COEFFICIENT FOR COMMON BURNT CLAY BRICKWORK COEFFICIENT FOR BLOCK WORK (600x300x20

Volume of Bricks with mortar = 0.24X0.12X0.08 0.002 Volume of Blocks with mortar = 0.61X0.31X0.21
No. of bricks required for 1cu.m. 434.000 No. of blocks required for 1cu.m.
Volume of Bricks without mortar = 0.23X0.11X0.07 0.002 Volume of Blocks without mortar = 0.6X0.3X0.2
Volume of 434 bricks without mortar 0.769 Volume of 25 blocks without mortar
Cement Mortar for 1cu.m. 0.250 Cement Mortar for 1cu.m.
Cement coeff./cum for 1:6 mortar (DSR 3.6) 2.500 Cement coeff./cum for 1:6 mortar (DSR 3.6)
Coefficient per cum 0.625 Coefficient per cum
Therefore, coefficient per cum=0.625 quintal (DSR 6.1.2) Therefore, coefficient per cum=0.25 quinta
DERIVED BASED ON NEAREST
COEFFICIENT FOR BLOCK WORK (600x300x200) COEFFICIENT FOR BLOCK WORK (600x300x300)
ume of Blocks with mortar = 0.61X0.31X0.21 0.040 Volume of Blocks with mortar = 0.61X0.31X0.31 0.059
No. of blocks required for 1cu.m. 25.000 No. of blocks required for 1cu.m. 17.000
ume of Blocks without mortar = 0.6X0.3X0.2 0.036 Volume of Blocks without mortar = 0.6X0.3X0.3 0.054
Volume of 25 blocks without mortar 0.900 Volume of 17 blocks without mortar 0.918
Cement Mortar for 1cu.m. 0.100 Cement Mortar for 1cu.m. 0.100
ement coeff./cum for 1:6 mortar (DSR 3.6) 2.500 Cement coeff./cum for 1:6 mortar (DSR 3.6) 2.500
Coefficient per cum 0.250 Coefficient per cum 0.250
Therefore, coefficient per cum=0.25 quintal Therefore, coefficient per cum=0.25 quintal
DERIVED BASED ON NEAREST SIMILAR MATERIAL (NOT AVAILABLE IN DSR)
COEFFICIENT FOR COMMON BURNT CLAY BRICKWORK COEFFICIENT FOR MODULAR

Volume of Bricks with mortar = 0.24X0.12X0.08 0.0020 Volume of Modular Bricks with mortar = 0
No. of bricks required for 1cu.m. 434 No. of bricks required for 1cu.m
Volume of Bricks without mortar = 0.23X0.11X0.07 0.0018 Volume of Bricks without mortar = 0.19X
Volume of 434 bricks without mortar 0.7686 Volume of 500 bricks without mo
Cement Mortar for 1cu.m. 0.2500 Cement Mortar for 1cu.m.
Cement coeff./cum for 1:4 mortar (DSR 3.4) 3.8000 Cement coeff./cum for 1:3 mortar (D
Coefficient per cum 0.9500 Coefficient per cum
Therefore, coefficient per cum=0.95 quintal (DSR 6.1.1) Therefore, coefficient per cum=1.27
COEFFICIENT FOR BLOCK WORK (600x300x200) COEFFICIENT FOR BLO

Volume of Blocks with mortar = 0.61X0.31X0.21 0.0397 Volume of Blocks with mor
No. of blocks required for 1cu.m. 25 No. of blocks requir
Volume of Blocks without mortar = 0.6X0.3X0.2 0.0360 Volume of Blocks without m
Volume of 25 blocks without mortar 0.9000 Volume of 17 blocks
Cement Mortar for 1cu.m. 0.1000 Cement Mortar
Cement coeff. Per cum for 1:4 mortar 3.8000 Cement coeff. Per cum
Coefficient per cum 0.3800 Coefficient p
Therefore, coefficient per cum=0.38 quintal Therefore, coefficie
DERIVED BASED ON NEAREST SIMILAR MATERIAL (NOT AVAILA
COEFFICIENT FOR MODULAR BRICKWORK COEFFICIENT FOR BLOCK WORK (600x300x100)

e of Modular Bricks with mortar = 0.2X0.1X0.1 0.0020 Volume of Blocks with mortar = 0.61X0.31X0.11
No. of bricks required for 1cu.m. 500 No. of blocks required for 1cu.m.
e of Bricks without mortar = 0.19X0.09X0.09 0.0015 Volume of Blocks without mortar = 0.6X0.3X0.1
Volume of 500 bricks without mortar 0.7695 Volume of 48 blocks without mortar
Cement Mortar for 1cu.m. 0.2500 Cement Mortar for 1cu.m.
ment coeff./cum for 1:3 mortar (DSR 3.3) 5.1000 Cement coeff. Per cum for 1:4 mortar
Coefficient per cum 1.2750 Coefficient per cum
erefore, coefficient per cum=1.275 quintal (DSR 6.3.7) Therefore, coefficient per cum=0.57 quintal (DSR 6.38)
COEFFICIENT FOR BLOCK WORK (600x300x300)

Volume of Blocks with mortar = 0.61X0.31X0.31 0.0586


No. of blocks required for 1cu.m. 17
Volume of Blocks without mortar = 0.6X0.3X0.3 0.0540
Volume of 17 blocks without mortar 0.9180
Cement Mortar for 1cu.m. 0.1000
Cement coeff. Per cum for 1:4 mortar 3.8000
Coefficient per cum 0.3800
Therefore, coefficient per cum=0.38 quintal
MATERIAL (NOT AVAILABLE IN DSR)
WORK (600x300x100)

0.61X0.31X0.11 0.0208
or 1cu.m. 48
ar = 0.6X0.3X0.1 0.0180
out mortar 0.8640
cu.m. 0.1500
1:4 mortar 3.8000
m 0.5700
m=0.57 quintal (DSR 6.38)
COEFFICIENT FOR CEMENT CONCRETE 1:1.5:3 COEFFICIENT FOR CEMENT CONCRE
Wet Volume of Cement Concrete 1.00 Wet Volume of Cement Concrete
Dry Volume of Cement Concrete 1.54 Dry Volume of Cement Concrete
Volume of Cement in cu.m. 0.28 Volume of Cement in cu.m.
Bulk Density of Cement (Kg/cu.m) 1440.00 Bulk Density of Cement (Kg/cu.m)
Weight of Cement (Kg) 400.00 Weight of Cement (Kg)
Weight of Cement (Quintal) 4.00 Weight of Cement (Quintal)
Therefore, coefficient per cum= 4 quintal (DSR 4.1.2) Therefore, coefficient per cum= 3.2 quintal

COEFFICIENT FOR CEMENT CONCRETE 1:4:8


Wet Volume of Cement Concrete 1.00
Dry Volume of Cement Concrete 1.54
Volume of Cement in cu.m. 0.12
Bulk Density of Cement (Kg/cu.m) 1440.00
Weight of Cement (Kg) 170.00
Weight of Cement (Quintal) 1.70
Therefore, coefficient per cum= 1.7 quintal (DSR 4.1.8)
COEFFICIENT FOR CEMENT CONCRETE 1:2:4 COEFFICIENT FOR CEMENT CONCRETE 1:3:6
Wet Volume of Cement Concrete 1.00 Wet Volume of Cement Concrete
Dry Volume of Cement Concrete 1.54 Dry Volume of Cement Concrete
Volume of Cement in cu.m. 0.22 Volume of Cement in cu.m.
Bulk Density of Cement (Kg/cu.m) 1440.00 Bulk Density of Cement (Kg/cu.m)
Weight of Cement (Kg) 320.00 Weight of Cement (Kg)
Weight of Cement (Quintal) 3.20 Weight of Cement (Quintal)
ore, coefficient per cum= 3.2 quintal (DSR 4.1.3, 4.1.4) Therefore, coefficient per cum= 2.2 quintal (DSR 4.1.5, 4.1.6)
COEFFICIENT FOR CEMENT CONCRETE 1:3:6
Wet Volume of Cement Concrete 1.00
Dry Volume of Cement Concrete 1.54
Volume of Cement in cu.m. 0.15
Bulk Density of Cement (Kg/cu.m) 1440.00
Weight of Cement (Kg) 220.00
Weight of Cement (Quintal) 2.20
ore, coefficient per cum= 2.2 quintal (DSR 4.1.5, 4.1.6)