Professional Documents
Culture Documents
Critical Path Analysis Example: 1. Original Data
Critical Path Analysis Example: 1. Original Data
Duration
Activity Activity code Predecessors (Days)
A F
START B G
C E
We identify the critical path from the activities that have 0 slack, i.e. C, E, G.
It can be seen that these activities form a continuous path through the network from start to end.
More explanation about this method can be found in our book or by downloading the tool.
END
Latest start Latest finish
(LS) (LF) Slack
2 4 2
2 8 2
0 3 0
4 8 2
3 8 0
15 16 13
8 16 0