Elevators Traffic Planning 

Tower H: 

 core 2: 

inputs:  

‐ Travel Height = 62.7 m. from 3rd basement to 14th floor. 
‐ Population “from layouts” = 96 persons. 
‐ Occupancy 40% ‐60% leave in the morning, thus 3% →6% per five minutes. as 
per attached code. 
‐ Waiting time: excellent ≤35sec.  good ≤40 sec.  moderate ≤45 sec. 
‐ Two elevators of layouts : 
Elevator 1: (2.15m. x 2.2m.) dimensions with 10 persons capacity.  
Elevator2 :(2.7 m. x 2.15m.)  Dimensions with 12 persons capacity. 
‐ Normal speed = 2.5m/sec. as per attached TOSHIBA code. 

Calculations: 

Required capacity = population x occupancy x peak demand. 

             = 108 x (40% →60%) x (3% → 6%) 
             = 2 → 4 persons per 5 min. 

Travel time (ascending & descending) = 2 x   + exit & entry time. 

                     = 25.8 +25.8 +25.8 
                     = 75.24 sec.           

Number of travels per 5 min. =   = 8 travels. 
.

.
Waiting time =    =   = 37.62 sec. < 40 sec. which is good 

Elevator capacity at layouts: “per five minutes” 

(8x 10) + (12x8) = 176 persons per 5 min. as per code 2→4 per 5min. 

    4<176 
 
Elevators Traffic Planning  

Tower type H: 

 core 1: 

inputs:  

‐ Travel Height = 49.1 m. from 3rd basement to 10th floor. 
‐ Population “from layouts” = 108 persons. 
‐ Occupancy 40% ‐60% leave in the morning, thus 3% →6% per five minutes. as 
per attached code. 
‐ Waiting time: excellent ≤35sec.  good ≤40 sec.  moderate ≤45 sec. 
‐ Two elevators of layouts:  
Elevator 1: dimensions (2.15m. x 2.2m.)10 persons capacity. 
 Elevator2: dimensions (2.7 m. x 2.15m.) 12 persons capacity. 
‐ Normal speed = 2m/sec. as per attached TOSHIBA code. 

Calculations: 

Required capacity = population x occupancy x peak demand. 

             = 108 x (40% →60%) x (3% → 6%) 
             = 2 → 4 persons per 5 min. 

Travel time (ascending & descending) = 2 x   + exit & entry time. 

                     = 2 x 24.55 +24.55 
                     = 74 sec.           

Number of travels per 5 min. =   = 8 travels. 

Waiting time =    =   = 37 sec. < 40 sec. which is good 

Elevator capacity at layouts: “core 1” 

(8x 10) + (8x12) = 176 persons per 5 min. as per code 2→4 per 5min. 

    4<176 
 
 

Elevators Traffic Planning 

Tower type B: 

inputs:  

‐ Travel Height = 73.50 m. from 2nd basement to 18th floor. 
‐ Population “from drawings layouts” = 196 persons. 
‐ Occupancy 40% ‐60% leave in the morning, thus 3% →6% per five minutes. as 
per attached code. 
‐ Waiting time: excellent ≤35sec.  good ≤40 sec.  moderate ≤45 sec. 
‐ Two elevators “layouts” 
‐ Elevators car capacity:  
Elevator 1: dimensions (2.15m. x 2.2m.) 10 persons capacity. 
Elevator2: dimensions (2.7 m. x 2.15m.)  12 persons capacity. 
‐ Nominal speed = 3m/sec. as per TOSHIBA attached code. 

Calculations: 

Required capacity = population x occupancy x peak demand. 
        = 196 x (40% →60%) x (3% → 6%) 
        =3→7 persons per 5 min. 

Travel time (ascending & descending) = 2 x   + exit & entry time. 

                     = 2 x24.5+24.5                
                     = 73.5 per sec.           

Number of travels per 5 min. =   = 8 travels 
.

.
Waiting time =    =   = 36.75 sec. < 40 sec. which is good 

Elevator capacity at layouts: “per five minutes” 

(8x 10) + (12x8) = 176 persons per 5 min. as per code 3→7  persons per 5min.  

    7 <176 
 