Project : Two Storey Sales office Building

Location : Himamaylan City, Neg. Occ.

Subject : Quotation

Scope of Works Qty Unit Unit Cost Amount


1. Supply and Installation of 3/4 PVC pipe from data location 229.43 l.m 320.00 73,417.60
to data cabinet including fittings. -
-
2. Supply and Installation of UtilityBox 54.00 pcs 650.00 35,100.00
-
4.50 l.m 320.00 1,440.00
3. Supply and Installation 3/4 PVC pipe from Ground Floor
-
Data Cabinet to 2nd Floor Data Cabinet including fittings
-
-
4. Supply of Consumables 1.00 lot 20,000.00 20,000.00
-
5. Labor for Chipping & Restoration Works 58.50 l.m 350.00 20,475.00

TOTAL COST (Vat-Ex) 150,432.60