DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

DMRC DC-2 DMRC DC-02 Initial Works Programme 385 385 0% 30-Dec-19 18-Jun-21 165

DC-02-CA Signing of ContractAgreement 30 30 0% 20-Jan-20 20-Feb-20 19


DC-02-PBG Submission of Performance Bank Guarantee including ABG 20 20 0% 30-Dec-19 20-Jan-20 -1
DC-02-PBG2 Submission of Additional Bank Guarantee (1% of Contract Value) 28 28 0% 30-Dec-19 29-Jan-20 -1
PV-01-NTP Notice to Proceed/Date of Commencement 0 0 100% 30-Dec-19
DMRC DC-2.1 Key Dates 41 41 0% 27-Jan-20 23-Mar-20 0

DMRC DC-2.1.1 Viaduct 55 55 0% 27-Jan-20 23-Mar-20 0


KD-1 (V) Submission of construction programme. 0 0 0% 27-Jan-20* 0
KD-2 (V) Commissioning of 1st Batching Plant (production of 1st batch of concrete) 0 0 0% 24-Feb-20* 0
KD-3 (V) Submission of Definitive Design 0 0 0% 24-Feb-20* 0
KD-4 (V) Completion of 1st Formwork for U-Girder element of production line for Engineer's approval 0 0 0% 23-Mar-20* 0
DMRC DC-2.1.2 Stations 20 20 0% 24-Feb-20 23-Mar-20 0
KD-1 (ST) Submission of Definitive Design 0 0 0% 24-Feb-20* 0
KD-2 (ST) Completion of 1st Formwork for precast elements i.e. Cross arm, pie Girder, Cross beam for Engineer's
0 approval 0 0% 23-Mar-20* 0
DMRC DC-2.1.2.1 Access to finishing contractor in operational rooms along with permanent staircase 0 0 0% 0
DMRC DC-2.1.2.2 Completion of lift shaft & Escalator pits (Concourse to Platform) 0 0 0% 0
DMRC DC-2.1.2.3 Completion of one entry exit structure (Ground to Concourse) including lift/escalator pit 0 0 0% 0
DMRC DC-2.1.2.4 Access to PEB & Finishing contractor at platform level 0 0 0% 0
DMRC DC-2.1.2.5 Completion of entire works as per the Contract 0 0 0% 0
DMRC DC-2.1.3 Integrated Elevated Viaduct 28 28 0% 27-Jan-20 24-Feb-20 0
KD-1 (IEV) Submission of Construction Programme for Integrated Elevated Viaduct including ramp & shifting
0 of median & road0widening 0% 27-Jan-20* 0
KD-2 (IEV) Submission of definitive design for Integrated Elevated Viaduct 0 0 0% 24-Feb-20* 0
DMRC DC-2.1.4 Yamuna Bridge 0 0 0% 0
DMRC DC-2.1.5 Balanced Cantilever Spans 0 0 0% 0
DMRC DC-2.3 Land Handover/Project Initiation 20 20 0% 30-Dec-19 20-Jan-20 314
HO- CY Handover of Land for Casting Yard, Batching Plant, office establishment and temperory land for0site work facilitation 0 100% 30-Dec-19 0
HO- VD-STR-1 Handover of Land for Stretch-1 of viaduct exclu. viaduct area of station from Ch: 00 m to Ch: 1325.51
0 m 0 100% 30-Dec-19 15
HO- VD-STR-2 Handover of Land for Stretch-2 of viaduct exclu. viaduct area of station from Ch: 1466.13 m to Ch:
0 2798.5 m 0 100% 30-Dec-19 0
HO- VD-STR-3 Handover of Land for Stretch-3 of viaduct exclu. viaduct area of station from Ch: 2939.15 m to Ch:
0 3602.02 m 0 0% 10-Jan-20 20
HO- VD-STR-4 Handover of Land for Stretch-4 of viaduct exclu. viaduct area of station from Ch: 3742.69 m to Ch:
0 4844.14 m 0 0% 10-Jan-20 20
HO- VD-STR-5 Handover of Land for Stretch-5 of viaduct exclu. viaduct area of station from Ch: 4984.79 m to Ch:
0 6532.44 m 0 0% 05-Jan-20 46
HO- VD-STR-6 Handover of Land for Stretch-6 of viaduct exclu. viaduct area of station from Ch: 6673.09 m to Ch:
0 7898.63 m 0 0% 15-Jan-20 36

Page 1 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

HO- VD-STR-7 Handover of Land for Stretch-7 of viaduct exclu. viaduct area of station from Ch: 8039.28 m to Ch:
0 8996.16 m 0 0% 15-Jan-20 49
HO- VD-STR-8 Handover of Land for Stretch-8 of viaduct exclu. viaduct area of station from Ch: 9136.81 m to Ch:
0 10470.73 m 0 0% 15-Jan-20 49
HO- VD-STR-9 Handover of Land for Stretch-9 of viaduct exclu. viaduct area of station from Ch: 10611.38 m to Ch:
0 12098.41 m 0 0% 15-Jan-20 49
HO-ST1-JMS Handover of Complete land for Jharoda Majra @ Ch Start: 8996.16m 0 0 0% 05-Jan-20 25
HO-ST2-BRS Handover of Complete land for Borari @ Ch Start: 10470.73m 0 0 0% 05-Jan-20 27
HO-ST3-YVS Handover of Complete land for Yamuna Vihar @ ChStart: 1325.51m 0 0 0% 15-Jan-20 17
HO-ST4-BJS Handover of Complete land for Bhajanpura @ Ch Start: 2798.5m 0 0 0% 15-Jan-20 58
HO-ST5-KKS Handover of Complete land for Khajuri Khas @ Ch Start: 3602.4m 0 0 0% 15-Jan-20 58
HO-ST6-SVS Handover of Complete land for Sonia Vihar @ Ch Start: 4844.14m 0 0 0% 20-Jan-20 283
HO-ST7-SGS Handover of Complete land for Soorghat @ Ch Start: 6532.44m 0 0 0% 20-Jan-20 314
HO-ST8-JTS Handover of Complete land for Jagatpura @ Ch Start: 7898.63m 0 0 0% 20-Jan-20 314
HO-ST8-YRB Handover of Land for Yamuna Bridge 0 0 0% 05-Jan-20 2
DMRC DC-2.2 Preliminary Work & Mobilization 145 145 0% 30-Dec-19 19-Jul-20 405

DMRC DC-2.2.1 Initial Works 135 135 0% 05-Jan-20 22-May-20 25


SIW Soil Investigation Works-Confirmatory Bore Holes 120 120 0% 20-Jan-20 22-May-20 25
SURVEY REF. Receipt of Permanent Benchmarks, Survey points, Data Reference points 0 0 0% 05-Jan-20 05-Jan-20 40
TS Topographic Survey 90 90 0% 20-Jan-20 21-Apr-20 25
DMRC DC-2.2.4 Utility Identification and Diversion (Chartered & Unchartered) 123 123 0% 28-Jan-20 19-Jul-20 5
DMRC DC-2.2.4.1 First 3.7 km stretch (Ch: 0m P-1 to Ch: 3742.69 m Khajuri Khas Station End) 171 171 0% 28-Jan-20 19-Jul-20 5
UT-RH1-A Approval of Utility Diversion by DMRC 40 40 0% 04-Feb-20 16-Mar-20 5
UT-RH1-D Utility Diversion as per approved plan 150 150 0% 18-Feb-20 19-Jul-20 5
UT-RH1-S Utility Identification and Submission of diversion plan 40 40 0% 28-Jan-20 08-Mar-20 5
DMRC DC-2.2.4.2 Next 4.2 km stretch (Ch: 3742.69 m Khajuri Khas Station End to Ch: 8039.28 m Jagatpura Station42
End) 42 0% 08-Mar-20 20-Apr-20 6
UT-RH2-A Approval of Utility Diversion by DMRC 35 35 0% 16-Mar-20 20-Apr-20 6
UT-RH2-S Utility Identification and Submission of diversion plan 35 35 0% 08-Mar-20 13-Apr-20 6
DMRC DC-2.2.4.3 Balance Stretch including 2 balance stations (Ch: 8039.28 m to Ch: 12098.41 m Project End) 0 0 0% 0
DMRC DC-2.2.5 Traffic Management 104 104 0% 15-Jan-20 30-Apr-20 0
DMRC DC-2.2.5.1 First 3.7 km stretch (Ch: 0m P-1 to Ch: 3742.69 m Khajuri Khas Station End) 45 45 0% 15-Jan-20 01-Mar-20 0
TD-RH1 Traffic Diversion 30 30 0% 31-Jan-20 01-Mar-20 0
TD-RH1-A Approval of Traffic Diversion Plan 14 14 0% 30-Jan-20 13-Feb-20 0
TD-RH1-S Submission of Traffic Diversion Plan 14 14 0% 15-Jan-20 30-Jan-20 -1
DMRC DC-2.2.5.2 Next 4.2 km stretch (Ch: 3742.69 m Khajuri Khas Station End to Ch: 8039.28 m Jagatpura Station38
End) 38 0% 30-Jan-20 08-Mar-20 -1
TD-RH2 Traffic Diversion 25 25 0% 12-Feb-20 08-Mar-20 -1

Page 2 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

TD-RH2-A Approval of Traffic Diversion Plan 12 12 0% 11-Feb-20 23-Feb-20 -1


TD-RH2-S Submission of Traffic Diversion Plan 12 12 0% 30-Jan-20 11-Feb-20 -1
DMRC DC-2.2.5.3 Balance Stretch including 2 balance stations (Ch: 8039.28 m to Ch: 12098.41 m Project End) 78 78 0% 11-Feb-20 30-Apr-20 0
TD-RH3 Traffic Diversion 70 70 0% 19-Feb-20 30-Apr-20 0
TD-RH3-A Approval of Traffic Diversion Plan 30 30 0% 18-Feb-20 20-Mar-20 0
TD-RH3-S Submission of Traffic Diversion Plan 30 30 0% 11-Feb-20 13-Mar-20 0
DMRC DC-2.2.6 Tree Cutting/Transplantation 125 125 0% 05-Jan-20 12-May-20 225
DMRC DC-2.2.6.4 Casting Yard 31 31 0% 05-Jan-20 06-Feb-20 44
Tree-CY-A Permission for Tree Cutting/transplantation 7 7 0% 09-Jan-20 16-Jan-20 44
Tree-CY-Cut Tree Cutting/transplantation 20 20 0% 16-Jan-20 06-Feb-20 44
Tree-CY-ID-S Identification of Tree's in Work Area & Intimation to Employer 4 4 0% 05-Jan-20 09-Jan-20 44
DMRC DC-2.2.6.1 First 3.7 km stretch (Ch: 0m P-1 to Ch: 3742.69 m Khajuri Khas Station End) 40 40 0% 04-Feb-20 16-Mar-20 6
Tree-RH1-A Permission for Tree Cutting/transplantation 7 7 0% 11-Feb-20 18-Feb-20 6
Tree-RH1-Cut Tree Cutting/transplantation 26 26 0% 18-Feb-20 16-Mar-20 6
Tree-RH1-ID-S Identification of Tree's in Work Area & Intimation to Employer 7 7 0% 04-Feb-20 11-Feb-20 6
DMRC DC-2.2.6.2 Next 4.2 km stretch (Ch: 3742.69 m Khajuri Khas Station End to Ch: 8039.28 m Jagatpura Station40
End) 40 0% 11-Feb-20 23-Mar-20 109
Tree-RH2-A Permission for Tree Cutting/transplantation 7 7 0% 18-Feb-20 25-Feb-20 109
Tree-RH2-Cut Tree Cutting/transplantation 26 26 0% 25-Feb-20 23-Mar-20 109
Tree-RH2-ID-S Identification of Tree's in Work Area & Intimation to Employer 7 7 0% 11-Feb-20 18-Feb-20 109
DMRC DC-2.2.6.3 Balance Stretch including 2 balance stations (Ch: 8039.28 m to Ch: 12098.41 m Project End) 82 82 0% 18-Feb-20 12-May-20 225
Tree-RH3-A Permission for Tree Cutting/transplantation 7 7 0% 04-Mar-20 12-Mar-20 225
Tree-RH3-Cut Tree Cutting/transplantation 60 60 0% 12-Mar-20 12-May-20 225
Tree-RH3-ID-S Identification of Tree's in Work Area & Intimation to Employer 15 15 0% 18-Feb-20 04-Mar-20 225
DMRC DC-2.2.7 Existing Building/Civil Structure Demolition 64 64 0% 04-Feb-20 09-Apr-20 177
DMRC DC-2.2.7.1 First 3.7 km stretch (Ch: 0m P-1 to Ch: 3742.69 m Khajuri Khas Station End) 60 60 0% 04-Feb-20 05-Apr-20 1
ECS-RH1-A Permission for Existing Building Demolition 15 15 0% 19-Feb-20 05-Mar-20 1
ECS-RH1-DEM Demolition of Existing Building 30 30 0% 05-Mar-20 05-Apr-20 1
ECS-RH1-ID-S Identification of Existing Building in Work Area & Intimation to Employer 15 15 0% 04-Feb-20 19-Feb-20 1
DMRC DC-2.2.7.2 Next 4.2 km stretch (Ch: 3742.69 m Khajuri Khas Station End to Ch: 8039.28 m Jagatpura Station49
End) 49 0% 19-Feb-20 09-Apr-20 92
ECS-RH2-A Permission for Existing Building Demolition 12 12 0% 02-Mar-20 15-Mar-20 92
ECS-RH2-DEM Demolition of Existing Building 25 25 0% 15-Mar-20 09-Apr-20 92
ECS-RH2-ID-S Identification of Existing Building in Work Area & Intimation to Employer 12 12 0% 19-Feb-20 02-Mar-20 92
DMRC DC-2.2.7.3 Balance Stretch including 2 balance stations (Ch: 8039.28 m to Ch: 12098.41 m Project End) 30 30 0% 02-Mar-20 02-Apr-20 184

Page 3 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

ECS-RH3-ID-S Identification of Existing Building in Work Area & Intimation to Employer 30 30 0% 02-Mar-20 02-Apr-20 184
DMRC DC-2.2.2 Contractual Submission and Approvals 141 141 0% 30-Dec-19 23-May-20 610
DMRC DC-2.2.2.1 Submission of Construction Work Programme 106 106 0% 30-Dec-19 17-Apr-20 645
Acheive-KD-1 (V) Acheivement of KD-1 of Viaduct 0 0 0% 26-Jan-20 -1
DWP-S Submission of Detailed Work Program 60 60 0% 16-Feb-20 17-Apr-20 645
IEV-Const Prog Submission of Construction Programme for Integrated Elevated Viaduct including ramp and shifting
26 of meadian and
26 road 0% 30-Dec-19 26-Jan-20 -1
IEV-KD-1 Achievement of KD-1 of IEVD 0 0 0% 26-Jan-20 -1
IWP-A Approval of Initial Work Program 20 20 0% 27-Jan-20 16-Feb-20 645
IWP-S Submission of Construction Programme 26 26 0% 30-Dec-19 26-Jan-20 -1
DMRC DC-2.2.2.2 Other Contractual Submissions 141 141 0% 30-Dec-19 23-May-20 70
OCS-MD-A Approval of Mix Design 10 10 0% 31-Jan-20 10-Feb-20 8
OCS-MD-S Submission of Mix Design 30 30 0% 30-Dec-19 31-Jan-20 8
OCS-MS-A Method statements approval 120 120 0% 21-Jan-20 23-May-20 70
OCS-MS-S Method statements submissions 120 120 0% 30-Dec-19 02-May-20 70
OCS-Org. Chart-S Submission of Organization chart 20 20 0% 30-Dec-19 20-Jan-20 87
OCS-PQP-A Approval of Project Quality Plan 10 10 0% 29-Jan-20 08-Feb-20 69
OCS-PQP-S Submission of Project Quality Plan 28 28 0% 30-Dec-19 29-Jan-20 69
OCS-SHE-A Approval of SHE plan 10 10 0% 29-Jan-20 08-Feb-20 10
OCS-SHE-S Submission of SHE plan 28 28 0% 30-Dec-19 29-Jan-20 10
DMRC DC-2.2.3 Casting Yard Establishment 123 123 0% 30-Dec-19 05-May-20 215
CY-SO Establishing Site Office 30 30 0% 30-Dec-19 31-Jan-20 15
DMRC DC-2.2.3.1 Enabling Structures-Design 95 95 0% 07-Jan-20 13-Apr-20 35
Design-ES-Layout-A Approval of Casting yard layout drawing 10 10 0% 22-Jan-20 02-Feb-20 18
Design-ES-Layout-S Submission of Casting yard layout drawing 15 15 0% 07-Jan-20 22-Jan-20 18
Design-ES-SUBSTR-AApproval of Substructure mould drawings 10 10 0% 28-Mar-20 07-Apr-20 41
Design-ES-SUBSTR-SSubmission of Substructure mould drawing 20 20 0% 07-Mar-20 28-Mar-20 41
Design-ES-SUPSTR-AApproval of Superstructure mould drawings 10 10 0% 28-Jan-20 07-Feb-20 0
Design-ES-SUPSTR-SSubmission of Superstructure mould drawing 20 20 0% 07-Jan-20 28-Jan-20 0
Design-ES-SUPSTR-TFA
Submission of Traveller Formwork Design & Drawing 20 20 0% 24-Mar-20 13-Apr-20 0
DMRC DC-2.2.3.2 Casting Yard-Set up 123 123 0% 30-Dec-19 05-May-20 116
Acheive-KD-2 (ST) Acheivement of KD-2 of Stations 0 0 0% 23-Mar-20 0
Acheive-KD-2 (V) Acheivement of KD-2 of Viaduct 0 0 0% 24-Feb-20 0
Acheive-KD-4 (V) Acheivement of KD-4 of Viaduct 0 0 0% 23-Mar-20 0

Page 4 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

CY-Setup-1st Form-CACompletion of 1st Formwork for precast elements i.e. Cross arm, pie Girder, Cross beam for Engineer's
1 approval 1 0% 22-Mar-20 23-Mar-20 0
CY-Setup-AD Area Development 77 77 0% 30-Dec-19 19-Mar-20 0
CY-Setup-BP1 Establishment and Commisioning of 1st Batching Plant (production of 1st batch of concrete) 45 45 0% 09-Jan-20 24-Feb-20 0
CY-Setup-Gantry Erec Foundation and erection of Gantrys 53 53 0% 02-Feb-20 27-Mar-20 18
CY-Setup-Mould-CA Setting up of balance Cross Arms and mould 25 25 0% 28-Mar-20 22-Apr-20 113
CY-Setup-Mould-RG Setting up of balance Station-Rec Girder and mould 45 45 0% 18-Mar-20 03-May-20 31
CY-Setup-UG-1st FormCompletion of first formwork for U Girder element of production line for Engineers inspection and
1 approval 1 0% 22-Mar-20 23-Mar-20 0
CY-Setup-UG-1st RH Setting up of 1st row of Casting Bed of U Girders/Cross arm, pie Girder 18 18 0% 03-Mar-20 22-Mar-20 0
CY-Setup-UG-Bal. RH Setting up of balance rows of Casting Bed and mould/formwork of U Girders 35 35 0% 30-Mar-20 05-May-20 116
DMRC DC-2.2.3.3 Mould Fabrication 84 84 0% 07-Feb-20 03-May-20 217
CY-MouldFab-CA Station-Cross Arms 20 20 0% 02-Mar-20 23-Mar-20 13
CY-MouldFab-IG PSC I Girders 50 50 0% 07-Feb-20 29-Mar-20 251
CY-MouldFab-PB Portal Beam 10 10 0% 13-Mar-20 23-Mar-20 13
CY-MouldFab-PC Pier Cap 60 60 0% 07-Feb-20 08-Apr-20 0
CY-MouldFab-RG Station-Cross Rec girder 60 60 0% 02-Mar-20 03-May-20 31
CY-MouldFab-TG PSC-T- Girders 60 60 0% 07-Feb-20 08-Apr-20 0
CY-MouldFab-UG-1 U Girder-first line and stations Cross arms, rec-girder 1st formwork 25 25 0% 07-Feb-20 03-Mar-20 0
CY-MouldFab-UG-2 U Girder-balance lines 60 60 0% 28-Feb-20 29-Apr-20 116
DMRC DC-2.8 Engineering & Design 524 524 0% 30-Dec-19 18-Jun-21 79

DMRC DC-2.8.1 Main Structures 524 524 0% 30-Dec-19 18-Jun-21 79


DMRC DC-2.8.1.1 Viaduct 499 499 0% 30-Dec-19 24-May-21 0
Acheive-KD-3 (V) KD Acheivement of KD-3 of Viaduct 0 0 0% 24-Feb-20 0
Design-V-DD-A Approval of Definitive Design 30 30 0% 01-Feb-20 02-Mar-20 0
Design-V-DD-S Submission of Definitive Design 30 30 0% 24-Jan-20 24-Feb-20 0
Design-V-GA-A Approval of General Arrangement/Layout AutoCAD Drawing 20 20 0% 04-Jan-20 24-Jan-20 0
Design-V-GA-S Submission of General Arrangement/Layout Drawing 20 20 0% 30-Dec-19 20-Jan-20 0
Design-V-GFC-A Approval of Working Drawings (GFC) 447 447 0% 22-Feb-20 24-May-21 0
Design-V-GFC-S Submission of Working Drawings (GFC) 447 447 0% 15-Feb-20 17-May-21 0
Design-V-GFC-SUP-REC
Receipt of GFCAutoCAD drawing for superstructure from DMRC 7 7 0% 30-Dec-19 07-Jan-20 0
DMRC DC-2.8.1.2 Stations 524 524 0% 30-Dec-19 18-Jun-21 -1
Acheive-KD-1 (ST) Acheivement of KD-1 of Stations 0 0 0% 24-Feb-20 0
Design-INTER-CSD-A Approval of CSD Drawings 14 14 0% 26-Feb-20 12-Mar-20 -1

Page 5 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

Design-INTER-CSD-I Interface inputs (CSD) from Employer 20 20 0% 15-Jan-20 05-Feb-20 -1


Design-INTER-CSD-S Submission of CSD Drawings 20 20 0% 19-Feb-20 11-Mar-20 -1
Design-INTER-SEM-A Approval of SEM Drawings 20 20 0% 14-Feb-20 05-Mar-20 5
Design-INTER-SEM-I Interface inputs (SEM) from Employer 12 12 0% 07-Jan-20 19-Jan-20 5
Design-INTER-SEM-S Submission of SEM Drawings 20 20 0% 07-Feb-20 27-Feb-20 5
Design-ST-DD-A Approval of Definitive Design 27 27 0% 04-Feb-20 02-Mar-20 8
Design-ST-DD-S Submission of Definitive Design 27 27 0% 28-Jan-20 24-Feb-20 0
Design-ST-GA-A Approval of General Arrangement/Layout Drawing 20 20 0% 07-Jan-20 28-Jan-20 0
Design-ST-GA-S Submission of General Arrangement/Layout Drawing 20 20 0% 30-Dec-19 20-Jan-20 0
Design-ST-GFC-A Approval of Working Drawings (GFC) 447 447 0% 19-Mar-20 18-Jun-21 -1
Design-ST-GFC-S Submission of Working Drawings (GFC) 447 447 0% 12-Mar-20 11-Jun-21 -1
DMRC DC-2.8.1.3 Integrated Elevated Viaduct 492 492 0% 30-Dec-19 17-May-21 111
IEVD-0 Receipt of GFC drawing for superstructure from DMRC 7 7 0% 30-Dec-19 07-Jan-20 0
IEVD-1 Submission of General Arrangement/Layout Drawing 20 20 0% 30-Dec-19 20-Jan-20 0
IEVD-2 Approval of General Arrangement/Layout Drawing 20 20 0% 07-Jan-20 28-Jan-20 0
IEVD-3 Submission of Definitive Design 37 37 0% 17-Jan-20 24-Feb-20 0
IEVD-3.1 KD Acheivement of KD-2 of Integrated Elevated Viaduct 0 0 0% 24-Feb-20 0
IEVD-4 Approval of Definitive Design 40 40 0% 24-Jan-20 05-Mar-20 111
IEVD-5 Submission of Working Drawings (GFC) 447 447 0% 08-Feb-20 10-May-21 111
IEVD-6 Approval of Working Drawings (GFC) 447 447 0% 15-Feb-20 17-May-21 111
DMRC DC-2.8.1.4 Yamuna River Bridge 105 105 0% 30-Dec-19 16-Apr-20 32
YRBD-0 Receipt of GFC drawing for superstructure from DMRC 7 7 0% 30-Dec-19 07-Jan-20 0
YRBD-1 Submission of General Arrangement/Layout Drawing 30 30 0% 30-Dec-19 31-Jan-20 0
YRBD-2 Approval of General Arrangement/Layout Drawing 30 30 0% 15-Jan-20 15-Feb-20 0
YRBD-3 Submission of Definitive Design 65 65 0% 31-Jan-20 06-Apr-20 0
YRBD-4 Approval of Definitive Design 60 60 0% 15-Feb-20 16-Apr-20 32
DMRC DC-2.4 Construction 98 98 0% 30-Dec-19 13-May-20 448

DMRC DC-2.4.1 Casting Yard 75 75 0% 08-Feb-20 24-Apr-20 0


CY-Setup-BP2 Establishment and Commisioning of 2nd Batching Plant 40 40 0% 25-Feb-20 06-Apr-20 0
CY-STRM-Proc. Procurement of HT Strand, Debonding Tubes etc 40 40 0% 15-Mar-20 24-Apr-20 0
CY-STRSAG Final Finalization of Prestressing Agency 35 35 0% 08-Feb-20 15-Mar-20 0
DMRC DC-2.4.2 Viaduct 60 60 0% 31-Jan-20 25-Apr-20 0

Page 6 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

DMRC DC-2.4.2.1 Standard Viaduct (Excl. Special Spans) 84 84 0% 31-Jan-20 25-Apr-20 0


DMRC DC-2.4.2.1.2 First 3.7 km stretch (Ch: 0m P-1 to Ch: 3742.69 m Khajuri Khas Station End) excluding CLC &50
IEV 50 0% 31-Jan-20 22-Mar-20 0
RH1-SB Site Barricading and preparaorty activities for Main Structure Works 50 50 0% 31-Jan-20 22-Mar-20 0
V-Test Pile Cast. Test Pile Casting (V+H) 4 locations 25 25 0% 25-Feb-20 22-Mar-20 0
V-Test Pile Loc. Finalization of Location of Test Pile By DMRC 4 locations 10 10 0% 15-Feb-20 25-Feb-20 0
50 End)
DMRC DC-2.4.2.1.4 Next 4.2 km stretch (Ch: 3742.69 m Khajuri Khas Station End to Ch: 8039.28 m Jagatpura Station 50 0% 22-Feb-20 13-Apr-20 -1
RH1-SB2 Site Barricading and preparaorty activities for Main Structure Works 50 50 0% 22-Feb-20 13-Apr-20 -1
V-Test Pile Cast.2 Test Pile Casting (V+H) 3 locations 25 25 0% 19-Mar-20 13-Apr-20 -1
V-Test Pile Loc.2 Finalization of Location of Test Pile By DMRC 3 locations 10 10 0% 08-Mar-20 19-Mar-20 -1
DMRC DC-2.4.2.1.1 Balance Stretch excluding CLC & Stations (4059.3 rmt) 50 50 0% 05-Mar-20 25-Apr-20 0
RH1-SB4 Site Barricading and preparatory activities for Main Structure Works 50 50 0% 05-Mar-20 25-Apr-20 0
V-Test Pile Loc.4 Finalization of Location of Test Pile By DMRC 4 locations 10 10 0% 21-Mar-20 31-Mar-20 0
DMRC DC-2.4.2.5 Full Access of the Viaduct 0 0 0% 0
DMRC DC-2.4.2.2 Finishing and Handing Over to Interface Contractor 0 0 0% 0
DMRC DC-2.4.2.3 Completion of Entire Work as per the Contract 0 0 0% 0
DMRC DC-2.4.6 Special Spans 65 65 0% 30-Dec-19 06-Mar-20 681
DMRC DC-2.4.6.7 Balanced Cantilever Span from P-26 to P-29 (224m) 65 65 0% 30-Dec-19 06-Mar-20 681
VD-SS-CLC10 Site Clearance & Dismantling of obstructions 15 15 0% 30-Dec-19 15-Jan-20 71
VD-SS-CLC14 Utility Trenching 15 15 0% 20-Jan-20 05-Feb-20 71
VD-SS-CLC16 Diversion of Utility 30 30 0% 05-Feb-20 06-Mar-20 681
VD-SS-CLC31 Barrication Works from P-26 to P-29 5 5 0% 15-Jan-20 20-Jan-20 71
DMRC DC-2.4.5 Integrated Elevated Viaduct 90 90 0% 30-Dec-19 02-May-20 0
DMRC DC-2.4.5.5 Stretch 2 (Ch: 1466.13 m to 2803.47 m) 90 90 0% 30-Dec-19 02-May-20 0
DMRC DC-2.4.5.5.3 Modification of Mangal Pandey Road 120 120 0% 30-Dec-19 02-May-20 0
IEV-2 Site Barricading and preparaorty activities for modification works 35 35 0% 30-Dec-19 05-Feb-20 0
IEV-3 Shifting of median and widening of roads 85 85 0% 05-Feb-20 02-May-20 0
DMRC DC-2.4.5.5.1 Intergrated Elevated Viaduct 0 0 0% 0
DMRC DC-2.4.4 Yamuna Bridge 100 100 0% 07-Jan-20 18-Apr-20 41
VD-YB-1001 Preparatory Works & Detailed Survey 10 10 0% 07-Jan-20 17-Jan-20 0
VD-YB-1003 Geotechnical Investigation from P-188 to P-196 45 45 0% 17-Jan-20 03-Mar-20 0
VD-YB-1005 Preparation & Submission of Geotechnical Investigation Reports 45 45 0% 03-Mar-20 18-Apr-20 0
VD-YB-1007 Site Clearance & Dismantling of obstructions 10 10 0% 03-Mar-20 14-Mar-20 71
VD-YB-1009 Preparatory work for piling with proper layout & benchmarks 5 5 0% 14-Mar-20 19-Mar-20 71
DMRC DC-2.4.3 Stations 73 73 0% 31-Jan-20 13-May-20 92

Page 7 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

DMRC DC-2.4.3.2 First Two Stations 73 73 0% 31-Jan-20 13-May-20 2


DMRC DC-2.4.3.2.3 Jharoda Majra 73 73 0% 31-Jan-20 13-May-20 -1
DMRC DC-2.4.3.2.3.1 Station Box Area 101 101 0% 31-Jan-20 13-May-20 -1
ST-YV-11000 Site Barricading and preparaorty activities for Main Structure Works 12 12 0% 31-Jan-20 12-Feb-20 0
ST-YV-11000.1 Casting of Test Piles & Pile Load Tests with approval from DMRC 40 40 0% 10-Feb-20 22-Mar-20 0
ST-YV-11001 Piling 50 50 0% 23-Mar-20 13-May-20 -1
DMRC DC-2.4.3.2.3.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.2.3.3 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.2.3.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.2.4 Borari 39 39 0% 01-Mar-20 23-Apr-20 16
DMRC DC-2.4.3.2.4.1 Station Box Area 52 52 0% 01-Mar-20 23-Apr-20 23
ST-BS1000 Site Barricading and preparaorty activities for Main Structure Works 12 12 0% 01-Mar-20 14-Mar-20 23
ST-BS1000.1 Casting of Tests Piles & Pile Load Tests with approval from DMRC 40 40 0% 14-Mar-20 23-Apr-20 23
DMRC DC-2.4.3.2.4.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.2.4.4 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.2.4.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.2.4.6 Acheivement of Key Date 3.1 and 4.1 0 0 0% 0
DMRC DC-2.4.3.2.4.3 Acheivement of Key Date 5.1 and 6.1 0 0 0% 0
DMRC DC-2.4.3.4 Next Three Stations 20 20 0% 08-Mar-20 03-Apr-20 120
DMRC DC-2.4.3.4.1 Yamuna Vihar 10 10 0% 22-Mar-20 03-Apr-20 41
DMRC DC-2.4.3.4.1.1 Station Box Area 12 12 0% 22-Mar-20 03-Apr-20 58
ST-KK1000 Site Barricading and preparaorty activities for Main Structure Works 12 12 0% 22-Mar-20 03-Apr-20 58
DMRC DC-2.4.3.4.1.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.4.1.3 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.4.1.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.4.2 Bhajanpura 10 10 0% 08-Mar-20 21-Mar-20 90
DMRC DC-2.4.3.4.2.1 Station Box Area 12 12 0% 08-Mar-20 21-Mar-20 126
ST-SV1000 Site Barricading and preparaorty activities for Main Structure Works 12 12 0% 08-Mar-20 21-Mar-20 126
DMRC DC-2.4.3.4.2.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.4.2.3 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.4.2.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.4.4 Khajuri Khas 10 10 0% 08-Mar-20 21-Mar-20 130
DMRC DC-2.4.3.4.4.1 Station Box Area 12 12 0% 08-Mar-20 21-Mar-20 181
ST-SG1000 Site Barricading and preparaorty activities for Main Structure Works 12 12 0% 08-Mar-20 21-Mar-20 181
DMRC DC-2.4.3.4.4.2 Entry/Exit Structure A 0 0 0% 0

Page 8 of 9 TASK filter: one month Look ahead.


© Oracle Corporation
DMRC DC-02 Initial Works Programme Classic Schedule Layout 29-Jan-20 00:17
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float
Duration Complete

DMRC DC-2.4.3.4.4.3 Entry/Exit Structure B 0 0 0% 0


DMRC DC-2.4.3.4.4.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.4.4.6 Acheivement of Key Date 3.2 and 4.2 0 0 0% 0
DMRC DC-2.4.3.4.4.4 Acheivement of Key Date 5.2 and 6.2 0 0 0% 0
DMRC DC-2.4.3.5 Balance Stations 0 0 0% 0
DMRC DC-2.4.3.5.4 Sonia Vihar 0 0 0% 0
DMRC DC-2.4.3.5.4.1 Station Box Area 0 0 0% 0
DMRC DC-2.4.3.5.4.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.5.4.3 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.5.4.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.5.3 Soorghat 0 0 0% 0
DMRC DC-2.4.3.5.3.1 Station Box Area 0 0 0% 0
DMRC DC-2.4.3.5.3.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.5.3.3 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.5.3.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.5.1 Jagatpura 0 0 0% 0
DMRC DC-2.4.3.5.1.1 Station Box Area 0 0 0% 0
DMRC DC-2.4.3.5.1.2 Entry/Exit Structure A 0 0 0% 0
DMRC DC-2.4.3.5.1.3 Entry/Exit Structure B 0 0 0% 0
DMRC DC-2.4.3.5.1.5 Ancillary Building 0 0 0% 0
DMRC DC-2.4.3.5.1.6 Acheivement of Key Date 3.3 and 4.3 0 0 0% 0
DMRC DC-2.4.3.5.1.4 Acheivement of Key Date 5.3 and 6.3 0 0 0% 0
DMRC DC-2.4.3.1 Completion of Entire Work as per the Contract 0 0 0% 0

Page 9 of 9 TASK filter: one month Look ahead.