Construction of 4/6 laning Pavement from km 132.375 to km 153.058(length 20.

683km) on Daboka Dimapur


section(Dimapur by pass)on NH36&NH39 on EPC basis under phase -A of SARDP-NE in the State of Nagaland

M/S Yongma Engineering Co. Ltd in association with M/S Sterling Indo Tech National highways and Infrastructure
M/S Simplex Infrastructures Limited
Consultants Pvt Ltd development Corporation Limited

TEST SUMMARY FOR REINFORCED SOIL

Location of Sampling 147+700 LHS

Source of Sample BA-04

Date of Sampling 02.06.2020

Date of Testing 02.06.2020

Kind of Material Coarse Grained Soil

Sample No
Name of Test Results Average Remarks
1 2

Maximum Dry Density (ϒd) g/cc 1.860 1.855 1.858


Modified Proctor Test
( IS 2720 Part 8)
Optimum Moisture Content (%) 11.00 10.80 10.9

Angle of Internal Friction ( ɸ) Deg. 38.0 36 37.0


Direct Shear Test
( IS 2720 Part 13 )
Cohession ( C) -0.06 -0.09 -0.08

Liquid Limit ( LL) % 25.6 24.8 25.2

Atterberg Limit test


Plastic Limit (PL) % N.P N.P N.P
( IS 2720 Part 5 )

Plasticity Index (PI) % 0 0 0.0

Passing % on 75mm Sieve 100 100 100

Passing % on 4.75mm Sieve 100 98.6 99.3

Sieve Analysis Test Passing % on 0.425mm Sieve 81.6 78.7 80.2


( IS 2720 Part 2 )

Passing % on 0.075mm Sieve 37.0 37.8 37.4

Passing % on 0.015mm Sieve 7.3 5.7 6.5

EPC REPRESENTATIVE CONSULTANT REPRESENTATIVE