01 - Details Sequence of Work - TNB Manhole
01 - Details Sequence of Work - TNB Manhole
Revision No: 00
SEQUENCE OF WORKS Date: 25th June 2018
THE PROPOSED CONSTRUCTION AND COMPLETION OF 118 UNITS 2 STOREY TERRACE HOUSES AT
PLOT 12R2C AND ASSOCIATED WORKS AT PRESINT 12, PUTRAJAYA
Excavation
1. Excavate the opening are as per the construction drawing.
2. All excavation shall be by means of open excavation using hydraulic excavator.
3. Excavated material shall be stockpiled at the side for backfilling upon completion.
Manhole Installation
1. Sand-bedding the foundation of the manhole
2. Precast manhole installed into the excavated open cut area
3. Backfilled the excavation area after the iron cover installed.