
Norwegian tunnelling recommendations: 2-10%
of excavation cost for road tunnels; 5-15% for
sub sea tunnels
sub-sea
Caverns: about 1-2% of rock excavation cost
Engineering
g gggeological
g investigation
g of the rock,,
rock discontinuities and rock mass at site and in
laboratory
Integral part of the engineering design process for
any projects involving the ground
I
Important
t t for
f layout
l t planning,
l i supportt design
d i and d
costing
Also an important aspect of construction safety
and geological risk management
Phases of Site Characterisation
Geological
g mapping
pp g ((exposure
p and discontinuities))
Geophysical surveys (detective work)
Exploratory
p y drilling
g ((soil drilling
g and diamond core
drilling)
Laboratory testing (rock material properties)
In situ testing (rock mass properties)
In situ stress measurements
Important
p To Remember
No single
g technique
q is best
Select techniques based on geology and data
requirements
Complementary methods reduce uncertainty
Different methods as cross check
Allow for Phased SI during planning, design, and
construction
Methods of Investigation
g Used
Un-damaged wall
Composite
p Geological
g Profile
Weathered
Weathered Weathered EN1-ES1 trench – T12
trench – T11 trench – T12 F11 EN2-ES2 F11
68/79 178/83
181/11
292/55
Rock Joint Properties
p
Joint conditions Friction Angle, Cohesion, C
(o) (Kpa)
Freshly fractured and dry 45 6
45.6 258
No major
j tectonic faults
Three-layer geological profile
Deepp weathering g trenches
Sub-vertical strips of densely jointed rock
Favourable highg horizontal stresses
Relatively low permeability
Rock mass g generallyyg
good to veryyggood for
cavern construction
Geological
g Model
• Residual Soil
• Weathered granite
• Fresh granite
Weathering trenches &
dense joint strips
Rock Mass Classification
Rock Tunnelling
g Quality
y Index ((Q-system):
y )
Q = (RQD/Jn)(Jr/Ja)(Jw/SRF)
0 01 – 0.1
0.01 01 Extremely poor 19
1.9
4 – 10 Fair 13.6
10 – 40 Good 51.8
Survey Blasting
Rockbolt
Ventilation
Scaling
Cycle
y Time for a Single
g Face
16 15
14 12.7
1999 2001
12
Time ((hrs)
10
8
6 4 3.6 4.5
4 2.6 1.9
1 0.4 1.51.6 1 0.5 1 1.51.6
2 0.50.5
0
rt
n
l
ng
g
g
n
ou
ta
tio
tio
po
lin
in
io
To
gi
al
at
ga
ng
ila
ril
up
r
Sc
ha
ilis
nt
i
ki
lS
av
Ve
uc
ob
tia
N
M
M
g/
i
In
tin
as
Bl
Activity
Typical
yp Blasting
g Patterns
Perimeter holes
Production holes
65 m2 101 125 m2 151
holes holes
Cut holes
Lifter holes
Slash Pilot
Chamber
section: 275 m2
Bench 3
Bench, 3.5-m
5 m high
Blasting
g and Safety
y
Cost savings
savings, better safety,
safety
Mobile Charging Unit
and improved productivity!
Blasting
g Efficiency
y and Overbreak
Powder factor reduction from 2.5 kg/m3 to about 2 kg/m3
Underbreak is more expensive to remove than overbreak
Overbreak related to look-out angles, geology, and drilling accuracy,
and blasting design
Typical
yp overbreak in g
granite rock: 14-28% tunnel area
12
Kg/m 3
4 y = 0.0845x + 1.6906
0
0 10 20 30 40 50
% off O
Overbreak
b k
Blasting
g Vibrations
n
R
V H B
V = Peak Particle Velocity; H = constant;
Q B = scaling
li llaw; n = attenuation
tt ti coefficient
ffi i t
10
eak particle v
1
Pe
0
1.0 10.0 100.0
Scaled horizontal distance, m/kg1/3
Blasting
g Vibration Criteria
S
Singapore: 15 mm/s
/ is commonly
l imposed.
d
Good to be safe, but there is a price to pay! So excessive
conservatism is a waste of money!
Relative Costs for Vibration Control
Allowable Peak Particle Velocity, mm/s
Distance to
structure 20 mm/s 40 mm/s 60 mm/s
Site investigation
g and rock mass classification
Preliminary design based on precedence and
rock mass quality
Tunnel mapping by engineering geologist after
excavation
Final support design prescribed based on
mapped conditions and actual rock mass quality
S
Supported
t d by
b numerical
i l modelling
d lli (if necessary))
and instrumentation
Q-chart for Support
pp Design
g
Rock Bolt Length
g
Ref: E Hoek, 2001
General recommendations:
Roof: L = 2 + 0.15xSpan/ESR. Walls: L = 2 + 0.15xHeight/ESR
L = meters; B = Span; H = wall height; ESR = Excavation Support Ratio
Quantifying
y g Shotcrete Design
g
5 mm 10 mm 15 mm 20 mm 25 mm
Rock Class F E D C, B A
Energy Absorption, Joules, 560 400 280 200 NA
RDP (40 mm)
Energy Absorption, Joules, 1400 1000 700 500 NA
EFNARC (25 mm)
Grouting
g
Probe drillhole
Rock Mass Classification Method
Minimum competent
p rock cover of 20 m or 1.5
times span
Empirical rule of 0.2 x tunnel span for arch height
results in significant unused tunnel space
Does not take into consideration of favourable
h i
horizontal
t l stresses
t
Optimisation
p of Rock Support
pp
Numerical modelling
g
Geological representation
Realistic rock mass properties
Tunnel stability criteria (is deformation a good criterion to use in
hard rock?)
Instrumentation and monitoring
Use of results
Absolute deformation vs measured deformation vs supported
deformation
A Tale of Two Tunnels
160
140
100
80
60
40
20
0
0 20 40 60 80 100 120 140 160 180
Tunnel Orientation (Degrees)
Instrumentation and
g
Monitoring
Instrumented Cavern Sections
• Instrumentations &
monitoring performed during
& after construction:
– Borehole extensometer
– Convergence (tape)
– Bolt
B l load
l d (strain
( i gauges))
Cavern Excavation Sequence
q
CL
Slash
5 metres
Benching
Combined Instrumentation Section
Surface MPBX
Notes:
The locations of all anchors of
multi-point
p extensometers all
displayed with reference to the
crown surface of the cavern.
25m
MPBX-1(BH 1)
12m
MPBX-2 (BH 2) 6m MPBX-3 (BH 3)
2m
Diameter=76mm
Di t 76
Diameter=76mm Length=25 m
Length=25.m
0m
CT-1 CT-3
CT-4 Rebar-1
CT-2 Rebar-3
MPBX-4
MPBX 4 (BH4) Rebar-2
Rebar 2
MPBX-5 (BH 5)
Diameter=76mm
Length=12.m Rebar-5
Rebar-4
3.2m 3.2m
CT-5
Measured Deformation in Surface
MPBX
Displacement and Progress
(S f
(Surface MPBX M Main
i Phase
Ph Chamber
Ch b 44--CH50)
CH50)
4.0 100
25 m 12 m
3.0
6m 2m
rock; +:intto cavern mm)
80
m)
20
2.0
Progress (m
ment (-:intoo
Slash Pilot
1.0 Benching 60
0.0
Displacem
Excavation P
-1.0 40
-2.0
20
E
30
-3.0
-4.0 0
0 50 100 150 200 250 300 350 400
Days after 03 December 2001 (Installation date)
Measured Deformation in Internal
MPBX after Installation
Displacement and Progress
(MPBX-BH1 Main Phase Chamber 4--CH50)
4.0 100
90
3.0
80
ment (-:into rrock;
on Progress (m)
2.0
m)
70
o cavern mm
1.0 60
0.0 50
Displacem
Excavatio
+:into
-1.0 40
0m 2m 30
-2.0 6m 12m
20
Pilot Benching
-3.0 Slash 10
-4.0 0
0 50 100 150 200 250 300
Days after 19 March 2002
Summary of Deformation
Measurements
20.0
0.0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0
-20.0
Point 1 Point 2 1
2
3
-40.0 Point 3 Point 4 4
-60.0
Days after 15 March 2001
Comparison with Gjovik Stadium in
Norway (after Broch et al.
al 1996)
Rock Conditions & Bolt GjØvik Stadium, Norway Singapore Site
Parameters (Based on Broch at el. 1996)
Typical Rock Mass Quality 1 - 30 4 - 36
Vertical Stress, MPa 1 2-3
Max Horizontal Stress 3.5 8.2
Minimum Horizontal Stress 2 4.6
Ratio of Hori. to Vertical Stress 2-3.5 2-3
Tunnel/cavern span, meters 61 10 – 30
Type of Rock Bolts Fully grouted rebars Fully grouted CT-bolts
L th meters
Lengths, t 6 m (with
( ith alternating
lt ti 12-m
12 36m
3-6
long cables
Spacing, meters 2.5 m x 2.5 m 1.5 – 2.4
p y, KN
Bolt Capacity, 220 250
Minimum Measured Loads, KN 1 – 1.5 3 - 12
Typical Measured Loads, KN 30 - 60 20- 60
Typical Load Percentage 13 – 27% 8 – 24%
Ma im m Meas
Maximum Measured
red Load,
Load KN 87 70
Max Load Percentage 40% 28%
Comparison
p of World-wide Cost
45000
ost, $/m
World wide tunnelling cost (Hoek, 2001)
40000
upport Co
35000
30000
25000
Excavation and Su
20000
15000
10000
5000
0
6 8 10 12 14 16
Tunnel Span, meters
Competitive
p cost in Singapore
g p due p
primarily
y to a)) large
g tunnel
sections; b) good rock; and c) low labour cost
Conclusions
No surprises in construction due to good site
investigations
Bulk emulsion explosives proven very beneficial
for safety and productivity
High horizontal stress key factor for stability of
large-span
g rock caverns
For favourable horizontal stresses, support
design using Q-system could be further
optimized
ti i d
Useful References