Project Management Assignment No:2

Q1: Let us say Nice Ltd wants to expand its business and so it is willing to invest Rs 10,00,000. The
investment is said to bring an inflow of Rs.  100,000 in first year, 250,000 in the second year, 350,000
in third year, 265,000 in fourth year and 415,000 in fifth year. Compute net present value of the
project if the minimum desired rate of return is 9%.

Q2: A project has the following activities:

Activity Time (in week) Activity Time (in week)

1-2 4 5-7 8

1-3 1 6-8 1

2-4 1 7-8 2

3-4 1 8-9 1

3-5 6 8-10 8

4-9 5 9-10 7

5-6 4

Construct the network and compute 1. TE and TL for each event 2. Float for each activity 3. Critical
path and its duration.

SUBMIT ON EMAIL

Upasana.diwan@rdias.ac.in

Last Date May 13,2020