Regular Shirts

Laber Content Number of Cycle time Capacity /


Operation (Minutes per shirt) Workers Min/shirt day Utilization
1. Make Collar 3.90 8 0.49 985 0.81
2. Make cuffs 2.00 4 0.50 960 0.83
3. Make sleeves 0.65 2 0.33 1477 0.54
4. Make front 2.50 6 0.42 1152 0.69
5. Make back 1.70 4 0.43 1129 0.71
6. Join shoulders 0.66 2 0.33 1455 0.55
7. Attach collar 1.65 4 0.41 1164 0.69
8. Attach sleeves 1.55 4 0.39 1239 0.65
9. Stitch down sle 0.65 2 0.33 1477 0.54
10. Sew side sea 1.80 4 0.45 1067 0.75
11. Attach cuffs 1.55 4 0.39 1239 0.65
12. Hem bottom 1.70 4 0.43 1129 0.71
13. Inspect 1.50 4 0.38 1280 0.63
14.Iron 1.95 4 0.49 985 0.81
15. Fold, Package 1.75 4 0.44 1097 0.73
Regular Shirts
Laber Content Number of Cycle time Capacity /
Operation (Minutes per shirt) Workers Min/shirt day Utilization
1. Make Collar 3.90 8 0.49 985 0.91
2. Make cuffs 2.00 4 0.50 960 0.94
3. Make sleeves 0.65 2 0.33 1477 0.61
4. Make front 2.50 6 0.42 1152 0.78
5. Make back 1.70 4 0.43 1129 0.80
6. Join shoulders 0.66 2 0.33 1455 0.62
7. Attach collar 1.65 4 0.41 1164 0.77
8. Attach sleeves 1.55 4 0.39 1239 0.73
9. Stitch down sle 0.65 2 0.33 1477 0.61
10. Sew side sea 1.80 4 0.45 1067 0.84
11. Attach cuffs 1.55 4 0.39 1239 0.73
12. Hem bottom 1.70 4 0.43 1129 0.80
13. Inspect 1.50 4 0.38 1280 0.70
14.Iron 1.95 4 0.49 985 0.91
15. Fold, Package 1.75 4 0.44 1097 0.82
Regular Shirts
Laber Content Number of Cycle time Capacity /
Operation (Minutes per shirt) Workers Min/shirt day Utilization
1. Make Collar 3.90 7 0.56 862 0.84
2. Make cuffs 2.00 3 0.67 720 1.00
3. Make sleeves 0.65 1 0.65 738 0.98
4. Make front 2.50 5 0.50 960 0.75
5. Make back 1.70 3 0.57 847 0.85
6. Join shoulders 0.66 1 0.66 727 0.99
7. Attach collar 1.65 3 0.55 873 0.83
8. Attach sleeves 1.55 3 0.52 929 0.78
9. Stitch down sle 0.65 1 0.65 738 0.98
10. Sew side sea 1.80 3 0.60 800 0.90
11. Attach cuffs 1.55 3 0.52 929 0.78
12. Hem bottom 1.70 3 0.57 847 0.85
13. Inspect 1.50 3 0.50 960 0.75
14.Iron 1.95 3 0.65 738 0.98
15. Fold, Package 1.75 3 0.58 823 0.88
Over
Time
Regular Shirts
Laber Content Number of Cycle time Capacity /
Operation (Minutes per shirt) Workers Min/shirt day Utilization
1. Make Collar 3.90 1 3.90 123 0.81
2. Make cuffs 2.00 1 2.00 240 0.42
3. Make sleeves 0.65 1 0.65 738 0.14
4. Make front 2.50 1 2.50 192 0.52
5. Make back 1.70 1 1.70 282 0.35
6. Join shoulders 0.66 1 0.66 727 0.14
7. Attach collar 1.65 1 1.65 291 0.34
8. Attach sleeves 1.55 1 1.55 310 0.32
9. Stitch down sle 0.65 1 0.65 738 0.14
10. Sew side sea 1.80 1 1.80 267 0.38
11. Attach cuffs 1.55 1 1.55 310 0.32
12. Hem bottom 1.70 1 1.70 282 0.35
13. Inspect 1.50 1 1.50 320 0.31
14.Iron 1.95 1 1.95 246 0.41
15. Fold, Package 1.75 1 1.75 274 0.36
per /layer
1.5

Time/prodcut Rate

0.5 min/unit 2

0.008333 hr /unit 120

0.001042 day/unit 960


Layer cutting & R Time layers
60 30 120

Shirts C time capacity


480 0.25 min 1920 800

0.416667

Direct Labor Content for cutting


1 min

25.51

Std shirts 26.51 800 21208


Custom Shirt 25.56 100 2556
900 23764 26.40444