S.S.H.

P Site , Jagdalpur (Main Building Back Filling Qty)


BOQ DETAILS
Item PARTICULARS NO. Quantity
Nos L B D
Main Building Back filling Qty
Drawing No : 2019-SSH-AU-STR-2016
Total Excavation Qty 1 x 1 71.60 64.70 4.17 19317.6084
Main Building Avg.NGL=99.60m Lvl
Excavation Required Level = 95.425

Total Excavation Depth = (99.60-95.425)=4.175m


L=66.600+5.00=71.60
B = 64.70
Deductions: Off sets -1 x 1 9.45 2.70 4.17 -106.39755
-1 x 1 7.99 5.40 4.17 -179.91882
-1 x 1 19.65 5.00 4.17 -409.7025

Lift Pit-1 Excavation(1.80m Dept) 1 x 1 4.60 4.40 1.80 36.432


L=4.60,B=4.40
Lift Pit-2 Excavation(1.80m Dept) 1 x 1 5.00 4.00 1.80 36.000
L=5.00,B=4.00

Ramp -1 Excavation(Near Grid A1) 1 x 1 25.50 5.90 2.40 361.080


Ramp -2 Excavation(Near Grid I1) 1 x 1 24.40 5.35 2.35 306.769

Total Excavation Qty in Cum = 19361.8705


Deduction Gravel filling Qty in Cum = -246.40
Deduction P.C.C Qty in Cum = -246.40
Deduction Raft R.C.C. Qty in Cum = -3698.00
Deduction Beams R.C.C. Qty in Cum = -427.00
Deduction Columns R.C.C. Qty in Cum = -209.77
Deduction Basement area = -3320.00

Back Filling (up to NGL 99.60m Height) Qty in Cum = 11214.3005


From Plinth Beam Bottom to NGL Back Filling Including 2mtr
offset from column face(101.60-0.60-99.60 = 1.40mtr Height) 6251.84

Total Back Filling Qty in Cum = 17466.1405


Add 15% Compaction = 2619.92108

Total Back Filling Qty in Cum = 20086.0616


Total Back Filling Qty in Cft = 709319.18