Quantity Summary Sheet

25 - JAN - 2011

Q'TY
SYSTEM SIZE UNIT RAMARKS
Laboratory
HSE Building Total
Building

CON'C 20.7MPa ㎥ 24.31 23.51 47.82 LEAN

LAYING PE FILM ㎡ 323.99 313.53 637.52

LEAN ㎡ 35.31 41.74 77.05

FORMWORK F/D ㎡ 237.56 0.00 237.56

TOTAL ㎡ 272.87 0.00 272.87

D10 TON 0.370 0.370

D16 TON 3.263 3.263


RE-BAR
D20 TON 5.823 5.823

TOTAL TON 9.456 9.456


HSE Building

SYSTEM SIZE UNIT Q'TY RAMARKS

CON'C 20.7MPa ㎥ 24.31 LEAN

LAYING PE FILM ㎡ 323.99

LEAN ㎡ 35.31

FORMWORK F/D ㎡ 237.56

TOTAL ㎡ 272.87

D10 TON 0.370

D16 TON 3.263


RE-BAR
D20 TON 5.823

TOTAL TON 9.456


HSE Building 3

SYSTEM CALCULATION Q'TY


< LEAN CONCRETE >
⊙ F1
( 3.20 x 3.20 x 0.075 ) x 9 = 6.91
⊙ F2
( 3.20 x 3.20 x 0.075 ) x 2 = 1.54
CON'C ⊙ F2a

20.7MPa ( 3.20 x 3.20 x 0.075 ) x 1 = 0.77


⊙ F3
( 2.70 x 2.70 x 0.075 ) x 23 = 12.58
⊙ F4
( 2.00 x 2.00 x 0.075 ) x 8 = 2.40
⊙ F5
( 1.20 x 1.20 x 0.075 ) x 1 = 0.11

SUBTOTAL 24.31

< LAYING PE FILM >


⊙ F1
( 3.20 x 3.20 ) x 9 = 92.16
⊙ F2
( 3.20 x 3.20 ) x 2 = 20.48
⊙ F2a
LAYING PE FILM ( 3.20 x 3.20 ) x 1 = 10.24
⊙ F3
( 2.70 x 2.70 ) x 23 = 167.67
⊙ F4
( 2.00 x 2.00 ) x 8 = 32.00
⊙ F5
( 1.20 x 1.20 ) x 1 = 1.44

SUBTOTAL 323.99

< F/D >

⊙ F1

FOOT D20 ((( 3.00 - 0.15 )+ 0.40 )) * ( 3.00 / 0.20 + 1.00 )) * 2.00 * 0.00247
* 9.00 2.308
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 0.90 + 1.00 ) * 8.00 ) * 0.00247
) * 9.00 0.494

HOOF D10 ((( 0.50 + 0.40 )* 2.00 )- 0.30 )* (( 0.90 / 0.15 ) + 1.00 ) * 0.00062
) * 9.00 0.058
RE-BAR
⊙ F2

FOOT D20 ((( 3.00 - 0.15 )+ 0.40 )) * ( 3.00 / 0.20 + 1.00 )) * 2.00 * 0.00247
* 2.00 0.513
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 0.90 + 0.50 ) * 16.00 ) * 0.00247
) * 2.00 0.180
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 0.90 + 1.00 ) * 8.00 ) * 0.00247
) * 2.00 0.110

HOOF D10 ((( 0.65 + 0.65 )* 2.00 )- 0.30 )* (( 0.90 / 0.20 ) + 1.00 ) * 0.00062
) * 2.00
0.016

HOOF D10 ((( 0.40 + 0.50 )* 2.00 )- 0.30 )* (( 0.90 / 0.15 ) + 1.00 ) * 0.00062
) * 2.00 0.013
HSE Building 4

SYSTEM CALCULATION Q'TY

⊙ F2a

FOOT D20 ((( 3.00 - 0.15 )+ 0.40 )) * ( 3.00 / 0.20 + 1.00 )) * 2.00 * 0.00247
* 1.00 0.256
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 0.90 + 0.50 ) * 10.00 ) * 0.00247
) * 1.00 0.056
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 0.90 + 1.00 ) * 8.00 ) * 0.00247
) * 1.00
0.055

HOOF D10 ((( 0.60 + 0.50 )* 2.00 )- 0.30 )* (( 0.90 / 0.20 ) + 1.00 ) * 0.00062
) * 1.00 0.006

HOOF D10 ((( 0.50 + 0.40 )* 2.00 )- 0.30 )* (( 0.90 / 0.15 ) + 1.00 ) * 0.00062
) * 1.00 0.006

⊙ F3

FOOT D16 ((( 2.50 - 0.15 )+ 0.40 )) * ( 2.50 / 0.20 + 1.00 )) * 2.00 * 0.00158
* 8.00
0.938
COLUMN D20 ((( 0.50 - 0.08 + 0.36 + 1.00 + 1.00 ) * 10.00 ) * 0.00247
) * 8.00 0.549
RE-BAR
HOOF D10 ((( 0.40 + 0.50 )* 3.00 )- 0.30 )* (( 1.00 / 0.15 ) + 1.00 ) * 0.00062
) * 8.00 0.091

⊙ F4

FOOT D16 ((( 1.80 - 0.15 )+ 0.40 )) * ( 1.80 / 0.20 + 1.00 )) * 2.00 * 0.00247
* 23.00
2.325
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 0.90 + 1.00 ) * 12.00 ) * 0.00158
) * 23.00
1.214

HOOF D10 ((( 0.60 + 0.65 )* 2.00 )- 0.30 )* (( 0.90 / 0.20 ) + 1.00 ) * 0.00062
) * 23.00
0.171

⊙ F5

FOOT D20 ((( 1.00 - 0.15 )+ 0.40 )) * ( 1.00 / 0.20 + 1.00 )) * 2.00 * 0.00247
* 1.00
0.037
COLUMN D20 ((( 0.60 - 0.08 + 0.36 + 1.10 + 0.50 ) * 8.00 ) * 0.00247
) * 1.00 0.049

HOOF D10 ((( 0.55 + 0.50 )* 2.00 )- 0.30 )* (( 1.10 / 0.15 ) + 0.50 ) * 0.00062
) * 1.00 0.009

SUBTOTAL 9.456
D10 0.370
D16 3.263
D20 5.823
TOTAL 9.456

< LEAN CONCRETE >


⊙ F1
( ( 3.20 + 3.20 ) * 2 ) * 0.075 * 9.00 = 8.64
⊙ F2
( ( 3.20 + 3.20 ) * 2 ) * 0.075 * 2.00 = 1.92
⊙ F2a
FORMWORK
( ( 3.20 + 3.20 ) * 2 ) * 0.075 * 1.00 = 0.96
⊙ F3
( ( 2.70 + 2.70 ) * 2 ) * 0.075 * 23.00 = 18.63
⊙ F4
( ( 2.00 + 2.00 ) * 2 ) * 0.075 * 8.00 = 4.80
⊙ F5
( ( 1.20 + 1.20 ) * 2 ) * 0.075 * 1.00 = 0.36

SUBTOTAL 35.31
HSE Building 5

SYSTEM CALCULATION Q'TY

< F/D CONCRETE >


⊙ F1
( ( 3.00 + 3.00 ) * 2 ) * 0.60 * 9.00 = 64.80
⊙ F2
( ( 3.00 + 3.00 ) * 2 ) * 0.600 * 2.00 = 14.40
⊙ F2a
FORMWORK
( ( 3.00 + 3.00 ) * 2 ) * 0.600 * 1.00 = 7.20
⊙ F3
( ( 2.50 + 2.50 ) * 2 ) * 0.500 * 23.00 = 115.00
⊙ F4
( ( 1.80 + 1.80 ) * 2 ) * 0.600 * 8.00 = 34.56
⊙ F5
( ( 1.00 + 1.00 ) * 2 ) * 0.400 * 1.00 = 1.60

SUBTOTAL 237.56
TOTAL 272.87
Laboratory Building

SYSTEM SIZE UNIT Q'TY RAMARKS

CON'C 20.7MPa ㎥ 23.51 LEAN

LAYING PE FILM ㎡ 313.53

FORMWORK LEAN ㎡ 41.74


Laboratory Building 7

SYSTEM CALCULATION Q'TY

< LEAN CONCRETE >

⊙ F1

( 3.70 x 3.70 x 0.075 ) x 15 = 15.40


CON'C
20.7MPa ⊙ F2

( 3.20 x 3.20 x 0.075 ) x 10 = 7.68

⊙ F3

( 1.70 x 1.70 x 0.075 ) x 2 = 0.43

SUBTOTAL 23.51

< LEAN CONCRETE >

⊙ F1

( 3.70 x 3.70 ) x 15 = 205.35

LAYING PE FILM ⊙ F2

( 3.20 x 3.20 ) x 10 = 102.40

⊙ F3

( 1.70 x 1.70 ) x 2 = 5.78

SUBTOTAL 313.53

< LEAN CONCRETE >


⊙ F1
( ( 3.50 x 3.50 ) * 2 ) * 0.075 * 15.00 = 27.56
FORMWORK
⊙ F2
( ( 3.00 x 3.00 ) * 2 ) * 0.075 * 10.00 = 13.50
⊙ F3
( ( 1.50 x 1.50 ) * 2 ) * 0.075 * 2.00 = 0.68

SUBTOTAL 41.74