Sample Network Diagram

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Earliest start time for activity D = 8 weeks ,

EF = ES + t , where ES = earliest start time, EF, earliest finish time, t = expected activity time

EF = 8 + 4 = 12

LS = LF - t = 23 - 3

slack = LS - ES = LF - EF, slack for activity G = LS for G - ES for G = 16 - 10 = 6

slack for C = LS for C - ES for C = 5 - 5 =0, critical path are those with zero slack B,C, D, E J