DAILY DRILLING REPORT

Daily Operation Report Date: 1/1/2013 Project Rumaila 2 County Iraq


Rig IDC 37 Well R-543 (NP_GE31) Conductor: 45 m 20.000 in RT Elev. 8.10 m Activity Drilling Spud Date 13-Nov-2012
Obj: Zubair Planned Depth: 3,432 m Planned Days: 48 GL Elev. 15.50 m POB: 104
Depth MD (m) TVD (m) Bit Current Previous Screw in BHA Amou ID (in) OD (in) Lenght Total (m)
00:00 hrs 3,437.00 3,425.00 Make Smith nt (m)
14:00 hrs 3,437.00 3,424.82 Serial JF7752 Screw in sub SN:1631258 1 3.750 6.000 1.22 1.22

24:00 hrs 3,437.00 3,425.00 Number 1 x 6 3/4" DC 1 2.813 6.750 9.36 10.58

Meterage 0.00 0.00 Diameter 8.500 in 1 x 6 1/2" Drilling Jar SN:56719H 1 2.687 6.500 9.19 19.77

Lithology Top(m) Bottom(m) Model MSi716WPX 9 x 6 3/4" DC 9 2.813 6.750 84.79 104.56

Ahmadi 2,510 2,638 Nozzles (in) (7)11 12 x 5" HWDP 12 3.000 5.000 110.06 214.62

Maudud 2,638 2,764 Mts Drilled 0 1462


Nahr Umr 2,764 3,020 Oper. hrs 121.00
Shuaiba 3,020 3,107 Average x m 4.97
Z/1A 3,101 Last 3 Mts
Dull Grading ------- 0-0-NO-A-X-I-NO-PP
Casing Dia (in) Depth (m) Date MD(m) TVD (m) Angle Azimuth Closure (m) Severity (deg/30m)
Last 9.625 1,962.00 17-Dec-2012 3,393 3,381.18 1.33 283.73 105.32 0.12
Next 7.000 3,431.00 17-Dec-2012 3,320 3,307.75 1.04 283.09 106.79 0.09
Mud Polymer Density In 1.21 g/cm3 Den.Out 1.21 g/cm3 Temp. In 49 degC Formation Tests Material Cons Stock
Sand 0 % ECD 1.21 g/cm3 Calcium 280 mg/L Temp. Out degC EMW Test 1.50 g/cm3 Barite(ton) 0 55
Gel 0: 10.00 lbf/100ft2 Gel 10: 12.00 lbf/100ft2 Gel 30: 15.00 lbf/100ft2 API Cake 1 mm PP EMW g/cm3 Camp Fuel(L) 700 7,500
pH 9.00 API Vol. 3 cm3 Alkalin. 0.20 Choride 45,000 mg/L FP EMW g/cm3 Rig Fuel(L) 8,000 55,500
Viscosity 53 s Plast.Vis. 16 cP Yield P. 30 lbf/100ft2 Water 89 % Test Date 12-Dec-2012
Salinity ppm Solids 11 %
Weight on Bit MTon Liner Size 1 6.500 x 12.000 30 SPM Pump 1 40 stroke/min @ 700 psi SCR @ 3411 M W/ 1.2 SG.
Rotary Speed RPM Liner Size 2 6.500 x 12.000 30 SPM Pump 2 40 stroke/min @ 690 psi SCR @ 3411 M W/ 1.2 SG
Standpipe Pressure psi Flow Rate L/min 60 SPM Well Kill Drill Date: Time:
Torque 1000 ft.lbf Annular Velocity 0.00 MPM Koomey - Manifold: Accumulator Annular
Rotating Hook Load MTon BOP Test Date 30-Dec-2012
3LFN+RRN/RDG ĹĺĻ Days Without LTA 46
Summary Previous Day Continued RIH Screw in assembly to top of fish.Circulated to clean hole. Engaged fish. Worked on stuck string by jarring down. Observed fish disconnect from screw in sub. Circulated
to clean hole. Observed cavings on shale shaker. Engaged fish again. Worked on Stuck string by jarring down and holding torque. Observed 1 m progress. Worked on stuck string.
Found no further progress.

Printer on: 1/2/2013 2011.1 05Jan2012 v2.3


DAILY DRILLING REPORT

Hrs 01-Jan-2013 Operations Time


00:00 - 06:00 6.00 NPT: WORK ON STUCK STRING BY JARRING DOWN Mobilization (days) 113.00
- work on string by applying 20 klbs*ft torque and jarring down for one hour and 30 min to cool jar periodically Mobilization NPT (hrs)
- held 200 psi pressure and kept on jarring down
- no progress Mobilization (no NPT) 113.00
- 3m3 downhole losses measured by trip tank Drilling (days) 50.00
- offline start P-test choke manifold Drilling NPT (Last 24 hrs) (hrs) 24.00
06:00 - 12:00 6.00 NPT: WORKED ON STUCK STRING BY JARRING DOWN
NPT Total % 39.31 %
- work on string by applying 20 klbs*ft torque and jarring down for one hour and 30 min to cool jar periodically
- held 200 psi pressure and kept on jarring down Total Well Time 50.00
- no progress NPT DISTRIBUTION Hours
- 1.7m3 downhole losses measured by trip tank
Waiting Codes 28.50
12:00 - 14:30 2.50 NPT: WORKED ON STUCK STRING BY JARRING DOWN
- work on string by applying 20 klbs*ft torque and jarring down for one hour and 30 min to cool jar periodically Mobilization
- held 200 psi pressure and kept on jarring down. Equipment Repairs 71.50
- no progress. Drilling 24.00
- 0.5m3 downhole losses measured by trip tank
- decided to back off fishing string from fish due to unsuccessful jaring Wellhead and BOP 9.00
- offline finished P-test choke manifold at 300 psi/5 min, 2400 psi/10 min. ok QHSE
14:30 - 15:15 0.75 NPT: ATTEMPT BLIND BACK OFF RIR's/STOP's 12
- apply 15 kft*lbs left hand torque
Safety Meetings 0
- transmit torque several times - no success to back off
- apply 20 kft*lbs left hand torque - string backed off reading 32t (75t lost) Drills 0
- successfully reconnect lost string TOTAL 12
15:15 - 15:45 0.50 NPT: CHECK CIRCULATION Components and Aux. Equipments
- pump down the string to check for returns
- stop pumping when reached 1000psi - confirmed no return Shale Shaker#1 200/200/200/200
15:45 - 17:30 1.75 NPT: ATTEMPT BLIND BACK OFF SECOND TIME Shale Shaker#2 170/170/170/170
- apply 20 kft*lbs left hand torque at string neutral weight Shale Shaker#3 70/70/70/70
- transmit torque several times - no success to back off Well Engineer ALEK NIFANTOV
- release torque to zero
- apply 20 kft*lbs left hand torque again - string backed off at same place when first back off WSS HISHAM / DIMITRY
- successfully reconnect lost string again by applying 21 kft*lbs torque Client Witness MOHAMED ABDULSA
- transmit torque several times
Client Phone
17:30 - 20:00 2.50 NPT: TRANSMIT RIGHT HAND TORQUE TO ALL DRILL STRING CONNECTIONS
AWSS G.H.GOHER
- apply 21 kft*lbs right hand torque at string neutral weight counting turns
- transmit torque several times Rig Phone
- release torque to zero counting turns Rig Manager
- repeat steps above until number of turns before and after torque transmition is equal
Safety Coord.
20:00 - 22:00 2.00 NPT: ATTEMPT BLIND BACK OFF THIRD TIME
- apply 5 kft*lbs left hand torque at string neutral weight Client Geologist AMMAR
- transmit torque several times by picking up 20t from neutral weight
- repeat steps above in incriments of 5 kft*lbs reaching max 20 kft*lbs - no success
- release torque to zero
- repeat entire procedure again - no success
- release torque to zero
22:00 - 22:45 0.75 NPT: TRANSMIT RIGHT HAND TORQUE TO ALL DRILL STRING CONNECTIONS
- apply 25 kft*lbs right hand torque at string neutral weight counting turns
- transmit torque several times
- release torque to zero counting turns
- repeat steps above until number of turns before and after torque transmition is equal
22:45 - 00:00 1.25 NPT: ATTEMPT BLIND BACK OFF FOURTH TIME
- apply 5 kft*lbs left hand torque at string neutral weight
- transmit torque several times by picking up 20t from neutral weight
- repeat steps above in incriments of 5 kft*lbs reaching max 22 kft*lbs - string backed off reading 59t (48t lost)
- successfully reconnect lost string
Hrs 02-Jan-2013
00:00 - 01:30 1.50 NPT: TRANSMIT RIGHT HAND TORQUE TO ALL DRILL STRING CONNECTIONS
- apply 25 kft*lbs right hand torque at string neutral weight counting turns
- transmit torque several times
- release torque to zero counting turns
- repeat steps above until number of turns before and after torque transmition is equal
01:30 - 03:00 1.50 NPT: ATTEMPT BLIND BACK OFF FIFTH TIME
- apply 5 kft*lbs left hand torque at string neutral weight
- transmit torque several times by picking up 20t from neutral weight
- repeat steps above in incriments of 5 kft*lbs reaching max 20 kft*lbs - no success
- release torque to zero
- repeat entire procedure again - no success
- release torque to zero
03:00 - 04:30 1.50 NPT: TRANSMIT RIGHT HAND TORQUE TO ALL DRILL STRING CONNECTIONS
- apply 25 kft*lbs right hand torque at string neutral weight counting turns
- transmit torque several times
- release torque to zero counting turns
- repeat steps above until number of turns before and after torque transmition is equal
04:30 - 06:00 1.50 NPT: MAKING ARRANGEMENTS TO BACK OFF
Day Summary Worked on Stuck string by jarring down and holding torque. No progress. Attempted blind back off by applying 20 klbs.ft left hand torque, string backed off reading 32t (75t lost). Reconnected
successfully. Checked circulation. no returns. Attempted blind back off sencond time by applying 20 klbs.ft left hand torque, string back off from same place. Applied and transmitted 21 klb.ft
right hand torque to all drill string connection. Attempted blind back off by applying 20 klbs.ft left hand torque. No success. Applied and transmitted 25 klb.ft right hand torque to all drill string
connection. Attempted blind back off by applying 22 klbs.ft left hand torque, string backed off reading 59t (48t lost). Reconnected successfully.
Forecast Continue work on stuck string.
Comments Stop cards: 12, unsafe: 11, positive: 1, safety meeting: 0, PTW: 3, Inspection: 1, JSA: 2, MLP: 0, Drill: 0, Training: 0, Safety Topic: Safety Guards and Barriers
Supplies Needed

Printer on: 1/2/2013 2011.1 05Jan2012 v2.3