Professional Documents
Culture Documents
Nitrogen Removal From Synthetic Wastewater by Simultaneous Nitrification and Denitrification (SND) Via Nitrite in An Intermittently-Aerated Reactor
Nitrogen Removal From Synthetic Wastewater by Simultaneous Nitrification and Denitrification (SND) Via Nitrite in An Intermittently-Aerated Reactor
Nitrogen Removal From Synthetic Wastewater by Simultaneous Nitrification and Denitrification (SND) Via Nitrite in An Intermittently-Aerated Reactor
145±154, 1999
# 1998 Elsevier Science Ltd. All rights reserved
Printed in Great Britain
PII: S0043-1354(98)00159-6 0043-1354/98 $ - see front matter
1
Environment Research Center, Korea Institute of Science and Technology (KIST), P.O. Box 131
Cheongryang, Seoul, South Korea and 2Department of Environmental Engineering, Seoul National
Polytechnic University, Gongneung-Dong, Nowon-Ku, Seoul, South Korea
AbstractÐAn intermittently aerated and decanted single-reactor process was proposed and some key
control parameters investigated for nitrogen removal from wastewater by simultaneous nitri®cation and
denitri®cation (SND) via nitrite. Two types of synthetic wastewater with acetate as the main carbon
source, and chemical oxygen demand (COD):nitrogen (N) ratios of approximately 5:1 and 10:1 were
used. For both types of wastewater the average COD removal eciency reached above 95%, and under
optimal conditions nitrogen removal eciency also reached above 90%. This process consisted of
72 min aeration, 48 min settling and 24 min euent decanting. In¯uent wastewater was fed from the
bottom of the reactor, and did not require a separate mixing phase. In this process, nitritation (1st step
of nitri®cation) was induced but nitratation (2nd step of nitri®cation) was eectively suppressed and
denitri®cation was carried out using nitrite. Most important parameters for eective SND via nitrite in
the proposed process were: (1) the increase rate and the minimum and maximum dissolved oxygen
(DO) concentration during the aeration period, (2) length of one cycle, and of aeration per cycle, taking
advantage of the lag-time of nitrite-oxidizers behind ammonia-oxidizers when adjusting from anoxic/an-
aerobic to aerobic condition, and (3) close contact between the mixed liquor suspended solids (MLSS)
in the reactor and the in¯uent wastewater under anoxic/anaerobic condition. During the aeration
period, DO concentration dropped initially reaching the minimum value after several minutes, and then
rose in 2nd-order fashion. The optimal maximum DO concentration (at the end of the aeration period)
for nitrogen removal was determined to be around 2.0±2.5 mg/l in this proposed process. # 1998 Else-
vier Science Ltd. All rights reserved
Key wordsÐnitrogen removal, simultaneous nitri®cation and denitri®cation (SND), nitrate accumu-
lation, nitritation, nitratation, intermittently decanted extended aeration (IDEA)
during denitri®cation; (2) 63% higher rate of deni- with intermittent contact to high FA levels (5 mg
tri®cation; (3) 300% lower biomass yield during an- NH3±N/l) in the ®rst cell of a four-cell system.
aerobic growth; and (4) no apparent nitrite toxicity However, nitrite build-up could not be sustained
eects for the microorganisms in the reactor. inde®nitely, due to the acclimation of the
Abeling and Seyfried (1992) discovered in their Nitrobacter to FA. Wong-Chong and Loehr (1978)
half-technical experiences, that saving cost was also observed that the Nitrobacter acclimated to FA
possible with the reduced oxygen demand. For could tolerate concentrations as high as 40 mg
nitritation only 75% of the oxygen was required NH3±N/l, while unacclimated ones were inhibited
compared to that of the complete oxidation to at concentrations of 3.5 mg NH3±N/l. Many other
nitrate. researchers found out similar results. Ford et al.
SND is also eective in maintaining neutral pH (1980) reported total inhibition of nitri®cation ac-
level in the reactor, without the addition of external tivity at FA levels of 24 mg NH3±N/l, but noted
acid/base source. This is important since a narrow that system recovery was possible, even at levels as
optimal range between pH 7.5±8.6 is known to exist high as 56 mg NH3±N/l. Cecen and Gonenc (1994)
for the nitrifying bacteria. During nitri®cation alka- noted, in the batch start-up phase, the combined
linity is consumed, but alkalinity is produced during eect of high ammonia and high pH (8.5) inhibited
denitri®cation. The optimal pH lies between 7 and Nitrobacter and led to accumulation of nitrite.
8 for denitri®cation with dierent optimums for Mauret et al. (1996) showed that high FA concen-
dierent bacterial populations. tration inhibits Nitrobacter, in the range of 6.6 and
However, high nitrite build-up may, in many 8.9 mg NH3±N/l. Balmelle et al. (1992) reported
cases, be harmful to the operation of the waste- that the inhibition eect of nitratation could be
water treatment plant, and therefore its concen- observed at concentrations as low as 1 mg NH3±N/l.
tration in the euent must be kept low due to its Anthonisen (1976) found out values of 0.1±1.0 mg
toxicity to some species of ®sh; therefore, SND via NH3±N/l.
nitrite must accompany far-reaching denitri®cation. Abeling and Seyfried (1992) stated that in order
This investigation proposes a simple, single-reac- to attain the highest nitritation rate, it was decisive
tor nitrogen-removal process utilizing SND via to prevent the inhibition of the Nitrosomonas
nitrite, without a separate mixing period, evaluates caused by FA. The FA concentration necessary for
its performance, and suggests some key control par- the inhibition of Nitrobacter must be kept low
ameters for eective operation. The design of the enough to ensure that the inhibition of nitritation
proposed process is based on the following litera- does not also take place. At pH = 8.5 and
ture review; key control parameters and their opti- T = 208C, the optimal FA concentration for maxi-
mal values were determined in the laboratory. mum nitritation and minimum nitratation was
found to be around 5 mg NH3/l (Abeling and
Seyfried, 1992). On and after approximately 7 mg
FACTORS FOR NITRITE ACCUMULATION DURING
NITRIFICATION
NH3/l an inhibition on nitritation could be noticed.
At concentrations of around 20 mg NH3/l there was
Some of the best works investigating nitrite very little nitri®cation activity. Limits to prevent
build-up during nitri®cation were performed by nitritation inhibition had been found out in batch
Anthonisen (1976), Sutherson and Ganczarczyk tests which ranged between 10 and 150 mg NH3/l
(1986), Jayamohan and Ohgaki (1988) and Hanaki (Anthonisen, 1976). Also Neufeld et al. (1980) con-
and Wantawin (1990), which focused on a number ®rmed the beginning of nitritation inhibition at
of factors, such as the free ammonia (FA) concen- 10 mg NH3/l.
tration, the free hydroxylamine (FH) concentration,
the pH, the temperature, and the dissolved oxygen Temperature
(DO) concentration, on the transient build-up of Balmelle et al. (1992) showed that in spite of con-
the nitrite ion. centration of FA normally inhibiting for the
Nitrobacter of between 2 and 5 mg NH3±N/l, the
High free ammonia (NH3) concentration Nitrobacter was active over a range of temperature
According to the research by Anthonisen (1976), between about 10 and 208C. Under these con-
the non-ionized forms of the ammonium and nitrite ditions, nitrite build-up remained low, since the
have Ð as ammonia (NH3) and nitrous acid eect of the Nitrobacter activation by temperature
(HNO2) Ð an inhibition eect on both the prevailed over its inhibition by FA. On the other
Nitrosomonas and the Nitrobacter. The Nitrobacter hand, beyond a temperature of 20±258C, a slowing
react more sensitively so that concentration of NH3 of the nitratating activity was observed together
in relatively low range is sucient for inhibition. with an activation of the nitritating activity, which
Abeling and Seyfried (1992) reported that concen- passes through a maximum at 258C. These results
tration of 1±5 mg NH3/l inhibited nitratation but were in agreement with the data of Quinlan (1986),
not the nitritation. In the research of Turk and that showed high Nitrobacter activity for tempera-
Mavinic (1986, 1987) nitrite build-up was achieved ture below 158C. With respect to Nitrosomonas
Nitri®cation and dentri®cation via nitrite 147
under these conditions, the inhibiting eect of FA the microorganisms in direct contact with the in¯u-
was preponderant for temperature higher than ent wastewater in oxygen-de®cient condition to
258C. This result con®rmed that of Anthonisen induce contact with high concentration of FA and/
(1976), but fairly disparate observations had been or FH (factors1 and 5); (4) raise the pH (factors 1
found in the literature, notably those of Ford et al. and 5); (5) add hydroxylamine to the reactor (factor
(1980) which suggested the optimal temperature 5); and (6) maintain the reactor temperature near
range between 30 and 368C. 258C (factor 2).
Turk and Mavinic (1986) observed a lag time in The following cyclic activated sludge process con-
nitratation. Even with a bacterial population con- sisting of three dierent periods (Fig. 1) was pro-
taining Nitrobacter acclimated to FA, nitritation posed. It is a modi®ed form of an intermittently
rates lagged nitratation rates following the exit decanted extended aeration (IDEA) process (®rst
from the anoxic cell and entering the aerobic cell, developed by the Department of Public Works and
resulting in a temporary, but signi®cant, accumu- Services, NWS, Australia in 1965).
lation of nitrite which lasted for several hours in ``Anoxic'' is de®ned, in this process, as the state
the aerobic cell. Senanyake (1982), and Turk and or condition where denitrifying bacteria carry out
Mavinic (1986) have reported that the extension of denitri®cation utilizing nitrite and/or nitrate as elec-
aeration time alleviates stress on the nitrite oxidizers tron acceptors, independent of the DO concen-
and results in the loss of nitrite build-up. Duration tration in the surrounding environment. Such
of aeration time was found to be inversely related condition may take place in the entire water body
to the degree of nitrite build-up. of the reactor during the initial aeration phase, and
in the settling/settled sludge layer during the settling
Low DO concentration during aeration phase. ``Anaerobic'' condition in this process takes
Cecen and Gonenc (1994) reported that nitrite ac- place inside the settled sludge layer after all the
cumulation reached a considerable degree at DO to nitrite and nitrite are used up as electron acceptors
FA concentration ratios lower than 5 during nitri®- inside the layer. ``Aerobic'' condition takes place in
cation, and the formation of nitrate was inhibited. the reactor after some time has elapsed into the
No nitrite occurrence was encountered when this aeration period-denitri®cation is suppressed due to
ratio exceeded 5, which implied that oxygen limi- the rising DO concentration and nitri®cation takes
tation lead to nitrite accumulation. Therefore, eec- place.
tive nitritation might be achieved by supplying less As shown in Fig. 1, the in¯uent wastewater is fed
air during nitri®cation. constantly from the bottom throughout the cycle.
During the settling and decanting periods oxygen is
Free-hydroxylamine (FH) concentration de®cient, and the Nitrobacter are in direct contact
Yang and Alleman (1992) concluded that the DO with the FA in the in¯uent wastewater, which
level alone did not appear to be the dominant fac- theoretically has a high probability to be converted
tor behind nitrite build-up, and its correlation with to FH by the Nitrosomonas species. The settling/
free ammonia (FA) concentration alone was also settled sludge acts as an anoxic reactor where deni-
erratic. On the other hand, hydroxylamine tri®cation takes place. When the aeration period of
(NH2OH/NH3OH+), an intermediate in nitri®ca- the subsequent cycle starts, the condition in the
tion by Nitrosomonas, was found to inhibit nitrata- reactor is anoxic even with the added air; it takes
tion by the Nitrobacter. Indeed, hydroxylamine some time for the DO level to rise high enough to
appeared likely to accumulate in a nitrifying system suppress denitri®cation. Denitrifying activity is not
with high NH3/NH+ 4 concentration, de®cient oxy- completely suppressed, and the converted nitrite
gen, and high pH. This research showed that the and nitrate from nitri®cation with the added oxygen
presence of unionized or the so called free hydroxy- will be denitri®ed-thus the simultaneous nitri®cation
lamine (FH) fraction (as opposed to ``total'') and denitri®cation. Therefore, this modi®ed IDEA
appeared to have a consistent correlation with low process takes advantage of the non-instantaneous
nitratation activity. FH was believed to be a major, transition from anoxic/anaerobic to aerobic con-
if not principal, factor behind nitrite build-up in the dition of the microorganisms. Such alternating
batch nitrifying systems. between anoxic/anaerobic and aerobic condition is
necessary to take advantage of the lag-time of the
Process guidelines for suppressed nitratation nitrite-oxidizers behind the ammonium-oxidizers.
Therefore, to achieve eective SND via nitrite, it Such lag time may be dierent for each species of
is necessary to (1) use simultaneous and/or alternat- denitrifying bacteria, and certain species may carry
ing nitri®cation/denitri®cation process in the same out denitri®cation throughout the entire cycle. The
reactor (factors 1, 3 and 4 above); (2) maintain low length of the aeration period should be long enough
DO during aeration (factors 1, 4, and 5); (3) keep for eective COD removal, nitri®cation and denitri-
148 Hyungseok Yoo et al.
Fig. 1. Modi®ed IDEA process description and operation strategy: (a) three periods of the process; and
(b) length ratios of the three periods, corresponding conditions and the ideal DO pattern (determined
in this experiment).
®cation, but short enough to prevent the adaptation Experimental set-up and reactor operation
of nitrite-oxidizers to the aerobic environment. The two modi®ed IDEA reactors were variable-volume,
Ideal dissolved oxygen (DO) level curve for one and seeded with a grab sample of mixed liquor from the
cycle is shown in Fig. 1(b). Minimum DO concen- aerobic basin of the Kwangdongli Sewage Treatment
tration of the aeration period is achieved several Plant (Kyung-Gi-Do, Korea). They were operated for
122 days. Sample analysis commenced after approximately
minutes into the period. Intuitively, optimal average 22 days of operation and continued for the next 100 days.
and maximum DO concentration levels exist for The reactors had circular bottom with diameter of 20 cm,
nitrogen removal in this process. DO levels above and their maximum working volume was 17 l. Discharge
these values will yield too much nitrite/nitrate and sampling ports were located at dierent levels. The
top of the reactors was open to air. The reactors were
(NOx) in the euent, whereas levels too low will operated in parallel, with varying hydraulic retention times
induce a high level of NH3/NH+ 4 . It was one of the (HRT's), and sludge retention times (SRT's). The in¯uent
purposes of this experiment to determine such opti- wastewater was kept in a refrigerator (at 48C). The reactor
mal DO levels. This proposed process does not temperature was maintained at 22±278C.
require a separate mixing period, since the settling Cyclic operation as described in Fig. 1 was controlled
by a programmable logic controller (PLC). Aeration
and decanting periods, and the initial portion of the period was set at 72 min, settling period at 48 min, and
aeration period are anoxic/anaerobic treatment decanting period at 24 min for the reactors; the duration
phases. The amount of air supplied is such that the of each cycle was 144 min (2.4 h) i.e. 10 cycles per day.
DO level does not rise too quickly into the aeration 10 l of wastewater was fed to each reactor everyday, and
period.
Table 1. Composition of the two types of in¯uent wastewater
Added compounds In¯uent wastewater 1 In¯uent wastewater 2
(per l in¯uent) (mg) (mg)
MATERIALS AND METHODS
CH3COONa ÿ 256.41
Composition of the synthetic wastewater CH3COONH3 240.88
KH2PO4 43.94
Two types of synthetic wastewater, made accord- NaHCO3 125.00
ing to Table 1, were fed to reactors 1 and 2. CaCl2 10.00
FeCl2 0.375
The dierence between in¯uent wastewater 1 and MnSO4 0.038
2 was the COD/NH4±N ratio Ð approximately 5:1 ZnSO4 0.035
and 10:1 Ð and COD/phosphate ratio-approxi- MgSO4 25.00
Yeast extract 50.00
mately 10:1 and 20:1, respectively.
Nitri®cation and dentri®cation via nitrite 149
Fig. 4. Euent nitrogen compounds and DO concentration of reactor 1 (a) and reactor 2 (b). (``NH3 ±
N'' in this Figure is technically the sum of NH3±N and NH+
4 ±N.)
Dev. = 2.4) for reactor 2, respectively. Figure 3 According to Fig. 4, high concentration of nitrite
shows the euent suspended solids (SS) and SCOD resulted when the maximum and minimum DO con-
concentration. centration in the reactors was relatively high. High
Scum ¯oated on the water surface of both reac- NH3/NH+ 4 concentration was observed when the
tors; an attempt was not made to remove the scum. maximum and minimum DO concentration was
In full-scale operation, decanting system that separ- relatively low. Generally, the minimum DO concen-
ates the scum from the euent should be installed. tration was below 0.4 mg/l. From Fig. 4, SND via
In this experiment, euent samples contained the nitrite seemed very successful. Also, the initial guess
scum and exhibited relatively high SS concen- of the existence of optimal DO levels for N-removal
tration. proved to be correct. pH was never intentionally
raised or the addition of hydroxylamine made to
Nitrogen removal, and changes in DO, HRT and suppress nitratation; initially it was thought that
SRT these steps would be necessary. To con®rm the
SND via nitrite, NOx (sum of NOÿ ÿ
2 and NO3 ) con-
Figure 4 shows the euent nitrogen (N) com-
pounds' concentration with the minimum and maxi-
mum DO concentration for reactors 1 and 2.
Surprisingly, nitrite accumulation was very success-
ful in both reactors from day 1. For many days,
high concentration of nitrite was observed in the
euent, but low nitrate concentration. A corre-
lation between the euent nitrite concentration and
DO levels was observed.
1±25 25 39 31 25
Fig. 5. Nitrite concentration for reactor 1 (W) and reactor
26±60 25 45 31 45
61±100 13 45 17 45 2 (.), and nitrate concentration for reactor 1 (r) and reac-
tor 2 (w), at the end of aeration period.
Nitri®cation and dentri®cation via nitrite 151
Fig. 6. Cyclic study of reactor 1 on day 87. (``NH3±N'' is the sum of NH3±N and NH+
4 ±N.)
centration was measured at the end of the aeration be the accurate way to describe the pattern of DO
period. level. During settling and decanting periods, DO
Figure 5 shows high concentration of nitrite at level in the upper region of the reactor dropped
the end of aeration period in both reactors. Nitrite quickly reaching 0.4 mg/l by the end. Figure 6
oxidation was eectively suppressed in this pro- showed the ideal pattern of DO concentration; it
posed process. dropped and then started to rise several minutes
into the aeration period, and passed 1.0 mg/l at
Cyclic study
minute 38, about half-way into the period. Thus,
Figure 6 shows data from one of the cyclic stu- during the initial phase, mostly denitri®cation took
dies, which showed ideal DO pattern described in place indicated by the drop and low concentration
Fig. 1. All samples for the cyclic studies were col- of nitrite, and slight increase in pH. NH3/NH+ 4 ±N
lected by immersing 50 ml beaker slightly into the concentration stayed constant at around 6.5 mg/l
water surface and extracting about 20 ml. The
during the initial phase, but then dropped as the
samples were then immediately ®ltered using
DO concentration rose, and disappeared when the
0.45 mm ®lter paper. DO level changed sensitively in
DO concentration was between 1.5±2.0 mg/l. On
all cyclic studies.
the contrary, nitrite concentration rose with the DO
In Fig. 6, DO concentration rose in 2nd-order
fashion after about 5 min into the aeration period, level, indicating nitri®cation was active in the later
reaching 2.5 mg/l by the end. The median DO level, portion of the aeration period. Nitrite appeared as
de®ned as the mid-value between the minimum and the DO level passed through 1.0 mg/l and its con-
maximum DO values in a given aeration period, centration stayed high until the end. Due to nitri®-
was 1.3 mg/l in this cyclic study. To obtain the true cation, pH dropped slightly. Nitrite concentration
average DO concentration, integration must be per- rose steadily until the end of aeration. After several
formed for the DO curve during the aeration period minutes into the settling period, nitrite concen-
and then division by the time; however, such inte- tration started to drop. During the decanting
gration was not performed in this experiment. period, NH3/NH+ 4 appeared again due to diusion
Using the average DO concentration together with of the in¯uent wastewater's NH3/NH+ 4 . About
the minimum and maximum concentration would 1.3 mg/l of nitrite and 0.4 mg/l of NH3/NH+ 4 was
Fig. 7. Euent NO3±N (*), NOx±N (R), and (NH3+NOx)±N (w) concentrations of reactors 1 (a) and
2 (b) versus median DO levels (data from entire operation). (``NH3±N'' in this Figure is the sum of
NH3±N and NH+ 4 ±N. ``NOx ±N'' is the sum of NO2 ±N and NO3 ±N.)
152 Hyungseok Yoo et al.
Fig. 8. The eect of DO level on speci®c nitri®cation and denitri®cation rates for reactor 1 during days
61±100. (Dotted lines show the intuitive pattern.)
observed in the euent of this speci®c cycle indicat- the opposite trend occurred when the DO value was
ing eective N-removal. low. The median DO value of 1.0±1.5 mg/l seemed
From the cyclic studies, the importance of DO to be optimal, implying that if the minimum DO
level was realized. DO level should be controlled level was in the range of 0.0±0.4 mg/l, the maximum
two-dimensionally: (1) the maximum level of DO DO level should be in the range of 1.6 and 3.0 mg/l.
during the aeration period, and (2) the increase rate It is generally known that DO concentration above
of the DO level-aerobic condition should not be 1 mg/l is essential for nitri®cation; if the DO level is
created too quickly or slowly. Therefore, aeration lower, oxygen becomes the limiting factor and nitri-
system capable of such DO control must be im- ®cation slows or ceases. On the contrary in denitri®-
plemented in the full-scale plant of this proposed cation, high DO level will suppress the necessary
process. The aeration system should be easy to enzyme system. Thus, when SND via nitrite
install since there are four control parameters of air becomes the focus, controlling the DO level is criti-
supply: (1) DO level sensor, (2) ¯owmeter installed cal to balance the degrees of nitri®cation and deni-
at the air pump, (3) air-supply valve, and (4) ¯exi- tri®cation, and the resulting levels of N compounds
bility in the length of the aeration period. in the euent.
With certain portion of the data, speci®c nitri®ca-
Determining the optimal DO concentration for nitro- tion, denitri®cation and N-removal rates were cal-
gen-removal culated to study the eect of dierent DO levels on
The eect of maximum and minimum DO con- the relative degrees of nitri®cation and denitri®ca-
centration on the euent N compounds is shown in tion. For such study to be valid, MLSS concen-
Fig. 7; the median DO concentration is the x-axis. tration must be constant. Therefore, data from
According to Fig. 7, when the median DO level reactor 1 during days 61±100 (Fig. 2) were used.
was high, NOx concentration was high and NH3/ Figure 8 shows that nitri®cation rate increased
NH+ 4 was mostly removed from the euent, and with the DO concentration, whereas the denitri®ca-
tion rate decreased. Figure 9 shows the speci®c N-
removal rate at various DO levels. The optimal me-
dian DO level for nitrogen removal was 1.3 mg/l.
the in¯uent 41.3 mg/l NH3/NH+ 4 ±N at 258C should 1.2 mg/l. For reactor 2, maximum FA concentration
yield 0.07 mg/l NH3±N at pH = 6.5, 0.23 mg/l at was 0.58 mg/l NH3 (0.48 mg/l NH3±N) in the eu-
pH = 7.0, and 0.71 mg/l at pH = 7.5; so in reactor ent, and the DO level must be lower than 2.9 mg/l
1, NH3±N concentration should not exceed 1.0 mg/l for the ratio to be below 5. DO level in both reac-
at any time unless the pH reaches 7.65; such pH tors changed throughout the cycle as well as from
was never recorded. For reactor 2, the in¯uent day to day. The calculated DO levels (as reference
41.4 mg/l NH3/NH+ 4 ±N at 258C should yield points) suggest that DO:FA ratio was below 5 more
0.71 mg/l NH3±N at pH = 7.5, and 1.40 mg/l at than half of the time in both reactors.
pH = 7.8 which was the maximum pH recorded. The most in¯uential factor was believed to be the
Such result implies that the reported values by lag-time of nitrite-oxidizers behind ammonia-oxidi-
Abeling and Seyfried (1992), Turk and Mavinic zers during the transition from anoxic/anaerobic to
(1986, 1987), Wong-Chong and Loehr (1978), Ford aerobic condition. Turk and Mavinic (1986) stated
et al. (1980), and Mauret et al. (1996) for the FA such lag-time to be ``several hours'' but did not pro-
level inhibiting nitratation was not reached in either vide a speci®c numerical value. To study the eect
of the reactors. Only the values reported by of the lag-time, on day 96, aeration period in reac-
Balmelle et al. (1992) at 1 mg NH3±N/l, and tor 1 was extended for 330 min (the normal length
Anthonisen (1976) at 0.1±1.0 mg NH3/l were close had been 72). DO level was controlled at approxi-
to the levels observed in our experiment. Inhibition mately 2.5 mg/l by adjusting the air ¯owmeter.
eect of FA was maximum in the region of in¯uent
In¯uent wastewater was fed continuously, but the
feed at the bottom of the reactor, especially during
euent was not decanted; the water surface level
settling and decanting periods. Hydroxylamine was
continued to rise. All other experimental settings
not measured in this experiment. Thus, correlation
stayed the same.
between hydroxylamine concentration and nitrita-
72 min, the normal length of aeration, was ade-
tion/nitratation activity cannot be stated in numeri-
quate for eective COD and N-removal (Figs 3 and
cal terms. However, hydroxylamine was never
4). In Fig. 10, normally the aeration period should
added to the in¯uent or to the reactors, as initially
thought necessary to achieve SND via nitrite. have ended at minute 77. After minute 77, pH con-
Theoretically, hydroxylamine had high probability tinued to drop but never fell below 6.5; ammonia
of build-up (by the Nitrosomonas) in the settled did not appear and nitrite concentration increased
sludge during settling and decanting periods due to indicating on-going nitri®cation. Nitrate concen-
de®cient oxygen, and could have suppressed nitrata- tration rose as the aeration continued indicating
tion irreversibly. that (1) the nitrite-oxidizers were present in the
Temperature was in the range of 22±278C during reactor, and (2) they were adjusting to the aerobic
the entire operation, inducing maximum nitritation environment. Substantial portion of nitrite-oxidizers
activity. Maximum nitratation activity is expected could not adapt to the aerobic environment in the
in the temperature range below 158C. 72 min of normal aeration.
DO to FA ratio was calculated. Cecen and It was concluded that the active nitritation and
Gonenc (1994) suggested that below the ratio of 5, suppressed nitratation was caused by the combined
nitrite accumulation was high and the formation of eect of all the factors reviewed, and the most im-
nitrate inhibited. For reactor 1, maximum FA con- portant one was the lag-time of nitrite-oxidizers
centration in the euent was 0.20 mg/l NH3±N when transitioning from the anoxic/anaerobic to
(calculated previously), which corresponded to aerobic environment. The investigation to determine
0.24 mg/l NH3. For the DO to FA (NH3) ratio to exactly to what degree each of the factors was in¯u-
be below 5, the DO level must be lower than ential would be the subject of future research.
154 Hyungseok Yoo et al.