Professional Documents
Culture Documents
One Month Look Ahead
One Month Look Ahead
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete
DMRC DC-2 DMRC DC-02 Initial Works Programme 385 385 0% 30-Dec-19 18-Jun-21 165
HO- VD-STR-7 Handover of Land for Stretch-7 of viaduct exclu. viaduct area of station from Ch: 8039.28 m to Ch:
0 8996.16 m 0 0% 15-Jan-20 49
HO- VD-STR-8 Handover of Land for Stretch-8 of viaduct exclu. viaduct area of station from Ch: 9136.81 m to Ch:
0 10470.73 m 0 0% 15-Jan-20 49
HO- VD-STR-9 Handover of Land for Stretch-9 of viaduct exclu. viaduct area of station from Ch: 10611.38 m to Ch:
0 12098.41 m 0 0% 15-Jan-20 49
HO-ST1-JMS Handover of Complete land for Jharoda Majra @ Ch Start: 8996.16m 0 0 0% 05-Jan-20 25
HO-ST2-BRS Handover of Complete land for Borari @ Ch Start: 10470.73m 0 0 0% 05-Jan-20 27
HO-ST3-YVS Handover of Complete land for Yamuna Vihar @ ChStart: 1325.51m 0 0 0% 15-Jan-20 17
HO-ST4-BJS Handover of Complete land for Bhajanpura @ Ch Start: 2798.5m 0 0 0% 15-Jan-20 58
HO-ST5-KKS Handover of Complete land for Khajuri Khas @ Ch Start: 3602.4m 0 0 0% 15-Jan-20 58
HO-ST6-SVS Handover of Complete land for Sonia Vihar @ Ch Start: 4844.14m 0 0 0% 20-Jan-20 283
HO-ST7-SGS Handover of Complete land for Soorghat @ Ch Start: 6532.44m 0 0 0% 20-Jan-20 314
HO-ST8-JTS Handover of Complete land for Jagatpura @ Ch Start: 7898.63m 0 0 0% 20-Jan-20 314
HO-ST8-YRB Handover of Land for Yamuna Bridge 0 0 0% 05-Jan-20 2
DMRC DC-2.2 Preliminary Work & Mobilization 145 145 0% 30-Dec-19 19-Jul-20 405
ECS-RH3-ID-S Identification of Existing Building in Work Area & Intimation to Employer 30 30 0% 02-Mar-20 02-Apr-20 184
DMRC DC-2.2.2 Contractual Submission and Approvals 141 141 0% 30-Dec-19 23-May-20 610
DMRC DC-2.2.2.1 Submission of Construction Work Programme 106 106 0% 30-Dec-19 17-Apr-20 645
Acheive-KD-1 (V) Acheivement of KD-1 of Viaduct 0 0 0% 26-Jan-20 -1
DWP-S Submission of Detailed Work Program 60 60 0% 16-Feb-20 17-Apr-20 645
IEV-Const Prog Submission of Construction Programme for Integrated Elevated Viaduct including ramp and shifting
26 of meadian and
26 road 0% 30-Dec-19 26-Jan-20 -1
IEV-KD-1 Achievement of KD-1 of IEVD 0 0 0% 26-Jan-20 -1
IWP-A Approval of Initial Work Program 20 20 0% 27-Jan-20 16-Feb-20 645
IWP-S Submission of Construction Programme 26 26 0% 30-Dec-19 26-Jan-20 -1
DMRC DC-2.2.2.2 Other Contractual Submissions 141 141 0% 30-Dec-19 23-May-20 70
OCS-MD-A Approval of Mix Design 10 10 0% 31-Jan-20 10-Feb-20 8
OCS-MD-S Submission of Mix Design 30 30 0% 30-Dec-19 31-Jan-20 8
OCS-MS-A Method statements approval 120 120 0% 21-Jan-20 23-May-20 70
OCS-MS-S Method statements submissions 120 120 0% 30-Dec-19 02-May-20 70
OCS-Org. Chart-S Submission of Organization chart 20 20 0% 30-Dec-19 20-Jan-20 87
OCS-PQP-A Approval of Project Quality Plan 10 10 0% 29-Jan-20 08-Feb-20 69
OCS-PQP-S Submission of Project Quality Plan 28 28 0% 30-Dec-19 29-Jan-20 69
OCS-SHE-A Approval of SHE plan 10 10 0% 29-Jan-20 08-Feb-20 10
OCS-SHE-S Submission of SHE plan 28 28 0% 30-Dec-19 29-Jan-20 10
DMRC DC-2.2.3 Casting Yard Establishment 123 123 0% 30-Dec-19 05-May-20 215
CY-SO Establishing Site Office 30 30 0% 30-Dec-19 31-Jan-20 15
DMRC DC-2.2.3.1 Enabling Structures-Design 95 95 0% 07-Jan-20 13-Apr-20 35
Design-ES-Layout-A Approval of Casting yard layout drawing 10 10 0% 22-Jan-20 02-Feb-20 18
Design-ES-Layout-S Submission of Casting yard layout drawing 15 15 0% 07-Jan-20 22-Jan-20 18
Design-ES-SUBSTR-AApproval of Substructure mould drawings 10 10 0% 28-Mar-20 07-Apr-20 41
Design-ES-SUBSTR-SSubmission of Substructure mould drawing 20 20 0% 07-Mar-20 28-Mar-20 41
Design-ES-SUPSTR-AApproval of Superstructure mould drawings 10 10 0% 28-Jan-20 07-Feb-20 0
Design-ES-SUPSTR-SSubmission of Superstructure mould drawing 20 20 0% 07-Jan-20 28-Jan-20 0
Design-ES-SUPSTR-TFA
Submission of Traveller Formwork Design & Drawing 20 20 0% 24-Mar-20 13-Apr-20 0
DMRC DC-2.2.3.2 Casting Yard-Set up 123 123 0% 30-Dec-19 05-May-20 116
Acheive-KD-2 (ST) Acheivement of KD-2 of Stations 0 0 0% 23-Mar-20 0
Acheive-KD-2 (V) Acheivement of KD-2 of Viaduct 0 0 0% 24-Feb-20 0
Acheive-KD-4 (V) Acheivement of KD-4 of Viaduct 0 0 0% 23-Mar-20 0
CY-Setup-1st Form-CACompletion of 1st Formwork for precast elements i.e. Cross arm, pie Girder, Cross beam for Engineer's
1 approval 1 0% 22-Mar-20 23-Mar-20 0
CY-Setup-AD Area Development 77 77 0% 30-Dec-19 19-Mar-20 0
CY-Setup-BP1 Establishment and Commisioning of 1st Batching Plant (production of 1st batch of concrete) 45 45 0% 09-Jan-20 24-Feb-20 0
CY-Setup-Gantry Erec Foundation and erection of Gantrys 53 53 0% 02-Feb-20 27-Mar-20 18
CY-Setup-Mould-CA Setting up of balance Cross Arms and mould 25 25 0% 28-Mar-20 22-Apr-20 113
CY-Setup-Mould-RG Setting up of balance Station-Rec Girder and mould 45 45 0% 18-Mar-20 03-May-20 31
CY-Setup-UG-1st FormCompletion of first formwork for U Girder element of production line for Engineers inspection and
1 approval 1 0% 22-Mar-20 23-Mar-20 0
CY-Setup-UG-1st RH Setting up of 1st row of Casting Bed of U Girders/Cross arm, pie Girder 18 18 0% 03-Mar-20 22-Mar-20 0
CY-Setup-UG-Bal. RH Setting up of balance rows of Casting Bed and mould/formwork of U Girders 35 35 0% 30-Mar-20 05-May-20 116
DMRC DC-2.2.3.3 Mould Fabrication 84 84 0% 07-Feb-20 03-May-20 217
CY-MouldFab-CA Station-Cross Arms 20 20 0% 02-Mar-20 23-Mar-20 13
CY-MouldFab-IG PSC I Girders 50 50 0% 07-Feb-20 29-Mar-20 251
CY-MouldFab-PB Portal Beam 10 10 0% 13-Mar-20 23-Mar-20 13
CY-MouldFab-PC Pier Cap 60 60 0% 07-Feb-20 08-Apr-20 0
CY-MouldFab-RG Station-Cross Rec girder 60 60 0% 02-Mar-20 03-May-20 31
CY-MouldFab-TG PSC-T- Girders 60 60 0% 07-Feb-20 08-Apr-20 0
CY-MouldFab-UG-1 U Girder-first line and stations Cross arms, rec-girder 1st formwork 25 25 0% 07-Feb-20 03-Mar-20 0
CY-MouldFab-UG-2 U Girder-balance lines 60 60 0% 28-Feb-20 29-Apr-20 116
DMRC DC-2.8 Engineering & Design 524 524 0% 30-Dec-19 18-Jun-21 79