113 MW Confidence Power Rangpur Ltd.

Date 31.05.20
Current & Pending Maintenance Work Request
Requested By: Md.Nawsher Alam
SL No Request Date Equipment Name Scope R/H Description of Work Request Shift Remarks/ Status Maintenance
person
Engine Side
HFO booster module auto back wash filter again DP came from
1 30.05.20 HFO Booste(1-5) MM B side need to clean N Done

2 30.05.20 E-07 MM LO leakage from intermediate gear lubricating line B bank N Done Jahangir

Turbine & Boiler Side

Pending Works
1 27.05.20 Scada 03 EM After thundering SCADA 03 programme could not load D Done RR
2 28.05.20 HFO Sep.03 EM/MM Water block solenoid problem need to check D Done Ripon
3 23.05.20 E#15,14 EM /MM HT PID not working properly again. N Ongoing RR
4 25.05.20 HFO Serves tank MM Level gauge rope got broken D
5 21.05.20 Control Room Admin Printer black cartridge is very low D Urgent
EM & Rain water dropping on top of alternator and shaft from Roof
6 21.05.20 STG D Urgent
MM top
7 22.05.20 STG CR EM Mobile phone network problem at STG control room D Urgent
8 18.05.20 EGB 10-16 EM Soot blowing status is not showing in DCS N On-going
9 12.05.20 STG 1 EM Woodward control panel showing incorrect date D

10 20.03.20 STG-2 MM High speed coupling side oil leaking and gearbox blind plug oil C
leaking.

11 10.05.20 Sub-station EM Grid voltage 138KV,tap position 1 but LV side voltage is 11.6 - N
11.7 kv which may cause for STG trip. Need to check
Spare not available

1 19.05.20 EGB-4&5 MM EGB# 4&5 Soot blowing drain valve steam passing at closed N
position.
2 16.05.20 EGB #12,13 MM Soot blowing drain line steam passing at closed position N

3 17.05.20 Hydrophore Pump-01 MM Hydrophore pump-01 in WTP has abnormal sound and water N
leakage increased.
4 16.05.20 STG Hall MM STG-1 Inlet steam 8' valve gland packing leakage D
2 28.05.20 E-03 EM Start air solenoid again air leakage D ongoing RR
5 17.05.20 EGB & STG EM Need Emergency DC lighting for Turbine area N
6 17.05.20 EGB# 1-16 EM Lighting required for EGB D

7 18.05.20 EGB 16 MM EGB #16 Soot blowing drain valve steam passing at closed N
position
8 16.05.20 Turbine EM Need Emergency DC light for turbine area D
9 16.05.20 STG Hall EM North side light is blinking continuously N
10 15.05.20 E#03 EM JW preheating system indication lamp not working. N Done
Soot blowing drain line pneumatic valve steam passing at
11 15.05.20 EGB 10,11 MM/ EM N
closed position.
12 15.05.20 STG-01 EM Generator RMS panel light faulty D
13 14.05.20 Control air module -02 EM Control air module-02 dryer fan not working. N Ongoing RR
Alternator generating voltage getting high. Previously worked
14 10.05.20 STG 1 EM by EM, Need to check again. N

15 14.05.20 STG & EGB EM Auxiliary consumption Kwh data showing different in DCS and D
STG LV room multifunction meter.
SOOT BLOWING DRAIN LINE PNEUMATIC VALVE FEEDBACK
16 12.05.20 EGB 6,7 & 10,11 EM N
PROBLEM
Needle valve closed but steam passing through it from HP
17 12.02.20 HP Drum# 01-09 MM Drum manual glass level indicator, the glass indicator tubes A
also found broken.
18 08.04.20 EGB-14 EM /MM Soot blower motor burnt (14.3) D
STG-2 hot well level Controller showing abnormal data
19 07.03.20 STG-02 EM /MM C
(High/Low value alarm)
Impeller
20 29.03.20 EGB-03 & 10 MM Soot blower fan motor abnormal vibration N
problem
21 12.03.20 EGB-09 MM Superheater pneumatic vent valve body cracked. B
22 25.11.19 STG - 01 MM Ejector drain steam trap defective B
23 23.02.20 E # 10 MM TC washing line leakage inside cover in B-bank A
24 25.10.19 E - 02, 09 MM HFO C/O pump pressure gauge faulty B
25 09.07.19 E # 14-16 MM C/A Drain line hose pipe missing from cooler side. A Waiting for RR Urgent
Modification & Additional works
1 16.04.20 1 KL pump MM 1 KL pump need to support from rain water D
Both STG's present working hour needs to be matched with
2 19.05.20 STG-1&2 EM D
actual running hour.

3 15.03.20 Aux Boiler MM Bellow Feed water tank for condense operating v/v need A Urgent
ladder system
4 19.01.20 EGB-08 EM/MM Soot blower fan huge sound & vibration. A
5 04.02.20 FTP MM All TDM Need to proper support by welding A
6 22.02.20 All (9nos) HP Drum MM All (9nos) HP drum Vent Valve need to be prolonged. A
Today's Additional works
1
113 MW Confidence Power Rangpur Ltd.
Date 01.06.20
Current & Pending Maintenance Work Request
Requested By: Md.Nawsher Alam
Maintenance
SL No Request Date Equipment Name Scope R/H Description of Work Request Shift Remarks/ Status
person
Engine Side
1 31.05.20 E-3 MM A Bank side waste fuel line jam D Done Motiur
2 31.05.20 E-13 MM 6A cyl.tem 456 at 100% load need to check N Done Akter
3 31.05.20 E-07,11 MM TC wash inlet line hose pipe gasket damage D Done Motiur
4 31.05.20 E-14 MM TC wash drain pot got jam D Done Motiur
5 31.05.20 HFO booster -11 EM/MM Several time low level in mixing tank alarm came. N Done Akter
6 31.05.20 WTP EM/MM Smoke came from Fire pump shaft gland during running. Need D Done Akter
to check
7 31.05.20 E-02 EM EMCC -02 Ventilation fan burnt out N Done Rana
8 31.05.20 E-06,15 EM Exh.back pressure sensor showing wrong value N Done Rana

9 31.05.20 PHB-02 VFD EM VFD-09(1.2),10(1.2),11(1.2),12(2),13(2),15(2) found trip N Done Rana


condition.Need to check.
10 31.05.20 HFO sep-04 EM Emergency stop alarm came in various time. N Done Rana
11

Turbine & Boiler Side


1 31.05.20 LP drum 1&2 MM Safety valve of LP Drum 1&2 need to free to operate N Done Ashraf
2 31.05.20 HP drum -08 MM CBD pneumatic valve closed but water passing through it N

3 31.05.20 HPFWP1_1(unit-1) EM VFD showing Thermal Motor Protection alarm. Need to work N Done Rana
there ungent
Pending Works
1 23.05.20 E#15,14 EM /MM HT PID not working properly again. N Ongoing RR
2 28.05.20 E-03 EM Start air solenoid again air leakage D ongoing RR
3 14.05.20 Control air module -02 EM Control air module-02 dryer fan not working. N Ongoing RR
4 31.05.20 SCADA-02 RR Screen got blank in several times D RR
5 31.05.20 SCADA RR Real time and server time is not same. Need to adjust. D RR
6 25.05.20 HFO Serves tank MM Level gauge rope got broken D
7 21.05.20 Control Room Admin Printer black cartridge is very low D Urgent
8 21.05.20 STG EM & Rain water dropping on top of alternator and shaft from Roof D Urgent
MM top
9 22.05.20 STG CR EM Mobile phone network problem at STG control room D Urgent
10 18.05.20 EGB 10-16 EM Soot blowing status is not showing in DCS N On-going
11 12.05.20 STG 1 EM Woodward control panel showing incorrect date D

12 20.03.20 STG-2 MM High speed coupling side oil leaking and gearbox blind plug oil C
leaking.

13 10.05.20 Sub-station EM Grid voltage 138KV,tap position 1 but LV side voltage is 11.6 - N
11.7 kv which may cause for STG trip. Need to check
Spare not available
EGB# 4&5 Soot blowing drain valve steam passing at closed
1 19.05.20 EGB-4&5 MM position. N
2 16.05.20 EGB #12,13 MM Soot blowing drain line steam passing at closed position N
3 17.05.20 Hydrophore Pump-01 MM Hydrophore pump-01 in WTP has abnormal sound and water N
leakage increased.
4 16.05.20 STG Hall MM STG-1 Inlet steam 8' valve gland packing leakage D
5 17.05.20 EGB & STG EM Need Emergency DC lighting for Turbine area N
6 17.05.20 EGB# 1-16 EM Lighting required for EGB D
7 18.05.20 EGB 16 MM EGB #16 Soot blowing drain valve steam passing at closed N
position
8 16.05.20 Turbine EM Need Emergency DC light for turbine area D
9 16.05.20 STG Hall EM North side light is blinking continuously N
10 15.05.20 EGB 10,11 MM/ EM Soot blowing drain line pneumatic valve steam passing at N
closed position.
11 15.05.20 STG-01 EM Generator RMS panel light faulty D
Alternator generating voltage getting high. Previously worked
12 10.05.20 STG 1 EM by EM, Need to check again. N
Auxiliary consumption Kwh data showing different in DCS and
13 14.05.20 STG & EGB EM STG LV room multifunction meter. D

14 12.05.20 EGB 6,7 & 10,11 EM SOOT BLOWING DRAIN LINE PNEUMATIC VALVE FEEDBACK N
PROBLEM
Needle valve closed but steam passing through it from HP
15 12.02.20 HP Drum# 01-09 MM Drum manual glass level indicator, the glass indicator tubes A
also found broken.
16 08.04.20 EGB-14 EM /MM Soot blower motor burnt (14.3) D
17 07.03.20 STG-02 EM /MM STG-2 hot well level Controller showing abnormal data C
(High/Low value alarm)
18 29.03.20 EGB-03 & 10 MM Soot blower fan motor abnormal vibration N Impeller
problem
19 12.03.20 EGB-09 MM Superheater pneumatic vent valve body cracked. B
20 25.11.19 STG - 01 MM Ejector drain steam trap defective B
21 23.02.20 E # 10 MM TC washing line leakage inside cover in B-bank A
22 25.10.19 E - 02, 09 MM HFO C/O pump pressure gauge faulty B
23 09.07.19 E # 14-16 MM C/A Drain line hose pipe missing from cooler side. A Waiting for RR Urgent
Modification & Additional works
1 16.04.20 1 KL pump MM 1 KL pump need to support from rain water D
2 19.05.20 STG-1&2 EM Both STG's present working hour needs to be matched with D
actual running hour.
3 19.01.20 EGB-08 EM/MM Soot blower fan huge sound & vibration. A
4 04.02.20 FTP MM All TDM Need to proper support by welding A
5 22.02.20 All (9nos) HP Drum MM All (9nos) HP drum Vent Valve need to be prolonged. A
Today's Additional works
1
113 MW Confidence Power Rangpur Ltd
Date 02.06.20
Current & Pending Maintenance Work Request
Requested By: Md.Nawsher Alam
SL No Request Date Equipment Name Scope R/H

Engine Side
1 01.06.20 E-10 & 12 Control air MM

2 01.06.20 Power Tx. 01 & 02 EM


Turbine & Boiler Side
1 31.05.20 HP drum -08 MM
Pending Works

Spare not available


1 19.05.20 EGB-4&5 MM
2 16.05.20 EGB #12,13 MM
3 17.05.20 Hydrophore Pump-01 MM
4 16.05.20 STG Hall MM
5 18.05.20 EGB 16 MM

6 15.05.20 EGB 10,11 MM

7 12.02.20 HP Drum# 01-09 MM


8 29.03.20 EGB-03 & 10 MM
9 12.03.20 EGB-09 MM
10 25.11.19 STG - 01 MM
11 23.02.20 E # 10 MM
12 25.10.19 E - 02, 09 MM
13 09.07.19 E # 14-16 MM
Modification & Additional works
1 16.04.20 1 KL pump MM
2 04.02.20 FTP MM
3 22.02.20 All (9nos) HP Drum MM
113 MW Confidence Power Rangpur Ltd.
Current & Pending Maintenance Work Request
Requested By: Md.Nawsher Alam
Description of Work Request Shift Remarks/ Status

Engine Side
Control air module Regulator gasket leakage.Safety valve air leakae N
(E-12)
Power Tx. 01 & 02 silica gel need to change N
Turbine & Boiler Side
CBD pneumatic valve closed but water passing through it N
Pending Works

Spare not available


EGB # 4&5 Soot blowing drain valve steam passing at closed
N
position.
Soot blowing drain line steam passing at closed position N
Hydrophore pump-01 in WTP has abnormal sound and water N
leakage increased.
STG-1 Inlet steam 8' valve gland packing leakage D
EGB #16 Soot blowing drain valve steam passing at closed position N
Soot blowing drain line pneumatic valve steam passing at closed N
position.
Needle valve closed but steam passing through it from HP Drum
manual glass level indicator, the glass indicator tubes also found A
broken.
Soot blower fan motor abnormal vibration N Impeller problem
Superheater pneumatic vent valve body cracked. B
Ejector drain steam trap defective B
TC washing line leakage inside cover in B-bank A
HFO C/O pump pressure gauge faulty B
C/A Drain line hose pipe missing from cooler side. A Waiting for RR
Modification & Additional works
1 KL pump need to support from rain water D
All TDM Need to proper support by welding A
All (9nos) HP drum Vent Valve need to be prolonged. A
Maintenance
person

Urgent
113 MW Confidence Power Rangpur Ltd.
Date 02.06.20
Current & Pending Maintenance Work Request
Requested By: Md.Nawsher Alam
Maintenance
SL No Request Date Equipment Name Scope R/H Description of Work Request Shift Remarks/ Status
person
Engine Side
1 01.06.20 E-10 & 12 Control air MM Control air module Regulator gasket leakage.Safety valve air leakae N Done Akter
(E-12)

Turbine & Boiler Side


1 31.05.20 HP drum -08 MM CBD pneumatic valve closed but water passing through it N Done Ashraf
Pending Works
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 03.06.20
Requested By: Md.Nawsher Alam

Request Maintenance
SL No Date Equipment Name Scope R/H Description of Work Request Shift Remarks/ Status person
Engine Side
1 03.06.20 E # 09 MM A Bank side waste fuel line jam D Done Motiur
2 06.06.20 E-13 EM/MM C/A PID doesn’t work properly LO & CA temp.high N
3 02.06.20 E-15 EM HT PID not working properly again. N
4 02.06.20 E # 6,13 & 16 EM Exh. Back pressure value abnormal N
5 02.06.20 HFO sep.02 EM PLC Card have no power N Done Rana
Turbine & Boiler Side
1 03.06.20 EGB # 03 & 12 MM Exh. Back pressure found of EGB# 03 & 12 (252 & 241 mm WC respectively) need to Water clean manually D

2 03.02.20 Soot blowing unit MM steam pipe line elbow joint body cracked and huge steam leak aging. Need to work there with Urgency. N Done Ashraf
2_2(EGB-2) (M.M)

3 03.02.20 LP feed water EM Only(unit-1) is running at a time in Auto mode, though drum level is too low. N
pump(unit-1)
4 03.02.20 EGB-06 to EGB-11 EM Soot blowing command is not being processed from DCS.(E.M) N
Pending Works

Today's Additional works


1
2
3
4
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 04.06.20
Requested By: Md.Nawsher Alam

Request Equipment Remarks Maintenance


SL No Date Name Scope R/H Description of Work Request Shift Status person
Engine Side
1 03.06.20 E-05 MM Water leakage from C/A Cooler outlet hose pipe D Done Motiur
2 03.06.20 E-11 EM/MM Low level of mixing tank alarm came in several times. D
Need to check.
Oil mist concentration alarm came in several times.
3 03.06.20 E-04 EM Need to check D Done

4 03.06.20 HFO sep-04 EM Input PLC card got damage D


5
6
Turbine & Boiler Side
Pneumatic valve closed but water is passing through
1 03.06.20 HP drum-03 MM it. N Done Ashraf

2 03.06.20 EGB-16 MM LP generator inlet drain line flange leakage. N Done


3 03.06.20 EGB-07 MM Heat exchanger line water leakage N Done
CBD pneumatic at top side manual valve both are
4 03.06.20 HP drum-01 MM closed but water is passing through it. N Done
Alternating voltage of STG is getting high. Several
5 03.06.20 STG EM times STG tripped due to over voltage Protection D

Today's Additional works


1
2
3
4
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 05.06.20
Requested By: Md.Abdul Matin

Request Equipment Remarks Maintenance


SL No Date Name Scope R/H Description of Work Request Shift Status person
Engine Side
1 04.06.20 Sludge transfer MM FTP hall sludge transfer pneumetic pump sludge N Done Kamrul
Pump leakage from suction bellows
2 04.06.20 Eng-16 MM Engine cyl B4 CT result minimum (2.20 sec) N Done Jr.Harun
3 05.06.20 Comp.05 MM Compressor-05 (Sperre) oil level low need to top up. D Done Al-mamun

Turbine & Boiler Side

Today's Additional works


E # 01 to 09,
1 05.06.20 Feed pump-01 EM VFD showing alarm of HFO feed pump-01 Done Al-amin
VFD

Cranckase
2 05.06.20 ventilation fan EM Schedule cleaning of Fan & filter Done Al-amin
panel
3 05.06.20 FTP EM Schedule maintenance of all motor in FTP Done Al-amin

4 05.06.20 Instrument A/C-1 MM Instrument air compressor-01 drive belt tear up need Spare need
to replace.
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 06.06.20
Requested By: Md.Abdul Matin

Request Equipment Remarks Maintenance


SL No Scope R/H Description of Work Request Shift
Date Name Status person
Engine Side
1 05.06.20 HFO Sep-02 MM Oil leaking from bowl D Done Kamrul
2 05.06.20 E# 04 EM OMD sensor failure warning came several times. N Done Sohel
Exhaust back pressure only 9-12 mm showing at full
3 05.06.20 E # 06 EM & MM N Done Al-amin
load. Need to check
In battery charger panel-02,charger module-3
4 05.06.20 SSCR EM N Done Sohel
showing error value.
Turbine & Boiler Side
1 05.06.20 EGB #03 MM Exhaust Back pressure high (250mm) in EGB need to D U/O Al-mamun
manual cleaning.

Today's Additional works


1 06.06.20 E # 12 EM LT cooling water pressure is low D Done Sohel
2 06.06.20 E # 08 EM LT cooling water pump-1 tripped D Done Sohel
3 06.06.20 EGB-03 EM Drain line pneumatic v/v problem D Done Al-amin
4 06.06.20 EGB-04 MM Sootblower steam v/v opening problem D Done Al-mamun
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 07.06.20
Requested By: Md.Abdul Matin

Request Equipment Remarks Maintenance


SL No Scope R/H Description of Work Request Shift
Date Name Status person
Engine Side
1 06.06.20 E#06 MM NTC oil tank level gradually decreasing N Done Kamal

2 06.06.20 E#01 MM Cylinder temp 6A (447 c) high N Done Kamal

3 06.06.20 E# 1,2,5,9 MM HFO leakage drop by drop from inlet line flange. D 1,9 Done Sourov

4 06.06.20 E#01-09 EM E#01-09 all Dol fan filter need to clean N


Exhaust back pressure showing value when EGB OFF
5 07.06.20 E#1,2,15,16 EM& MM D 1 Done Al-amin
condition.
Exhaust back pressure sensor showing abnormal
6 06.06.20 E#13 EM& MM value (3.04 mmWC) in running condition. N Done Al-amin

Turbine & Boiler Side

Today's Additional works


1 07.06.20 FTP MM Sludge pump line modification D Done Al-mamun
2 07.06.20 E # 15 MM Cyl # A1,A6,B1,B4 & B6 exh. Temp high D Done Kamal
3
4
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 08.06.20
Requested By: Md.Abdul Matin

Request Equipment Remarks Maintenance


SL No Date Name Scope R/H Description of Work Request Shift Status person
Engine Side
1 07.06.20 E # 15 EM & MM HT PID not working in auto mode N On-going EM & MM

2 07.06.20 E # 10 MM Exhaust leakage from B5,B7 & B8 cyl. Indicator cock D Done Kamrul

3 07.06.20 E # 11 MM Exhaust manifold main line cover support bolt missing D Done Kamrul
(near A7 cylinder)
4 07.06.20 E # 04 & 11 EM & MM Exhaust back pre. Showing zero at running condition D 11 Done Sifat

5 07.06.20 E # 10 EM & MM Exhaust back pressure is flactuated(180-220 mm) D On-going Shifat

6 06.06.20 E# 2,3,4,5,6 MM HFO leakage drop by drop from inlet line flange. D Done Shourov
Exhaust back pressure showing value when EGB OFF
7 07.06.20 E#13,15,16 EM& MM condition. D On-going Shifat

Turbine & Boiler Side


1 06.06.20 LP feed water EM LP feed water pump VFD doesn't work properly as per D
pump drum requirment for Unit -02

2 07.06.20 EGB # 3,4,5 MM Sootblowing drain line jam need to be check D 3 Done jr.Harun

3 07.06.20 STG# 01 MM Ejector drain line steam trap huge steam passing D Done Al-mamun

Z stage ejector (west side ) glove valve gland packing


4 07.06.20 STG# 01 MM D Done Al-mamun
leaking

5 07.06.20 EGB# 10,11 EM Sootblowing doesn't working from DCS D Done Al-amin

6 07.06.20 EGB # 10 EM Sootblowing motor 10.1 is not working. D Done Al-amin

7 07.06.20 Unit -01 MM Chemical dosing pump-03 pressure gause meter D


doesn't show any value.
LP feed water LP feed water pump -01 for station -01 doesn't work
8 07.06.20 pump -01 EM automatically as per EGB's requirement N On-ging Sohel

9 07.06.20 EGB-10 EM Flue gas out Temperature not showing in DCS N Done Sohel

Today's Additional works


1 08.06.20 E # 02 MM Schedule maintenance D Done Kamal
2 08.06.20 Dearator-02 EM Pneumatic drain v/v feedback problem in DCS D Done Al-amin
3
4
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 09.06.20
Requested By: Md.Abdul Matin

SL No Request
Date
Equipment
Name Scope R/H Description of Work Request Shift Remarks
Status
Maintenance
person
Engine Side
1 08.06.20 E # 13 MM Before engine LO temp. high # 69 ' C D Done Sr.Harun
2 08.06.20 E # 13 MM Cylinder 4B exhaust temp. high 453 ' C N Done Kamrul
Exhaust leakage at E1# A3,A7 , E2# B7, E3# A4,A6, E4 #
3 08.06.20 Engine Hall-01 MM N
A2,A7, E5# A3,B5,B8 ,E8# A3,A4 & A7 cylinder.

At CT taken time cylinder B1 air pressure doesn't increase


4 08.06.20 E # 04 MM above 4 Bar, CT result 2-3 sec. Need to check . N Done Kamal

5 07.06.20 E # 15 EM & MM HT PID not working in auto mode N On-going EM & MM

6 07.06.20 E # 04 EM & MM Exhaust back pre. Showing zero at running condition D On-going

7 07.06.20 E # 10 EM & MM Exhaust back pressure is flactuated(180-220 mm) D Done Sifat

Exhaust back pressure showing value when EGB OFF


8 07.06.20 E#13,15,16 EM& MM condition. D On-going
Turbine & Boiler Side
Need to manual cleaning due to Exhaust back pressure is
1 08.06.20 EGB# 13 MM high 260 mmWC N

EGB-12 sootblowing motor 12.2, 12.4 motor side Valve


2 08.06.20 EGB# 12 MM steam passing at closed position D

EGB-3 sootblowing motor 3.1 & 3.5 motor side valve staem
3 08.06.20 EGB# 03 MM passing at closed position. D

EGB-9 sootblowing motor 9.2 motor side Valve steam


4 08.06.20 EGB# 09 MM passing at closed position. D

EGB-1-5 sootblowing main steam pneumatic valve gland


5 08.06.20 EGB# 01-05 MM packing leakage. D Done Mamun

6 08.06.20 EGB # 5 EM EGB-5 sootblowing motor not working. D Done Sohel

7 08.06.20 EGB # 4-5 EM EGB-4,5 sootblowing not working in automode from DCS N Need spare Sohel

8 08.06.20 EGB-12 EM EGB-12 sootblowing motor 12.3 tripped several times. N

9 08.06.20 EGB-02 EM EGB-2 flue gas In temperature not showing in DCS. N

LP feed water LP feed water pump VFD doesn't work properly as per drum
10 06.06.20 pump EM requirment for Unit -02 D Done Al-amin

11 07.06.20 EGB # 4,5 MM Sootblowing drain line jam need to be check D Done Mamun

Chemical dosing pump-03 pressure gause meter doesn't


12 07.06.20 Unit -01 MM show any value. D

LP feed water LP feed water pump -01 for station -01 doesn't work
13 07.06.20 pump -01 EM automatically as per EGB's requirement N Done Sohel

Today's Additional works


1 E # 13 MM NTC module failure Done Kamrul
2
3
4
5
6
7
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 10.06.20
Requested By: Md.Abdul Matin

SL No Request Equipment Scope R/H Description of Work Request Shift Remarks Maintenance
Date Name Status person
Engine Side
1 09.06.20 E # 12 MM TC -B bank water inlet line Jam found at TC wash time D
2 09.06.20 E # 01 MM TC washing water drain line Jam D Done Kamrul

3 09.06.20 E # 01 MM Water leakage from TC washing inlet line plastic filter D Done Kamrul

4 09.06.20 E #14 MM FIPC inlet pressure low alarm pump not working properly D Done Kamrul

5 09.06.20 E # 10 MM Huge exhaust leakage from B7 cylinder indicating cock N Done Sojib

6 09.06.20 Pit pum-01 MM Outside oily water pit pump not working (Outside E#1) N
7 09.06.20 E # 10 MM Both bank fuel gallery jam N

8 09.06.20 E # 04 MM Fuel gallery jam at B-bank side also need to engine clean. N Done Kamal

9 09.06.20 E # 13 MM 6A cylinder temp 453'C N Done Kamal


10 09.06.20 E # 03 MM A6 cylinder temp 440'C and deviation 44'C N Done Kamal
11 09.06.20 E # 02 MM B4 cylinder temp 445'C N Done Kamal
12 09.06.20 E # 11 MM Exhaust leakage from B7 & B8 cylinder indicating cock D Done Sojib
13 09.06.20 E # 03 MM Charge air cooler side PIT need to clean N
14 09.06.20 E # 01 MM Charge air condense drain line jam N Done Kamrul
15 09.06.20 E # 07 EM Exhaust back pressure not showing correct value D
16 10.06.20 E# 05 EM DG tripped due to over frequency stage-02 alarm D Urgent
17 09.06.20 E# 10-16 EM Auxiliary side not have enough lighting. D
Exhaust leakage at E1# A3,A7 , E2# B7, E3# A4,A6, E4 #
18 08.06.20 Engine Hall-01 MM N
A2,A7, E5# A3,B5,B8 ,E8# A3,A4 & A7 cylinder.

19 07.06.20 E # 15 EM & MM HT PID not working in auto mode N On-going EM & MM

20 07.06.20 E # 04 EM & MM Exhaust back pre. Showing zero at running condition D Done

Exhaust back pressure showing value when EGB OFF


21 07.06.20 E#13,15,16 EM& MM D On-going
condition.
Turbine & Boiler Side
EGB-11 flue gas diverter damper (FGDD11) feedback
1 09.06.20 EGB-11 EM problem. D Done Al-amin

STG-2 main 8" valve upper drain line valve gland packing
2 09.06.20 STG-2 MM D
leakage.
3 09.06.20 EGB-13 MM EGB-13 soot blowing all line jam need to check D Done
EGB-4&5 sootblowing drain line steam passing at closed
4 09.06.20 EGB-4 & 5 MM D
position.

5 09.06.20 EGB-6-9 MM EGB_6-9 sootblowing not working in auto mode from DCS. D

STG-2 both CEP pump tripped several times in both auto &
6 09.06.20 STG-2 EM & MM D Spare Al-amin
manual mode.
Need to manual cleaning due to Exhaust back pressure is
7 08.06.20 EGB# 13 MM N Done Jr.Harun
high 260 mmWC
EGB-12 sootblowing motor 12.2, 12.4 motor side Valve
8 08.06.20 EGB# 12 MM steam passing at closed position D

EGB-3 sootblowing motor 3.1 & 3.5 motor side valve staem
9 08.06.20 EGB# 03 MM D On-going Mamun
passing at closed position.
EGB-9 sootblowing motor 9.2 motor side Valve steam
10 08.06.20 EGB# 09 MM D
passing at closed position.

12 08.06.20 EGB-12 EM EGB-12 sootblowing motor 12.3 tripped several times. N

13 08.06.20 EGB-02 EM EGB-2 flue gas In temperature not showing in DCS. N

Chemical dosing pump-03 pressure gause meter doesn't


14 07.06.20 Unit -01 MM D Done Mamun
show any value.
Today's Additional works
1 10.06.20 E#04 EM Exhaust BP sensor fixing D Done Sifat
2 10.06.20 LP Feed pump EM LP feed water pump not working D Done Al-amin
3 10.06.20 LP Feed pump EM LP VFD not working Done Al-amin
4 10.06.20 EGB#13 MM EGB Manual cleaning N Done Jr.Harun
5 10.06.20 E#07 EM HT PID not working. D Done Sohel
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 11.06.20
Requested By: Md.Abdul Matin

SL No Request
Date
Equipment
Name Scope R/H Description of Work Request Shift Remarks
Status
Maintenance
person
Engine Side
1 10.06.20 E#05 EM Frequently power failure at turning gear module. N Done Sohel
2 10.06.20 E#10 EM Running hour problem need to be resolved N U/O Sohel
3 10.06.20 E#07 MM NTC oil level goes low two times. N Done Jr.Harun

4 10.06.20 Hose pipe MM Need 2 nos hose pipe ready for CT taking purpose only. N

From service air line we didn't get 06 bar pressure for CT


5 10.06.20 CAM-03 of PHB-2 MM taking purpose,pls need to check. N

6 10.06.20 Service air line MM Service air line need to ready from all control air module. N

HFO leakage drop by drop from inlet line flange in auxiliary


7 10.06.20 E# 07,08 MM side D Done Shourov

HFO leakage from High pressure pump dirty leak line E #03
8 10.06.20 E#03,09 MM (8A), E#09 (8A) D Done Shourov
9 09.06.20 E # 12 MM TC -B bank water inlet line Jam found at TC wash time D Done Kamrul
10 09.06.20 E # 10 MM Both bank fuel gallery jam. N Done Kamrul
11 09.06.20 E # 03 MM Charge air cooler side PIT need to clean again. N Done Kamrul
12 09.06.20 E # 07 EM Exhaust back pressure not showing correct value D Done Sifat
13 09.06.20 E# 10-16 EM Auxiliary side not have enough lighting. D
Exhaust leakage at E1# A3,A7 , E2# B7, E3# A4,A6, E4 #
14 08.06.20 Engine Hall-01 MM A2,A7, E5# A3,B5,B8 ,E8# A3,A4 & A7 cylinder. N Done Kamrul

Waiting for
15 07.06.20 E # 15 EM & MM HT PID not working in auto mode N Isolation MM

Exhaust back pressure showing value when EGB OFF


16 07.06.20 E#13,15,16 EM& MM D On-going Sifat
condition.
Turbine & Boiler Side
1 10.06.20 EGB-10 EM EGB-10 flue gas in temperature not showing in DCS N Al-amin
STG-2 main 8" valve upper drain line valve gland packing
2 09.06.20 STG-2 MM leakage. D Done Kamal

EGB-4&5 sootblowing drain line steam passing at closed


3 09.06.20 EGB-4 & 5 MM D
position.

4 09.06.20 EGB-6-9 EM EGB_6-9 sootblowing not working in auto mode from DCS. D Done Al-amin

EGB-12 sootblowing motor 12.2, 12.4 motor side Valve


5 08.06.20 EGB# 12 MM steam passing at closed position D

EGB-3 sootblowing motor 3.1 & 3.5 motor side valve staem
6 08.06.20 EGB# 03 MM D Done Mamun
passing at closed position.
EGB-9 sootblowing motor 9.2 motor side Valve steam
7 08.06.20 EGB# 09 MM passing at closed position. D

8 08.06.20 EGB-12 EM EGB-12 sootblowing motor 12.3 tripped several times. N

9 08.06.20 EGB-02 EM EGB-2 flue gas In temperature not showing in DCS. N Done Al-amin

Today's Additional works


1 11.06.20 FTP MM Hfo transfer pump strainer is dirty. U/O
2 11.06.20 E#08 EM Fuel flow meter interchange.(Inlet line) Done Al-amin
3 11.06.20 E#13 MM A-6 cylinder head replacement. Done Mamun
4
5
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 12.06.20
Requested By: Md.Abdul Matin

SL No Request
Date
Equipment
Name Scope R/H Description of Work Request Shift Remarks
Status
Maintenance
person
Engine Side
Starting air solenoid v/v was not closed after blowthrough
1 11.06.20 E#11 EM two times. D Done Al-amin

In CT test Cylinder B6 pressure was found 5.0 bar,time 2.54


2 11.06.20 E#13 MM s, also air leakage from indicating corck thread. N

In CT test Cylinder B8 air pressure (6.0 bar) lasted for 3.85


3 11.06.20 E#02 MM N Done Jr.Harun
secs
4 11.06.20 E#09 MM L/O sep 09 steam inlet line of heater gasket leakage N
In CT test Cylinder A5 air pressure was found 4.0 bar,didn't
5 11.06.20 E#02 MM increase time 2.0 s N Done Jr.Harun

EGB Need manual cleaning exhaust back pressure value 224


6 11.06.20 EGB# 08,10 MM and 248 mm respectively.
7 10.06.20 E#10 EM Running hour problem need to be resolved N U/O Sohel

8 08.06.20 Engine Hall-01 MM Exhaust leakage at E5# A3,B5,B8 ,E8# A3,A4 & A7 cylinder. N E 1,4 Done Kamrul

9 07.06.20 E # 15 EM & MM HT PID not working in auto mode N U/O Both MM & EM
Turbine & Boiler Side
EGB-10 sootblowing motor 10.2 junction box support has
1 12.06.20 EGB-10 MM been broken need to fix it D Done Mamun

Chemical dosing Chemical dosing pump 9both unit0 motor require oil
2 12.06.20 station MM filling(oil type- MOBILGEAR 600*P150 or SHC 629) D

All EGB sootblowing inlet steam valve (80nos) is filled with


3 12.06.20 EGB 1-16 MM rust that need to clean and painting. D

Sootblower system main steam both pneumatic & manual


4 12.06.20 EGB 6-9 MM N
valves has huge steam passing at closed position

EGB 1,2,3,4,5 Sootblower drain valve huge steam passsing at


5 12.06.20 EGB 1-5 MM & EM closed position N

6 12.06.20 Pump station MM Cooling water pump #2,3 gland packing leakage N Done Kamrul
7 10.06.20 EGB-10 EM EGB-10 flue gas in temperature not showing in DCS N Need spare
EGB-4&5 sootblowing drain line steam passing at closed
8 09.06.20 EGB-4 & 5 MM position. D

EGB-12 sootblowing motor 12.2, 12.4 motor side Valve


9 08.06.20 EGB# 12 MM steam passing at closed position D

EGB-9 sootblowing motor 9.2 motor side Valve steam


10 08.06.20 EGB# 09 MM D Done Mamun
passing at closed position.
Need re-
11 08.06.20 EGB-12 EM EGB-12 sootblowing motor 12.3 tripped several times. N winding Al-amin

Today's Additional works


1 11.06.20 FTP MM Hfo transfer pump strainer is dirty. U/O
2 12.06.20 EGB-07 EM 7.5 soot blower motor tripped Done Al-amin
3

5
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 13.06.20
Requested By: Md.Abdul Matin

Request Equipment
SL No Date Name Scope R/H

Engine Side
1 12.06.20 Dol Fan EM

2 12.06.20 Comp. Room EM

3 12.06.20 E#06,10 EM

4 12.06.20 E#01 MM

5 12.06.20 IAC-2 MM & EM

6 12.06.20 E#03 EM

7 13.06.20 FTP MM

8 13.06.20 E#01,04,05,06,07 MM

9 11.06.20 E#13 MM

10 11.06.20 E#09 MM

11 11.06.20 EGB# 08,10 MM

12 10.06.20 E#10 EM

13 08.06.20 Engine Hall-01 MM

Turbine & Boiler Side


1 12.06.20 STG-2 EM

2 12.06.20 EGB-7 MM

3 12.06.20 EGB 1-16 MM

4 12.06.20 EGB 6-9 MM

5 12.06.20 EGB 1-5 MM & EM

6 12.06.20 EGB-6 to 9 MM

7 12.06.20 EGB-8 MM

8 08.06.20 EGB# 12 MM
Today's Additional works

5
13 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Requested By: Md.Abdul Matin

Remarks Maintenance
Description of Work Request Shift Status person
Engine Side
E#01-09 Dol fan is dirty.(need to clean) N 1,2 Done Al-amin
Comp. Room ventilation fan filter is dirty(need to clean) &
N
one Fan breaker out of order.
Exhaust Back pressure showing fluctueted value. N Done Sifat

B-8 cylinder CT result is low.(6.0 bar , 2.3 sec) N Done Jr.Harun


"Over heated" alarm came in Instrument air compressor-
N Done Sr.Harun
02 .
Air leakage from Start air solinoide v/v line joint N

Hfo leakage from Transfer pump-1 inlet line v/v D Done Sr.Harun
Hfo leakage rom Hfo change-over pump & motor flange
D Done Sr.Harun
joint slightly.

In CT test Cylinder B6 pressure was found 5.0 bar,time 2.54


N Done Jr.Harun
s, also air leakage from indicating corck thread.

Again L.O sep-09 steam inlet line of heater gasket leakage N

EGB Need manual cleaning exhaust back pressure value 224


and 248 mm respectively.
Running hour problem need to be resolved N

Exhaust leakage at E5# A3,B5,B8 ,E8# A3,A4 & A7 cylinder. N E 5 Done Kamrul

Turbine & Boiler Side


Running hour meter doesn't working. N
Sootblowing motor 7.5 Sootblowing line roller bearing
D
became jam.
All EGB sootblowing inlet steam valve (80nos) is filled with
D
rust that need to clean and painting.

Sootblower system main steam both pneumatic & manual


valves has huge steam passing at closed position N

EGB 1,2,3,4,5 Sootblower drain valve huge steam passsing at


N
closed position

Steam passing from sootblower drain v/v at closed position. N

Steam leakage from Sootblower motor 8.2 flange. N


EGB-12 sootblowing motor 12.2, 12.4 motor side Valve
D Done Mamun
steam passing at closed position
Today's Additional works
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 14.06.20
Requested By: Md.Abdul Matin

SL No Request
Date
Equipment
Name Scope R/H Description of Work Request Shift Remarks
Status
Maintenance
person
Engine Side
1 13.06.20 Dol Fan EM E#03-09 Dol fan is dirty.(need to clean) N 3,4 Done Sifat
Comp. Room ventilation fan filter is dirty(need to clean) &
2 13.06.20 Comp. Room EM one Fan breaker out of order. N Done Sifat

3 13.06.20 HFO Sep-03 MM Bowl speed low alarm came several times. N Done Jr.Harun

4 13.06.20 E# 03 MM Charge air cooler side PIT need to clean again. N Done Kamrul

5 13.06.20 E#15 MM TC washing water inlet line leakage. N Done Kamrul

6 12.06.20 E#03 MM Air leakage from Start air solenoide v/v line joint N

7 13.06.20 Crane -02 EM &MM Engine hall -02 crane not working properly. D

8 11.06.20 E#09 MM Again L.O sep-09 steam inlet line of heater gasket leakage N

EGB Need manual cleaning exhaust back pressure value 240


9 13.06.20 EGB# 08,10 MM and 251 mm respectively. N

10 10.06.20 E#10 EM Running hour problem need to be resolved N


Exhaust leakage at E2#A7, E5# A5 , E8# A3,A4 & A7 cylinder
11 13.06.20 Engine Hall-01 MM indicating cork. N

Turbine & Boiler Side


1 13.06.20 EGB-14 MM & EM 14.3 Sootblower rewinding motor fixing. D On-going Al-amin
2 12.06.20 STG-2 EM Running hour meter doesn't working. N
3 12.06.20 EGB-7 MM 7.5 Sootblower roller bearing became jam. D On-going Mamun
All EGB sootblowing inlet steam valve (80nos) is filled with
4 12.06.20 EGB 1-16 MM rust that need to clean and painting. D

Sootblower system main steam both pneumatic & manual


5 12.06.20 EGB 6-9 MM valves has huge steam passing at closed position N On-going Sr.Harun

EGB 1,2,3,4,5 Sootblower drain valve huge steam passsing at


6 12.06.20 EGB 1-5 MM & EM closed position N

7 12.06.20 EGB-6 to 9 MM Steam passing from sootblower drain v/v at closed position. N On-going Sr.Harun

8 12.06.20 EGB-8 MM Steam leakage from Sootblower motor 8.2 flange. N On-going Sr.Harun
Today's Additional works
Turbine speed sensor & temp. sensor of alternator schedule
1 14.06.20 STG-1 & 2 EM checking Done Al-amin

2 14.06.20 Tank farm MM Done Sojib


HFO transfer pump suction line v/v gland packing leakage
3 14.06.20 DCDB panel EM At s/s DCDB panel alarm came several times Done Sohel

5
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 15.06.20
Requested By: Md.Abdul Matin

Request Equipment Remarks Maintenance


SL No Scope R/H Description of Work Request Shift
Date Name Status person
Engine Side
1 15.06.20 E # 16 MM Water found at A1 to A6 & B1 to B6 cylinder head N

2 14.06.20 E#14 EM &MM HT PID not working properly. D


Exhaust back pressure value doesn't showing in SCADA at
3 14.06.20 E#14 EM &MM D
engine running time.
4 14.06.20 E#02 MM Charge air drain pit is overflow.(need to clean) N Done

5 14.06.20 HFO Sep-01 MM "Bowl speed low" alarm came three times. N Done Sojib

6 14.06.20 IAC-2 Drayer EM Instrument air compressor-2 dryer temp. is high. N Done Al-Amin

13.06.20 Dol Fan EM E#05-09 Dol fan is dirty.(need to clean) N Done Sifat

7 12.06.20 E#03 EM Air leakage from Start air solenoide v/v line joint N Done Al-Amin

8 13.06.20 Crane -02 EM &MM Engine hall -02 crane not working properly. D Al-Amin

9 11.06.20 E#09 MM L.O sep-09 steam inlet line of heater gasket leakage N

10 13.06.20 EGB# 08,10 MM EGB Need manual cleaning exhaust back pressure value 240 N
and 262 mm respectively.
11 10.06.20 E#10 EM Running hour problem need to be resolved N

12 13.06.20 Engine Hall-01 & 2 MM Exhaust leakage at E2# A7, E5# A5 , E8# A3,A4 & A7 ,E11# N
B1 ,E14# A1 cylinder indicating cork.
Turbine & Boiler Side
1 13.06.20 EGB-14 MM & EM 14.3 Sootblower rewinding motor fixing. D Done Al-amin
2 12.06.20 STG-2 EM Running hour meter doesn't working. N Al-amin
3 12.06.20 EGB-7 MM 7.5 Sootblower roller bearing became jam. D Done Mamun

4 12.06.20 EGB 1-16 MM All EGB sootblowing inlet steam valve (80nos) is filled with D
rust that need to clean and painting.

Sootblower system main steam both pneumatic & manual


5 12.06.20 EGB 6-9 MM N On-going Sr.Harun
valves has huge steam passing at closed position.

EGB 1,2,3,4,5 Sootblower drain valve huge steam passsing at


6 12.06.20 EGB 1-5 MM & EM N
closed position

7 12.06.20 EGB-6 to 9 MM Steam passing from sootblower drain v/v at closed position. N On-going Sr.Harun

8 12.06.20 EGB-8 MM Steam leakage from Sootblower motor 8.2 flange. N Done Sr.Harun
Today's Additional works

5
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 16.06.20
Requested By: Md.Abdul Matin

Request Equipment Remarks Maintenance


SL No Date Name Scope R/H Description of Work Request Shift Status person
Engine Side
1 15.06.20 E # 16 MM Water found at A1 to A6 & B1 to B6 cylinder head N Done Sojib

4 15.06.20 E#05 MM FIPC inlet pressure alarm low. D Done Sr. Harun

5 15.06.20 E#14 MM Charge air drain line jam.(Alternetor side) N Done Sr. Harun

6 15.06.20 12 KL pump MM HFO leakage from 12KL pump bottom side.(PHB-01) D Done Sojib

7 15.06.20 E# 1,2,5 MM HFO leakage from return line flange joint. D Done Sr. Harun+Sojib

8 15.06.20 E#01 MM & EM Oil mist concentration high and engine normal stop N Done Sr. Harun + Shohel

9 15.06.20 E#15 EM DOL fan No.2 tripped. N Done Al- Amin

10 15.06.20 E#10,11 EM Oil mist converter failure alarm came several time. N Ongoing Shohel

11 15.06.20 E#14 MM HT PID not working properly. D Done Sr. Harun


Exhaust back pressure value doesn't showing at SCADA in
12 14.06.20 E#14 EM &MM engine running time. D Ongoing Al- Amin

13 15.06.20 IAC-2 Drayer MM Instrument air compressor-2 dryer air filter need to clean. N Done Sr. Harun

14 13.06.20 Dol Fan EM E#07-16 Dol fan is dirty.(need to clean) N 07 & 08 Done Sifat

15 13.06.20 Crane -02 EM & MM Engine hall -02 crane not working properly. D

16 11.06.20 E#09 MM L.O sep-09 steam inlet line of heater gasket leakage N Sojib Isolation needed

17 15.06.20 EGB# 10 MM EGB Need manual cleaning exhaust back pressure value 261 N
mm.
18 10.06.20 E#10 EM Running hour problem need to be resolved N
Exhaust leakage at E2# A7, E5# A5 , E8# A3,A4 & A7 ,E11#
19 13.06.20 Engine Hall-01 & 2 MM N
B1 ,E14# A1 cylinder indicating cork.
Turbine & Boiler Side

1 15.06.20 LP Drum-2 MM Level control pneumatic v/v (LPDLCV2) stem has been bend. D Done Sr. Harun

2 15.06.20 EGB 1-5 ,16 MM & EM EGB 1,2,3,4,5,16 Sootblowing drain valve huge steam D
passsing at closed position

3 15.06.20 Cooling Water MM Water leakage from gland packing. N Done Mamun
Pump-2

4 15.06.20 EGB-2 & 14 MM Water leakage from Jacket water heat exchanger line N Sr.Harun Need to isolation
(JWHPV).
All EGB sootblowing inlet steam valve (80nos) is filled with
5 12.06.20 EGB 1-16 MM D
rust that need to clean and painting.

Sootblower system main steam both pneumatic & manual


6 12.06.20 EGB 6-9 MM valves has huge steam passing at closed position. N Sr.Harun Need to isolation

Today's Additional works

1 E # 05 EM TC A bank speed high Al- Amin U/O

5
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 17.06.20
Requested By: Md. Syeful Islam

Request Equipment Maintenance


SL No Date Name Scope R/H Description of Work Request Shift person
Engine Side
Steam leakage from inlet steam line flange
1 16.06.20 LO sep-11 MM gasket D

2 16.06.20 Booster# 06- MM Steam leakage from inlet steam line control D
09 pneumetic valve
3 16.06.20 E # 12 MM TC washing drain line jame D Aktar

4 16.06.20 E # 05 MM LO DP high ( 1.5 bar )

5 16.06.20 E # 06 EM LT pump -02 tripped N Rana

6 16.06.20 E # 16 EM DOL fan-01 tripped N Rana


Oil mist converter failure alarm came several
7 15.06.20 E#10,11 EM time. N Shohel

8 13.06.20 Dol Fan EM E# 09-16 Dol fan is dirty.(need to clean) N Sifat, Rashed

9 14.06.20 E#14 EM Exhaust back pressure value doesn't showing at D Al- Amin
&MM SCADA in engine running time.
10 13.06.20 Crane -02 EM & Engine hall -02 crane not working properly. D
MM
11 11.06.20 E#09 MM LO sep-09 steam inlet line of heater gasket N Sojib
leakage

12 15.06.20 EGB# 10 MM EGB Need manual cleaning exhaust back N


pressure value 261 mm.
13 10.06.20 E#10 EM Running hour problem need to be resolved N

Engine Hall-01 Exhaust leakage at E2# A7, E5# A5 , E8# A3,A4 &
14 13.06.20 &2 MM A7 ,E11# B1 ,E14# A1 cylinder indicating cork. N

Turbine & Boiler Side

1 15.06.20 EGB 1-5 ,16 MM & EGB 1,2,3,4,5,16 Sootblowing drain valve huge D Aktar
EM steam passsing at closed position
Water leakage from Jacket water heat
2 15.06.20 EGB-2 & 14 MM exchanger line (JWHPV). N Aktar

3 12.06.20 EGB 1-16 MM All EGB sootblowing inlet steam valve (80nos) is D
filled with rust that need to clean and painting.

Sootblower system main steam both pneumatic


4 12.06.20 EGB 6-9 MM & manual valves has huge steam passing at N Aktar
closed position.
Today's Additional works
1 E-12 MM Cyl B2 head replace for water found Ripon, Aktar, Motiur

5
Remarks Status

Isolation needed (Friday


plan)
Isolation needed (Friday
plan)
Done

Done

Done

Ongoing

Done ( E# 09 & 10 )

Ongoing

Isolation needed (Friday


plan)

W/C to RR

Done ( EGB- 1 & 2 )

Done ( EGB-14)

Done

Done
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 18.06.20
Requested By: Md. Syeful Islam

SL No Request
Date Equipment Name Scope R/H Description of Work Request Shift Maintenance
person Remarks Status

Engine Side
Aux. Boiler Feed
1 17.06.20 MM Need to fixing comical dossing hose D Ashraf Done
Tank

2 17.06.20 Olly water transfer


pump-01 MM Need to clean strainer N Ashraf Done

3 16.06.20 E # 05 MM LO DP high ( 1.5 bar )

4 15.06.20 E#10,11 EM Oil mist converter failure alarm came several time. N E-11 bypass

5 13.06.20 Doll Fan EM E# 11-16 Doll fan is dirty.(need to clean) N

6 14.06.20 E#14 EM Exhaust back pressure value doesn't showing at SCADA D


&MM in engine running time.
EM &
7 13.06.20 Crane -02 MM Engine hall -02 crane not working properly. D

8 15.06.20 EGB# 10 MM EGB Need manual cleaning exhaust back pressure N


value 261 mm.

Exhaust leakage at E2# A7, E5# A5 , E8# A3,A4 & A7


9 13.06.20 Engine Hall-01 & 2 MM ,E11# B1 ,E14# A1 cylinder indicating cork. N

Turbine & Boiler Side


1 17.06.20 EGB- 3 & 4 MM Soot blowing drain line blocked N Akter Done
Steam leakage from LP generator outlet valve flange
2 17.06.20 EGB-01 MM gasket N

3 15.06.20 EGB-2 MM Water leakage from Jacket water heat exchanger line N Isolation needed
(JWHPV).

4 15.06.20 EGB 3 & 16 MM & EGB 3,4,5,16 Soot blowing drain valve huge steam D Akter Done (EGB-03)
EM passing at closed position

5 12.06.20 EGB 1-16 MM All EGB soot blowing inlet steam valve (80nos) is filled D
with rust that need to clean and painting.
Today's Additional works
DME, Sohel &
1 STG - 01 EM Over Voltage activation problem rectification works Rana Done

2 Eng. 12 EM Speed Sensor cable problem work Rana Done

4
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 19.06.20
Requested By: Md. Syeful Islam

SL No Request
Date Equipment Name Scope R/H Description of Work Request Shift Maintenance
person Remarks Status

Engine Side

1 16.06.20 E # 05 MM LO DP high ( 1.5 bar )

2 15.06.20 E#10 EM Oil mist converter failure alarm came several time. N

3 13.06.20 E#11-16 EM Doll fan filter is dirty.(need to clean) N Sifat, Rashed Done(E11-12)

4 14.06.20 E#14 EM/MM Exhaust back pressure value doesn't showing at SCADA D
in engine running time.
5 13.06.20 Crane -02 EM/MM Engine hall -02 crane not working properly. D
Exhaust leakage at E2# A7, E5# A5 , E8# A3,A4 & A7
6 13.06.20 Engine Hall-01&02 MM ,E11# B1 ,E14# A1 cylinder indicating cork. N

Turbine & Boiler Side


EGB Need manual cleaning exhaust back pressure
1 18.06.20 EGB# 10 & 11 MM value 305 & 270 mm. D Motiur Done (E-10)

2 18.06.20 EGB-11 MM Steam leakage from super heater drain line flange N Aktar Done
gasket
3 18.06.20 STG-02 EM/MM condenser hotwel level gauge abnormal showing N Aktar Done

4 17.06.20 EGB-01 MM Steam leakage from LP generator outlet valve flange N Aktar Done
gasket

5 15.06.20 EGB-2 MM Water leakage from Jacket water heat exchanger line N Isolation needed
(JWHPV).
Soot blowing drain valve huge steam passing at closed
6 15.06.20 EGB- 16 MM/EM position D Aktar Done

7 12.06.20 EGB 1-16 MM All EGB soot blowing inlet steam valve (80nos) is filled D
with rust that need to clean and painting.
Today's Additional works

1 E # 09 LO Separator Steam leakage Done

2 E # 11 LO Separator Steam leakage Done

3 E#4-6 Booster Steam leakage Done

4
113 MW Confidence Power Rangpur Ltd.
Current Maintenance Work Request
Date 20.06.20
Requested By: Md. Syeful Islam

SL No Request
Date Equipment Name Scope R/H Description of Work Request Shift Maintenance
person Remarks Status

Engine Side
1 19.06.20 Eng-07 MM A bank leak fuel drain line jam N

2 19.06.20 Air Com. # 06 MM Air Compressor oil level low 30 % need to refill N

3 13.06.20 E # 13-16 EM Doll fan filter is dirty (need to clean) N


Turbine & Boiler Side

1 19.06.20 EGB # 11 MM EGB Need manual cleaning exhaust back pressure D Ongoing
value 279 mm.

2 19.06.20 EGB # 01 MM LP Generator outlet drain valve couldn’t Full N


Open/Close.
3 19.06.20 EGB-16 MM Diverter damper air hose pipe leakage found D
Pending Works
1 16.06.20 E # 05 MM LO DP high ( 1.5 bar )

2 15.06.20 E#10 EM Oil mist converter failure alarm came several time. N
Exhaust back pressure value doesn't showing at SCADA
3 14.06.20 E#14 EM/MM in engine running time. D

4 13.06.20 Crane -02 EM/MM Engine hall -02 crane not working properly. D
Exhaust leakage from E2# A7, E5# A5 , E8# A3,A4 &
5 13.06.20 Engine Hall-01&02 MM A7 ,E11# B1 ,E14# A1 cylinder indicating cork. N

6 15.06.20 EGB-2 MM Water leakage from Jacket water heat exchanger line N Isolation needed
(JWHPV).
All EGB soot blowing inlet steam valve (80nos) is filled
7 12.06.20 EGB 1-16 MM with rust that need to clean and painting. D

Today's Additional works