SOP HOTTAPING :
1.CLOSE ISOLATION VALVE ATTACHED HOT TAP FITTING
2.INSTALL TAPPING MACHINE ON TO THE VALVE
3.INSTALL VENTING VALVE ON TO TAPPING MACHINE ,OPEN ISOLATION
4.PRESSURE TEST HOT TAP FITTING , ISOLATION VALVE AND TAPPING MACHINE ADAPTER
ASSEMBLY
5.HOLDING 30 MINUTES
6.RELEASE TEST PRESSURE
7.EXTEND BORING BAR OF TAPPING MACHINE INTO HOT TAP FITTING UNTIL PILOT DRILL TOUCHES
TOP OF EXISTING PIPE.
8.CONNECT THE HYDRAULIC HOSE OF TAPPING MACHINE AND HYDRAULIC POWER UNIT
9. START ENGINE OF HYDRAOULIC POWER UNIT OF TAPPING MACHINE
10. WHEN THE PILOT DRILL PENETRATE THROUGH THE PIPE, REMOVE GAS REST AND CLOSE
VENTING VALVE
11.STOP HOT TAPPING MACHINE ,RETRACT BORING BAR UNTIL THE CUTTER ARE INSIDE THE
ADAPTER
12.CLOSE ISOLATION VALVE
13.REMOVE TAPPING MACHINE FROM THE ISOLATION VALVE