CONTINUATION OF CONSTRUCTION

PROJECT : TWO‐STOREY RESIDENTIAL
LOCATION : ANNEX 31, BETTER LIVING SUBDIVISION

NO. OF WORKERS : 5  (INCLUDING THE FOREMAN)

SCOPE OF WORKS

Plastering DATE START DATE FINISH NO. OF DAYS


Interior Second Floor 29‐Jun 1‐Jul 3
Exterior Wall Ground Floor (Left Wall) 29‐Jun 3‐Jul 5
CHB Laying
Roof Deck 4‐Jul 7‐Jul 3
2F Exterior Wall (Right Wall) 2‐Jul 7‐Jul 5
(Correction of Window Opening at Stairs
and Closure of blackout)
Stair 2F-Roof Deck
Fabrication and Installation of RSB 8‐Jul 11‐Jul 4
Fabrication and Installation of Formworks 9‐Jul 11‐Jul 3
Concreting 13‐Jul 13‐Jul 1
Plastering
Exterior Wall Second Floor
Front 14‐Jul 15‐Jul 2
Right 14‐Jul 17‐Jul 4
Rear 17‐Jul 18‐Jul 2
Exterior Wall Ground Floor (Rear Wall) 18‐Jul 21‐Jul 3

Total  Duration 20

Qty. Daily wage Total


Foreman 1 700       14,000.00
Mason 2 550       22,000.00
Labor 2 450       18,000.00

Total Labor Cost       54,000.00