This document provides a 360 day schedule for the construction of the Paktia Regional Cold Chain Building in Afghanistan from June 2020 through May 2021. It includes timelines for mobilization, site preparation, foundation work, structural work, interior and exterior finishing work. The project is currently in the documents preparation stage and is scheduled for completion on May 26, 2021.
A Hierarchy of Turing Degrees: A Transfinite Hierarchy of Lowness Notions in the Computably Enumerable Degrees, Unifying Classes, and Natural Definability (AMS-206)
This document provides a 360 day schedule for the construction of the Paktia Regional Cold Chain Building in Afghanistan from June 2020 through May 2021. It includes timelines for mobilization, site preparation, foundation work, structural work, interior and exterior finishing work. The project is currently in the documents preparation stage and is scheduled for completion on May 26, 2021.
This document provides a 360 day schedule for the construction of the Paktia Regional Cold Chain Building in Afghanistan from June 2020 through May 2021. It includes timelines for mobilization, site preparation, foundation work, structural work, interior and exterior finishing work. The project is currently in the documents preparation stage and is scheduled for completion on May 26, 2021.
This document provides a 360 day schedule for the construction of the Paktia Regional Cold Chain Building in Afghanistan from June 2020 through May 2021. It includes timelines for mobilization, site preparation, foundation work, structural work, interior and exterior finishing work. The project is currently in the documents preparation stage and is scheduled for completion on May 26, 2021.
PAKTIA REGIONAL COLD CHAIN BUILDING ALASKA CONSTRUCTION AND ENGINEERING COMPANY 06-Jun-20 23:32
Activity Name Original Remaining Schedule % Start Finish May 2020
Total June 2020 July 2020 A S O N D J F March 2021 April 2021 May 2021 June 2021 July 2021 A S Duration Duration Complete Float 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 01
Total 360 360 0% 01-Jun-20 26-May-21 1 26-May-21, Total
PAKTIA REGIONAL COLD CHAIN BUILDING 360 360 0% 01-Jun-20 26-May-21 1 26-May-21, PAKTIA REGIONAL COLD CHAIN BUILDING Documents preparation for project 10 10 0% 01-Jun-20 10-Jun-20 1 Documents preparation for project Mobilization of Project 15 15 0% 11-Jun-20 25-Jun-20 1 Mobilization of Project Site preparation 5 5 0% 22-Jun-20 26-Jun-20 1 Site preparation Excavation for foundation 8 8 0% 27-Jun-20 04-Jul-20 1 Excavation for foundation Gravel filling and compaction 5 5 0% 05-Jul-20 09-Jul-20 1 Gravel filling and compaction Bed pcc for foundation 5 5 0% 10-Jul-20 14-Jul-20 1 Bed pcc for foundation Rcc footing work 15 15 0% 15-Jul-20 29-Jul-20 1 Rcc footing work Stone masonry for foundation 15 15 0% 30-Jul-20 13-Aug-20 1 Stone masonry for foundation Rcc columns up to ring beam 6 6 0% 14-Aug-20 19-Aug-20 1 Rcc columns up to ring beam Rcc ring beam work 7 7 0% 20-Aug-20 26-Aug-20 1 Rcc ring beam work Back filling work 5 5 0% 24-Aug-20 28-Aug-20 1 Back filling work Rcc columns of ground floor 12 12 0% 29-Aug-20 09-Sep-20 1 Rcc columns of ground floor Brick masonry wall for ground floor 12 12 0% 10-Sep-20 21-Sep-20 1 Brick masonry wall for ground floor Rcc beams , slab and stairs of ground floor 24 24 0% 22-Sep-20 15-Oct-20 1 Rcc beams , slab and stairs of ground floor Rcc columns of first floor 12 12 0% 16-Oct-20 27-Oct-20 1 Rcc columns of first floor Brick masonry wall for first floor 12 12 0% 28-Oct-20 08-Nov-20 1 Brick masonry wall for first floor Rcc beams , slab and stairs of first floor 24 24 0% 09-Nov-20 02-Dec-20 1 Rcc beams , slab and stairs of first floor Rcc work of parapet walls 5 5 0% 03-Dec-20 07-Dec-20 1 Rcc work of parapet walls Gravel filling and compaction for floor 5 5 0% 08-Dec-20 12-Dec-20 1 Gravel filling and compaction for floor Pcc for floor 100cm thick 5 5 0% 13-Dec-20 17-Dec-20 1 Pcc for floor 100cm thick Rcc slab on grade 12 12 0% 18-Dec-20 29-Dec-20 1 Rcc slab on grade Doors and windows installation 10 10 0% 30-Dec-20 08-Jan-21 1 Doors and windows installation Interior plaster work 18 18 0% 09-Jan-21 26-Jan-21 1 Interior plaster work Rigid foam for roof 5 5 0% 27-Jan-21 31-Jan-21 1 Rigid foam for roof Steel mash for roof on the top of rigid foam 5 5 0% 01-Feb-21 05-Feb-21 1 Steel mash for roof on the top of rigid foam Pcc for roof 5cm thick on the top of steel mash 5 5 0% 06-Feb-21 10-Feb-21 1 Pcc for roof 5cm thick on the top of steel mash Isogam one layer for roof on the top of pcc 5 5 0% 11-Feb-21 15-Feb-21 1 Isogam one layer for roof on the top of pcc Pcc for roof on the top of isogam 5 5 0% 16-Feb-21 20-Feb-21 1 Pcc for roof on the top of isogam Exterior plaster work 15 15 0% 21-Feb-21 07-Mar-21 1 Exterior plaster work Gravel filling and compaction for floor 5 5 0% 08-Mar-21 12-Mar-21 1 Gravel filling and compaction for floor Pcc for floor 100cm thick 5 5 0% 13-Mar-21 17-Mar-21 1 Pcc for floor 100cm thick DPC layer ( tar paper 2mm thick ) 5 5 0% 18-Mar-21 22-Mar-21 1 DPC layer ( tar paper 2mm thick ) Marble work 25 25 0% 23-Mar-21 16-Apr-21 1 Marble work Tiles work 15 15 0% 17-Apr-21 01-May-21 1 Tiles work Metal work like raillings and Gi sheet 8 8 0% 02-May-21 09-May-21 1 Metal work like raillings and Gi sheet Painting work 15 15 0% 04-May-21 18-May-21 1 Painting work Table and cabinet work for kitchen 8 8 0% 13-May-21 20-May-21 1 Table and cabinet work for kitchen Parquetry work for floor and wall 10 10 0% 17-May-21 26-May-21 1 Parquetry work for floor and wall Complete electric system 225 225 0% 22-Sep-20 04-May-21 13 Complete electric system Complete water and sewer system 130 130 0% 26-Dec-20 04-May-21 13 Complete water and sewer system Complete mechanical system 25 25 0% 10-Apr-21 04-May-21 13 Complete mechanical system Complete septic tank work 20 20 0% 23-Mar-21 11-Apr-21 46 Complete septic tank work Site clean up 5 5 0% 05-May-21 09-May-21 13 Site clean up Demobilization of project 5 5 0% 10-May-21 14-May-21 13 Demobilization of project
A Hierarchy of Turing Degrees: A Transfinite Hierarchy of Lowness Notions in the Computably Enumerable Degrees, Unifying Classes, and Natural Definability (AMS-206)