NTPC - LOT 2 W

Sl.No. Plant Location Boiler 

1 TSTPS Talcher STPP Stage I& II Angul, Odisha BHEL

Vizag,
2 Simhadri STPP (Stage I & II) BHEL
AndhraPradesh

3 Sipat STPP (Stage -I) Bilaspur, Chhattisgarh DOOSAN

4 NTECL Vallur TPS Chennai, Tamilnadu BHEL

Durg, Bhilai,
5 NSPCL Bhilai EXP. Power Project Chhattisgarh
BHEL

6 KBUNL Muzaffarpur TPS (Stage II) Muzaffarpur, Bihar BHEL

NSPCL Rourkela PP-II Exp.Power Rourkela Steel Plant, BHEL - EPC under
7
Project Sundergarh, Orissa. Construction

NTPC - LOT 3 W

Sl.No. Plant Location Boiler 

1 Farakka-I,II&III BHEL

2 Kahalgaon-I&II BHEL

3 Korba-I,II&III BHEL

4 Unchahar-I,II&III BHEL

5 Ramagundam-I&II BHEL

6 Singrauli-I&II BHEL

7 Vindhychal-I&II BHEL

8 Rihand-I BHEL
NTPC - LOT 2 WFGD PROJECTS
Reverse Auction
Units Value of L1 (in Cr.)
L1
Without TAX. Tax incl. Tax
(2 x 500 +
Wrong value by BHEL.
4 X 500)
(2 x 500 +
GE 872.00
2 X 500)

(3 x 660) GE 702.00

(3 x 500) BHEL 904.01 1066.81

(2 x 250) BHEL 388.83 458.82

(2 x 195) MHPS 418.00

(1 x 250) THERMAX 199.00

NTPC - LOT 3 WFGD PROJECTS


Reverse Auction
Units Value of L1 (in Cr.)
L1
Without TAX. Tax incl. Tax
(3 X 200 + 2 X 500 +
L&T 1329.00
1 X 500 MW)

(4 X 210 + 3 X 500 MW) L&T only Bidder 1235.00

(3 X 200 + 3 X 500 +
BHEL 1435.00
1 X 500 MW)

(2 X 210 + 2 X 210 +
Thermax 821.00
1 X 210 MW)

(3 X 200 + 3 X 500 MW) BHEL 1299.50

(5 X 200 + 2 X 500 MW) BHEl 1275.00

(6 X 210 + 2 X 500 MW) L&T 1300.00

(2 X 500 MW) GE 620.00 732.00


Present Status (22-06-
Remarks( lac per MW)
2019)

To be Retendered to LOT
5

LOI to GE 43.60

LOI to GE 35.45

To be Retendered to LOT
60.27
5

LOI to BHEL 77.77

To be Retendered to LOT
107.18
5
To be Retendered to LOT
79.60
5

Present Status (22-06-


Remarks
2019)

to be Retendered to LOT
51.12
4
to be Retendered to LOT
52.78
4

LOI to BHEL 55.19

to be Retendered to LOT
78.19
4

LOI to BHEL 61.88

to be Retendered to LOT
63.75
4

LOI to L&T 57.52

to be Retendered to LOT
73.20
4
NTPC - LOT 5 W

Sl.No. Plant Location Boiler 

1 TSTPS Talcher STPP Stage I& II Angul, Odisha BHEL

2 NTECL Vallur TPS Chennai, Tamilnadu BHEL

3 KBUNL Muzaffarpur TPS (Stage II) Muzaffarpur, Bihar BHEL

NSPCL Rourkela PP-II Exp.Power Rourkela Steel Plant, BHEL - EPC under
4 Sundergarh, Orissa. Construction
Project

5 Sipath stage-II Bilaspur, Chhattisgarh BHEL

6 Ramagudam stage-III Ramagudam BHEL

7 Barauni stage-II, Barauni BHEL

NTPC - LOT 4 W

Sl.No. Plant Location Boiler 

1 Farakka-I,II&III BHEL

2 Kahalgaon-I&II BHEL

3 Unchahar-I,II&III BHEL

4 Singrauli-I&II BHEL

5 Rihand-I BHEL
NTPC - LOT 5 WFGD PROJECTS
Reverse Auction
Units Value of L1 (in Cr.)
L1
Without TAX. Tax incl. Tax
(2 x 500 +
TPL+ANDZ 1579.00
4 X 500)

(3 x 500) TPL+ANDZ 1143.00

(2 x 195) MHPS 570.00

(1 x 250) EPIL+WK 207.00

(2 x 250) GE 617.00

(1 x 500) EPIL+WK 277.00

2X250MW Thermax 605.00

NTPC - LOT 4 WFGD PROJECTS


Reverse Auction
Units Value of L1 (in Cr.)
L1
Without TAX. Tax incl. Tax
(3 X 200 + 2 X 500 +
MHPS 1400.00
1 X 500 MW)

(4 X 210 + 3 X 500 MW) BHEL 1571.00

(2 X 210 + 2 X 210 +
GE 828.30
1 X 210 MW)

(5 X 200 + 2 X 500 MW) PES+SPC 1207.00

(2 X 500 MW) GE 700.50


Present Status Remarks

LOI to TPL 52.63

LOI to TPL 76.20

To be Retendered to LOT 6 146.15

LOI to EPIL 82.80

To be Retendered to LOT 6 123.40

LOI to EPIL 55.40

To be Retendered to LOT 6 121.00

Present Status Remarks

LOI to MHPS 53.85

LOI to BHEL 67.14

LOI to GE 78.89

LOI to PES 60.35

To be Retendered to LOT 6 70.05


NTPC - LOT 5 W

Sl.No. Plant Location Boiler 

1 NLC NTPL Tuticorin Tuticorin BHEL

2 NLC Ghatampur GA-4 Ghatampur L&T-MHS


NTPC - LOT 5 WFGD PROJECTS
Reverse Auction
Units Value of L1 (in Cr.)
L1

(2 X 500 MW) BHEL 535.17

(3 X 660 MW) BGR+CPCEP 945.64


Present Status Remarks

L1 53.52

Retendered 94.56