Published Conference Paper

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

ISGTI 2018

7-8 April2018, IIT Delhi, India

Soil Nailing For Failed Slope Stabilization on Hilly Terrain


Mr. Shuvranshu Kumar Rout
Mr. Manos De
Dr. Anup Kumar Mandal
Mr. Biswajit Das
Tata Consulting Engineers Ltd., Pipe Line Road, Sakchi, Jamshedpur, Jharkhand-831001, India
E-mail: skrout@tce.co.in; mde@tce.co.in; akmandal@tce.co.in; biswajitd@tce.co.in

ABSTRACT: In applications where it is required to enhance stability of vertical cut faces or natural slopes, soil nailing
techniques are being increasingly used. The nails improve the ability of soil mass to take care of tensile forces by acting
as reinforcement. From reported literature, it is found that such applications have been made mostly in highway projects
with favourable soil conditions. The advantages can be extrapolated for applications in mine infrastructure projects and
difficult soil conditions with undulated terrain. This paper aims to highlight a unique case on the rehabilitation of a
failed slope in lateritic soil mixed with iron ore fragments and stabilization of 33kV transmission tower foundation
which is situated just edge of the hill slope. This achieved the desired purpose for stabilization of failed slope and
restoration of conveyor operation which is just beneath the hill slope in a shortest possible time. The site specific design
aspects along with modified construction methodologies in difficult geological situations have been reported and
lessons are learned for future implementation.
Keywords: soil nailing; grouting; shotcrete; limit equilibrium method; factor of safety

1. Introduction carrying conveyor. The alignment of the bench was


Conventionally soil nails are used in situations where roughly parallel to the slope of the hill. It was noted at the
vertical excavation faces are required to create time that the rock formation had discontinuities with
necessary working space. Soil nailing techniques with
inward inclination.
appropriate facing element finds wide application in
In the next phase of construction on this hill slope, the
various situations across the world. Not all types of soils
conveyor foundation was constructed by again cutting into
are suitable for application of soil nailing techniques. Of
the hill slope along the conveyor route including the
particular interest to the present study is the application
portion below the tower foundation. The construction
of this technique in laterite which is a highly weathered
activities which required cutting into this hill side had also
soil. Only few references of such studies and
endangered the stability of the foundation for this vital
applications are available (Atefeh and Erwin, 2014).
installation. In order to prevent failure of the excavated
The current study attempts to evaluate the adaptability
slope for creation of the bench, the conveyor contractor
of soil nailing techniques for re-stabilizing failed soil
constructed a gabion wall of height 3m.
mass caused due to landslides in lateritic soil mixed
with iron ore fragments. The intent of this paper is to After one year of operation, initial signs of shallow
present a case study in an application where collapse of failure were noticed just above the gabion wall after
existing slope led to disruption of ongoing plant significant rainfall at project site. The bulging of gabion
operation and endangered the stability of structures boxes was observed in the bottom portion. As a
previously built at top of the slope and mitigation of the protective measure, a stepped random rubble masonry
problem by stabilizing the failed slope through wall was constructed by local contractor just above the
application of soil nailing. gabion wall and backfilled the cut with locally available
fines from mine spoils. Heavy rainfall during the
2. Brief History of Problems retreating period of monsoon had further detrimental
The site is located in an iron ore mines area in eastern effect on the already vulnerable situation. Failure of the
region of India. The property owner had installed a new soil slope caused extensive damage to the conveyor in
ore processing and handling plant at site comprising of operation. The damage was for a length of
long conveyors and junction houses. approximately 30m. The slope failure additionally
There exists a 33kV transmission line tower at the top threatened the stability of 33kV tower foundation which
of the slope of this hill. The 33kv transmission line is is present just at the edge of the slope. The poorly
also crossing the railway lines further downhill of the managed drainage system for the facilities, uphill of this
slope and is connected to state electric grids. The 33kV conveyor location pass through this stretch during rainy
tower is the lifeline of the total operation of plant. The season which further destabilized the soil mass. It was
foundation for this tower was constructed by cutting concluded that RR Masonry wall which was constructed
into the slope and subsequently backfilling the over existing gabion wall could not sustain the earth
foundation pit. pressure and pore pressure developed due to the seepage
Following completion of the new expansion project, water. The typical location of transmission tower and
excavation into the hill side was made by the mine conveyor has been presented in Figure -1.
developer to create bench for installation of material
307
Soil Nailing For Failed Slope Stabilization on Hilly Terrain

4. Design Basis & Formulation of Inputs


There is very little previous available reference of any
successful slope protection scheme applied in such type
of iron-ore rich soils. Detail discussions and literature
survey was done to evaluate the merits and demerits of
slope protection treatments in similar type of conditions.
Based on the available input data, design charts by
FHWA (Federal Highway Administration) was initially
used for the analysis in absence of IS codes.
Subsequently, stability of 33kv tower under various
operational circumstances was established to reach
acceptable level of confidence. Therefore, design aspect
were investigated for different stages throughout the site
progress and inputs collected from drilling time in
different strata, volume of grout consumptions etc.
Accordingly, stability of the slope was assessed under
different operating conditions e.g. variation in nail length
Fig. 1 Project location showing the hill slope with 33kV & spacing, diameter, inclination with varying slope
tower at top and conveyor at bottom along with position profile, varying geotechnical parameters, etc. For
of collapsed RR masonry wall above gabion wall optimum design iterations were continued until the
required minimum factor of safety was obtained.
3. Site Constraints, Geology & Sub-surface Profile Ultimate bond strength of nail and grout was taken from
The disruption of the conveyor system led to shut down design guidelines initially and verified by pullout test
of the mining plant and the operation was required to be results on sacrificial nails on adjacent locations. Stability
restarted on urgent basis. There was no scope for new of slopes are commonly analyzed by established classical
geotechnical investigation at the landslide location. limit equilibrium methods of slope stability analysis
Therefore considering the urgency previous geotechnical
using commercial software package (GeoStudio 2007).
reports of nearby area were considered for design
purpose. The geological formation is of hematite rock. The following Table 2 presents the basic design inputs
The soil layers encountered at site comprise a thin fill for soil nails.
layer of hard silty clay underlain by completely Table-2 Design parameters for soil nails
weathered to highly weathered reddish brown laterite and
rock with steel grey fine grained iron ore mixture. The Item Description Value
input design parameters for sub-soil profile as obtained Vertical wall height, m 7-13
from field and laboratory test results are shown under
Table 1. Nail length, m 4-11

Table-1 Geotechnical parameters for design Nail spacing, m 1-1.3

Grade of nail bar Fe 500


Internal
Unit Cohesion Friction Grade of steel plate Fe 250
Sub-strata weight Angle
(kN/m3) (kN/m2) Grade of grout & shotcrete M 30
(degree)
Drill hole diameter, mm 150
Filled up soil 18 0.5 28 2
Ultimate bond strength, kN/m 80
Residual soil 19 5 30
Weathered rock 22 25 35 5. Challenges in Design Stage
At the start of the design, full length nails were planned
The lateritic soil being of residual formation is naturally in equal grid spacing. However, when drilling started at
of high porosity. The presence of water in the soil mass top layers, full length couldn't be achieved due to collapse
highly aggravates tendency for slope failure and also of holes. This was because of the heterogeneous back fill
impedes slope protection schemes. Parametric study on material in the tower foundation zone. Manually 1m
residual soils with various values of internal friction
casing were pushed to facilitate further drilling. However,
angle and cohesion have already shown that such soil
slopes tend to have probability of collapse when cohesion success was not achieved beyond 4m drilling. Due to
values are less than 10 kN/m2 with factor of safety less presence of large iron ore boulders the equal spacing was
than the acceptable value of 1.5 (Atefeh and Erwin, not maintained both vertically and horizontally. Also, the
2014). top nails had to be drilled with sufficient safe distance
from underground tower foundation. After removal of

308
debris at bottom level, civil, mechanical & electrical
erections for conveyor were started along with nailing.
The bottom row nailing was not feasible due to space
constraint. To compensate the short length top nail a
concrete toe wall with 3m vertical nails was introduced at
bottom portion as additional protection.
Based on continuously changing soil properties, time,
space constraint and all possible construction issues that
arose during and after excavation, various situations have
been analyzed. Results of the minimum 'Factor of Safety
(FOS)' are summarized in tabular form below and
outcome figures are shown in thereafter.
Fig. 3 Prediction of FOS > 1.5 with 8 rows designed
Table-3 Preliminary Cases considered in Design Stage length nail (Case-B)
Method of Analysis
Sl. No.
Fellinious Bishop Janbu Spencer
Case-A 0.47 0.48 0.47 0.47
Case-B 1.57 1.65 1.61 1.64
Case-C 1.72 1.84 1.82 1.84
Case-A: After complete removal of debris from slope
face at one go.
Case-B: Installation of 8 rows of designed length nails
Case-C: Installation of 8 rows of designed length nails
with 1m height RCC toe wall
The factor of safety in Case-A is very low to work under Fig. 4 Prediction of FOS > 1.7 with 8 rows designed
these conditions. To maintain minimum factor of safety length nail and RCC toe wall at bottom (Case-C)
of 1.0, step wise debris removal of 1 to 1.5m depth from
top-down approach was adopted during execution.
Table-4 Additional Cases considered at Execution Stage

Method of Analysis
Sl. No.
Fellinious Bishop Janbu Spencer
Case-D 1.54 1.62 1.57 1.61
Case-E 1.71 1.84 1.78 1.83
Case-D: Installation of 2 rows of short nail & 6 rows of
designed length nails.
Case-E: Installation of 2 rows of short nail, 6 rows of
designed length nails & 1 row of vertical nail with 1m
Fig. 5 Decrease of FOS to1.5 with 2 top rows of short
height RCC toe wall
length and 6 rows of designed length nail (Case-D)

Fig. 2 Prediction of FOS < 0.5 under condition of Fig. 6 Increase of FOS to1.7 with addition of vertical
complete debris removal and without nails (Case-A). nail and RCC toe wall at bottom (Case-E)

309
Soil Nailing For Failed Slope Stabilization on Hilly Terrain

6. Challenges in Construction Methodology The other aspect of nail installation is the insertion of
Soil nailing is generally carried out in top-down approach nails inside the hole. Special care needs to be taken so
with staged excavation. Hence the general approach is to that the nails do not touch the mouth of the drilled hole at
create benches to accommodate drilling & grouting insertion point causing it to collapse. Manual lifting and
operation. The bench heights are restricted to desired insertion of nails causes needless striking of the nail
depths for which the face of excavation can safely remain against the hole face and can create holes to collapse.
unsupported till the drilling & grouting of last row nail. Therefore for long holes and nails at heights, support
The bench heights are also guided by the requirement of system with the help of crane at nail end was deployed to
the nozzle operator to hold the nozzle at an angle normal minimize the hole collapse. Since there was no space to
to the face of the slope. Detail analysis of the convenient operate a crane at this location for both vertical (due to
bench height for nailing and shotcreting operations are active high 33kV transmission line) and horizontal
presented by Kutschke, Tarquinio & Petersen (DFI clearance (due to conveyor and trestles), nail insertion
2007). was carried out manually.
In the present case, the slope reinforcing is carried out on Normal steel reinforcement bars were used for nailing.
an existing failed slope and hence required a different For extra precaution against corrosion, one coat of
approach in planning the execution activities. The galvanization were applied at site.
collapsed soil mass actually provided additional support Similarly, inclined drilling were done for installation of
to the failed slope and was preventing further slide. It was drainage pipes of length 2-3m. The drainage pipes were
decided to take advantage of this mass of collapsed soil to perforated PVC pipes wrapped with non-woven geo-
facilitate the normal top down approach for carrying out textiles over the perforation and end of pipes.
the slope reinforcing work.
6.4 Shotcrete & Grouts
6.1 Anchoring Tower During simultaneous drilling operation for both ends of
The first requirement at the site was to immediately platform, the disturbance to the loose soil mass from the
ensure and enhance the stability of the slope beneath the vibrations caused large soil mass to collapse when the
33kV tower foundation. In order to enhance the stability drilling depth had reached about 3 metres. As indicated
of the tower in this modified profile of the slope, tie-back earlier, the drainage through the soil mass on the slope
structure with massive anchor blocks embedded in soil further aggravated the situation. Therefore, in many
was provided to the tower structure. Additionally sand cases, large quantity of shotcrete was required to fill the
bags were placed on the slope for additional support pockets created by collapsed soil. The same thing
during drilling. happened for grouting operation also. In some places the
grout consumption was very high; about 50%-200%
6.2 Staging Platform, Debris Removal & Bench
greater than the usual grout consumption. The presence
Excavation
of fracture planes or pockets inside the strata which can
Staging platform were erected from limited space at
account for higher grout consumption couldn’t be
bottom, taking support from existing trestles of
quantified accurately even with proper investigation
conveyors. Benches were created with scaffolding
report. Portland cement with plasticizers were used for
material resting on the collapsed debris at bottom. Stages
grouting with water-cement ratio of 0.45.
were created at different levels at intervals corresponding
to convenient operating height of 1.5m. The working
7. Instrumentation
platforms were connected by ramps fabricated from Conventional surveying methods were adopted for any
scaffolding material to allow the drilling machine to movement of ground and displacement of tower
reach the topmost level of the slope. Similarly pedestals. Due to schedule and time constraints, special
construction schedule was compressed by drilling & geotechnical field instrumentation were not installed.
grouting at day time and shotcreteing & scaffolding However, dedicated safety inspection teams were
erection during night time. engaged for 24/7 monitoring of site activity.
8. Conclusions
6.3 Nail & Drainage Pipe Installation
The soil nailing method was successfully implemented at
Due to the non-cohesive nature of the residual soil,
site comprising of lateritic soil mixed with iron ore
undulated surface profile resulted during the drilling
boulders in a constrained area especially with 33kV tower
operation. Modified design approach was adopted by
at top and conveyor at bottom. This achieved the desired
providing one layer of shotcrete on the exposed surface
purpose for stabilization of failed slope and restoration
prior to start of drilling to prevent sloughing of loose soil.
of conveyor operation in a shortest possible time.
This technique was also beneficial to enhance the
Successful implementation of soil nailing work in
stability of the vulnerable soil mass below the 33kV
situation presented in this study was possible through the
tower foundation.
following:

310
i. Detailed analysis and design for the soil nailing
system coupled with micro planning of all site
activities considering various constraints at the
site.
ii. Rechecking and modification of the design
calculations to incorporate site specific design
issues during execution.
iii. Continuous monitoring of site conditions as per
the progress and modifying execution
methodology accordingly.
The major learning from the present case study are
presented herein which will be beneficial for future
design as well as implementation practices.
The solution for slope stabilization should be looked at
holistically considering existing facilities and structures Fig. 8 Step wise debris removal and lowering platform
in the vicinity of the work site. Special attention has to be for smooth movements of drilling machine and resources.
paid to ensure safety and stability of nearby structures in
brown field projects.
Most of instability occurs in hill slope due to inefficient
drainage networks. To avoid such type of failure, an
extensive study of existing drainage networks and
periodical maintenance plans have to be addressed.
In order to facilitate the evaluation of long term risk and
the probable detrimental effect, continuous monitoring of
slope movement and water table is recommended with
installation of appropriate field instrumentation.

9. Acknowledgment
The authors gratefully recognize Tata Steel Limited,
Jamshedpur, India for giving opportunity to Tata
Consulting Engineers to work as "Consultant" in such a
complex brown field project. Similarly, the authors
would like to thank L & T Limited, India for their
continuous support on site specific inputs throughout the Fig. 9 Installation of grouted nails by wagon drilling
project execution. machine after phase wise debris removal from top.

10. Site Photographs


The site photographs showing site conditions and
construction stages are enclosed.

Fig. 10 Drilling and placing of perforated PVC drainage


Fig. 7 Project site of 33kV tower with damaged conveyor pipes and wire mesh for shotcreting layer.
due to collapse of gabion & random rubble masonry wall.

311
Soil Nailing For Failed Slope Stabilization on Hilly Terrain

72

Fig. 11 Application of shotcrete layer with additional Fig. 14 Final finished slope face showing 33kV tower at
cavity filling by concrete, small boulders. top and restored conveyor along with toe wall at bottom.

References
Atefeh, A. & Erwin, Oh. (2014) Strength Parameter
Selection in Stability Analysis of Residual Soil
Nailed Walls. International Journal of Geomate,
Vol. 7, No.1, Sl. No. 13.
Babu, G.L.S. (2009) Case Studies in Soil Nailing,
Indian Geotechnical Conference, Guntur, India.
Babu, G.L.S. Rao, R.S. & Dasaka, S.M. (2007)
Stabilization of Vertical Cut Supporting a Retaining
Wall Using Soil Nailing: A Case Study.
Ground Improvement, 11, No. 3, Page Nos. 157–
162.
FHWA, (1994) Soil Nailing Field Inspector Manual -
Soil Nail Walls. FHWA-SA-93-068, U.S.
Department of Transportation, Federal Highway
Fig. 12 Bottom debris removal & installation of vertical
Administration, Washington D.C., USA.
nails for RCC toe wall between slope toe and conveyor.
FHWA, (1998) Manual for Design & Construction
Monitoring of Soil Nail Walls. FHWA-SA-96-096R,
U.S. Department of Transportation, Federal
Highway Administration, Washington D.C., USA.
FHWA, (2003) Geotechnical Circular No.7- Soil Nail
Walls. FHWA-IF-03-017, U.S. Department of
Transportation, Federal Highway Administration
Washington, D.C., USA.
Kutschke, W.G. Tarquinio, F. S. & Petersen, W.K.
(2007) Practical Soil Nail Wall Design and
Constructability Issues, DFI’s 32nd Annual
Conference on Deep Foundations, Nicholson
Construction Company, Colorado Springs,
Colorado, USA.
Premalatha, K. Kumar, M.M. & Babu, D.M. (2009)
Analysis and Design of Nailed Soil Wall-A Case
Fig. 13 Final layer of shotcrete along with provision of Study. Indian Geotechnical Conference, Guntur,
top surface drainage to channelize surface run-off water. India.

312

You might also like