JULY

ACTIVITIES M T W TH F ST SN M T W TH F ST SN M T W TH F ST SN M T W TH F ST SN M T W TH F ST SN M T W TH F

22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Plastering
Interior Second Floor 1 1 1
Exterior Wall Ground Floor (Left Wall) 1 1 1 1 1

CHB Laying
Roof Deck 1 1 1
2F Exterior Wall (Right Wall) 1 1 1 1 1
(Correction of Window Opening at Stairs and
Closure of blackout)

Stair 2F-Roof Deck


Fabrication and Installation of RSB 1 1 1 1
Fabrication and Installation of Formworks 1 1 1
Concreting 1

Plastering
Exterior Wall Second Floor
Front 1 1
Right 1 1 1 1
Rear 1 1
Exterior Wall Ground Floor (Rear Wall) 1 1 1