PAKTIA REGIONAL COLD CHAIN BUILDING ALASKA CONSTRUCTION AND ENGINEERING COMPANY 06-Jun-20 23:32

Activity Name Original Remaining Schedule % Start Finish May 2020


Total June 2020 July 2020 A S O N D J F March 2021 April 2021 May 2021 June 2021 July 2021 A S
Duration Duration Complete Float
2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 01

Total 360 360 0% 01-Jun-20 26-May-21 1 26-May-21, Total


PAKTIA REGIONAL COLD CHAIN BUILDING 360 360 0% 01-Jun-20 26-May-21 1 26-May-21, PAKTIA REGIONAL COLD CHAIN BUILDING
Documents preparation for project 10 10 0% 01-Jun-20 10-Jun-20 1 Documents preparation for project
Mobilization of Project 15 15 0% 11-Jun-20 25-Jun-20 1 Mobilization of Project
Site preparation 5 5 0% 22-Jun-20 26-Jun-20 1 Site preparation
Excavation for foundation 8 8 0% 27-Jun-20 04-Jul-20 1 Excavation for foundation
Gravel filling and compaction 5 5 0% 05-Jul-20 09-Jul-20 1 Gravel filling and compaction
Bed pcc for foundation 5 5 0% 10-Jul-20 14-Jul-20 1 Bed pcc for foundation
Rcc footing work 15 15 0% 15-Jul-20 29-Jul-20 1 Rcc footing work
Stone masonry for foundation 15 15 0% 30-Jul-20 13-Aug-20 1 Stone masonry for foundation
Rcc columns up to ring beam 6 6 0% 14-Aug-20 19-Aug-20 1 Rcc columns up to ring beam
Rcc ring beam work 7 7 0% 20-Aug-20 26-Aug-20 1 Rcc ring beam work
Back filling work 5 5 0% 24-Aug-20 28-Aug-20 1 Back filling work
Rcc columns of ground floor 12 12 0% 29-Aug-20 09-Sep-20 1 Rcc columns of ground floor
Brick masonry wall for ground floor 12 12 0% 10-Sep-20 21-Sep-20 1 Brick masonry wall for ground floor
Rcc beams , slab and stairs of ground floor 24 24 0% 22-Sep-20 15-Oct-20 1 Rcc beams , slab and stairs of ground floor
Rcc columns of first floor 12 12 0% 16-Oct-20 27-Oct-20 1 Rcc columns of first floor
Brick masonry wall for first floor 12 12 0% 28-Oct-20 08-Nov-20 1 Brick masonry wall for first floor
Rcc beams , slab and stairs of first floor 24 24 0% 09-Nov-20 02-Dec-20 1 Rcc beams , slab and stairs of first floor
Rcc work of parapet walls 5 5 0% 03-Dec-20 07-Dec-20 1 Rcc work of parapet walls
Gravel filling and compaction for floor 5 5 0% 08-Dec-20 12-Dec-20 1 Gravel filling and compaction for floor
Pcc for floor 100cm thick 5 5 0% 13-Dec-20 17-Dec-20 1 Pcc for floor 100cm thick
Rcc slab on grade 12 12 0% 18-Dec-20 29-Dec-20 1 Rcc slab on grade
Doors and windows installation 10 10 0% 30-Dec-20 08-Jan-21 1 Doors and windows installation
Interior plaster work 18 18 0% 09-Jan-21 26-Jan-21 1 Interior plaster work
Rigid foam for roof 5 5 0% 27-Jan-21 31-Jan-21 1 Rigid foam for roof
Steel mash for roof on the top of rigid foam 5 5 0% 01-Feb-21 05-Feb-21 1 Steel mash for roof on the top of rigid foam
Pcc for roof 5cm thick on the top of steel mash 5 5 0% 06-Feb-21 10-Feb-21 1 Pcc for roof 5cm thick on the top of steel mash
Isogam one layer for roof on the top of pcc 5 5 0% 11-Feb-21 15-Feb-21 1 Isogam one layer for roof on the top of pcc
Pcc for roof on the top of isogam 5 5 0% 16-Feb-21 20-Feb-21 1 Pcc for roof on the top of isogam
Exterior plaster work 15 15 0% 21-Feb-21 07-Mar-21 1 Exterior plaster work
Gravel filling and compaction for floor 5 5 0% 08-Mar-21 12-Mar-21 1 Gravel filling and compaction for floor
Pcc for floor 100cm thick 5 5 0% 13-Mar-21 17-Mar-21 1 Pcc for floor 100cm thick
DPC layer ( tar paper 2mm thick ) 5 5 0% 18-Mar-21 22-Mar-21 1 DPC layer ( tar paper 2mm thick )
Marble work 25 25 0% 23-Mar-21 16-Apr-21 1 Marble work
Tiles work 15 15 0% 17-Apr-21 01-May-21 1 Tiles work
Metal work like raillings and Gi sheet 8 8 0% 02-May-21 09-May-21 1 Metal work like raillings and Gi sheet
Painting work 15 15 0% 04-May-21 18-May-21 1 Painting work
Table and cabinet work for kitchen 8 8 0% 13-May-21 20-May-21 1 Table and cabinet work for kitchen
Parquetry work for floor and wall 10 10 0% 17-May-21 26-May-21 1 Parquetry work for floor and wall
Complete electric system 225 225 0% 22-Sep-20 04-May-21 13 Complete electric system
Complete water and sewer system 130 130 0% 26-Dec-20 04-May-21 13 Complete water and sewer system
Complete mechanical system 25 25 0% 10-Apr-21 04-May-21 13 Complete mechanical system
Complete septic tank work 20 20 0% 23-Mar-21 11-Apr-21 46 Complete septic tank work
Site clean up 5 5 0% 05-May-21 09-May-21 13 Site clean up
Demobilization of project 5 5 0% 10-May-21 14-May-21 13 Demobilization of project