Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 44

DAFTAR HARGA SATUAN BAHAN DAN SEWA ALAT

No. Bahan Sat H.Satuan No. Bahan Sat H.Satuan


1 Kayu balok klas I M3 10,150,000
2 Kayu papan klas I M3 9,600,000 Upah Tenaga Kerja Sat
3 Kayu balok klas II M3 3,400,000 55 Pekerja OH 138,077
4 Kayu papan klas II M3 3,400,000 56 Tukang kayu OH 158,789
5 Kayu balok klas III M3 1,000,000 57 Tukang batu OH 158,789
6 Kayu papan klas III M3 1,500,000 58 Tukang besi/pipa OH 158,789
7 Kayu balok klas IV M3 1,000,000 59 Tukang cat OH 158,789
8 Kayu papan klas IV M3 1,000,000 60 Tukang gali OH 158,789
61 Kepala Tukang OH 173,978
9 Batu belah M3 168,000 62 Mandor OH 185,025
10 Batu koral/split 1/2 M3 278,000
11 Conblock Bh 9,500 63 Minyak bekisting L 40,000
12 Hebel 7.5cm Bh 8,190 64 Plywood 9mm Lbr 104,000
13 Pasir beton M3 225,000 65 Plint keramik 5 x20 Bh 120,000
14 Pasir pasang M3 210,000 66 Paku asbes gel Kg 38,000
15 Pasir urug M3 215,000 68 Besi hollow 40x40x2 Btg 74,000
16 Sirtu M3 200,000 69 Paku 5,7,10 Kg 40,000.00
17 zincalum Lbr 113,000 70 Besi Angker baut-20cm Bh 67,000.00
18 Bubungan nokstel Bh 70,200 71 Seng BJLS 30 lbr 90 M' 113,000.00
72 Kayu dolken dia 7cm Btg 41,400.00
19 Lem putih Fox Kg 24,000 73 Kaca polos 3mm M2 94,500.00
20 Lem Aibon Kg 15,000 74 Plywood 4mm Lbr 66,000.00
21 Semen PC Kg 1,950 75 Tripleks Lbr 45,000.00
22 Semen warna Kg 15,000 76 Seng gelombang Lbr 113,000.00
23 Engsel pintu Bh 32,400 77 Menie Kg 67,000.00
24 Engsel jendela Bh 32,400 78 Bambu dia 8cm Btg 18,000.00
25 Kunci tanam 2slag Bh 167,000 79 Air Lbr 800.00
26 Kunci Toilet-Alpha Bh 14,100 80 Ampelas Lbr 5,000.00
81 Kwas cat 3" Bh 13,000.00
27 Keramik dind 20x20 Doos 59,000 82 Sealant (silikon) Tube 34,000.00
28 Keramik lantai 30x30 Doos 85,000 83 Hak angin jendela Bh 44,000.00
29 zincalum Lbr 113,000 84 Kni PVC 4" Bh 33,000.00
30 Harfleks 4mm 120x240 Lbr 100,000 85 Kni PVC 6" Bh 67,000.00
31 Pipa PVC 8" tipe AW Btg 570,000 86 Saklar skw Broco Bh 77,000.00
32 Pipa PVC 6" tipe AW Btg 326,000 87 Stopkontak skw Broco Bh 77,000.00
31 PVC 4"-tipe AW Btg 268,000 88 Box MCM 3 group Unit 467,000.00
32 PVC 3" Btg 165,000 89 kabel NYM 3x1,5mm2 Roll 600,000.00
33 PVC 2" Btg 55,000 90 Slot unt pintu Bh 25,000.00
34 PVC 1" Btg 41,800 91 Slot unt jendela Bh 25,000.00
35 PVC 3/4" Btg 30,300 92 Panel Pembagi (SDP) Unit 120,000.00
36 PVC 1/2" Btg 22,000
37 Kran air 1/2" Bh 40,000
38 Stopkran 3/4" Bh 40,000
39 Socket PVC 8" Bh 31,200
40 Socket PVC 6" Bh 31,200 93 Sewa mixer beton 0.3 H 120,000.00
41 Reducer 8" - 6" Bh 90,000 94 Sewa crane 10TON H 6,500,000.00
39 Kitchenzink Unit 175,000 95 Sewa tackel &tripot 5 T H 567,000.00
40 Bak air Fiber 60x60 Unit 250,000 96 Sewa Dumptruck 10T H 450,000.00
41 Closet jongkok INA Unit 240,000 97
42 Sealtape ledeng Bh 20,000 98
43 Lem PVC Tb 20,000 99
44 Floor drain stainl Bh 55,000 100
45 Tanki air 500L Excel Bh 2,000,000
46 Kusen & pintu PVC set 250,000

47 Besi beton Kg 12,800


48 Kawat beton (benrat) Kg 28,000
49 Paku tripleks Kg 33,000
50 Plamuur tembok Kg 25,000
51 Cat tembok (Catylac) Kg 120,000
52 dempul kayu Kg 80,000
53 Cat minyak (Seiv) Kg 80,000
54 Plitur jadi Kg 65,000
Tinner A Kg 40,000
REKAP HARGA SATUAN PEKERJAAN

No. Jenis Pekerjaan Satuan AHSP


1 Pembersihan lahan M2 27,671
2 Pembuatan pagar pengaman M' 416,356
3 Pekerjaan Direksikit M2 1,145,227
4 Pasang pagar sementara seng gelombang M' 208,178
5 Pasang bouwplank M' 72,182
6 Galian Tanah M2 129,820
7 Urugan tanah padat M3 238,974
8 Urugan pasir padat M3 361,528
9 Pasang batu kosong/aanstamping M3 573,731
10 Pasang pondasi batu belah 1PC:5PS M3 1,121,007
11 Sloof dan kolom praktis beton 20MPa M3 6,721,568
12 Pasang lantai beton tumbuk 1:3:5 tebal 5cm M2 1,082,055
13 Pasang bekisting ground reservoir M2 597,814
14 Cor beton ground reservoir K200 M3 -
15 Plesteran dinding dan beton 1PC:3PS M2 160,323
16 Pasang dinding bata 1PC: 3PS M2 -
17 Pasang dinding bata 1PC:5PS M2 -
18 Plesteran Dinding 1PC:5PS M2 103,434
19 Acian dinding M2 -
20 Pas. Kusen kayu klas I M3 9,851,198.28
21 Pas. Pintu teakwood rangka diekpose Daun -
22 Pas. Daun jendela/pintu kaca rangka kayu M2 648,853.10
23 Pas kunci tanam 2 slag Bh 438,062.13
24 Pas. Kunci handel bulat Bh -
25 Pasang engsel untuk pintu Bh -
26 Pasang engsel untuk jendela Bh -
27 Pasang kaca polos 3mm M2 162,755.25
28 Pasang slot pintu Bh 31,250.00
29 Pasang hak angin kait untuk jendela Bh 55,000.00
30 Pasang rangka plafond kayu klas II M2 130,346.03
31 Pasang plafond seratsemen 4mm M2 170,214.58
32 Pasang plafond tripleks 4mm M2 23,525.74
33 Pas list plafond profil kayu M' -
34 Pengecatan dinding skw Catylac M2 72,139.66
35 Pengecatan plafond skw Catylac M2 90,174.58
36 Pengecatan logam/kayu skw Avian M2 86,536.64
37 Plituran kayu bangunan M2 74,782.97
38 Pasang pipa PVC dia 4" M' -
39 Pasang pipa PVC dia 2" M' 135,561.65
40 Pasang pipa PVC dia 3/4" M' 61,862.44
41 Pasang pipa PVC 1/2" M 61,862.44
42 Pasang kran kristal 1/2" Bh 135,936.74
43 Pasang kitchenzink stainlessteel Franco Unit 347,728.47
44 Pasang bak KM fibreglass 60cm x 60cm Unit 484,179.04
45 Pasang closet jongkok setara INA Unit 822,913.44
46 Pasang flordrain stainlessteel Bh 89,909.49
47 Pasang biofil (septictank fabrikasi) Unit 2,000,000.00
48 Pasang talang datar BJLS-30 M2 869,376.84
49 Pasang atap asbes gelombang kecil M2 180,622.84
50 Pasang rangka atap-gording kayu klas II M2 -
51 Pasang kuda-kuda kayu klas II M3 -
52 Pasang bubungan nokstel M' 244,882.69
53 Pasang listplank kayu klas I 3/30 M' -
54 Pasang titik lampu/stopkontak Ttk

Page 2
REKAP HARGA SATUAN PEKERJAAN

No. Jenis Pekerjaan Satuan AHSP


55 Pasang MCB 3 group Unit 583,750.00
56 Biaya Sambungan listrik 1300 VA Pkt
57 Pasang keramik lantai 30x30 M2 331,917.61
58 Pasang keramik dinding 20x20 M2 2,191,673.38
59 Pasang plint keramik M' 807,552.35
60 Pasang pipa transmisi PVC 8" M' -
61 Pasang pipa transmisi PVC 6" M' 432,823.12
62 Pasang Aksesories PVC 8" Bh -
63 Pasang Aksesories PVC 6" Bh 129,555.90
64 Commisioning instalasi listrik Ls
65 Commisioning plumbing Ls
66 Pasang daun pintu double teakwood Daun -
67 Pasang daun jendela kaca rangka kayu Daun 648,853.10
68 Pasang stopkontak skw Broco Bh 96,250.00
69 Pasang saklar ganda skw Broco Bh 96,250.00
70 Pasang panel kontrol lengkap Unit 150,000.00
71 Pasang arde kelistrikan Titik
72 Biaya sambung listrik PLN 1300 VA Ls

Page 3
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.3.2.1.3. Pemasangan 1 m3 Pondasi Batu Belah campuran 1SP : 5PP


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.5 138,077.00 207,115.50
Tukang Batu L.02 OH 0.75 158,789.00 119,091.75
Kepala Tukang L.03 OH 0.075 173,978.00 13,048.35
Mandor L.04 OH 0.075 185,025.00 13,876.88
JUMLAH TENAGA
353,132.48
KERJA
B BAHAN
Batu belah m3 1.2 168,000.00 201,600.00
Semen Portlan Kg 136 1,950.00 265,200.00
Pasir Pasang m3 0.544 210,000.00 114,240.00
JUMLAH HARGA
581,040.00
BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 934,172.48


E Overhead & Profit 20 % x D maksimum 186,834.50
F Harga Satuan Pekerjaan (D+E) 1,121,006.97

A. 2.2Pengukuran dan Pemasangan 1 m’ Bouwplank


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.1 138,077.00 13,807.70
Tukang Kayu L.02 OH 0.1 158,789.00 15,878.90
Kepala Tukang L.03 OH 0.01 173,978.00 1,739.78
Mandor L.04 OH 0.005 185,025.00 925.13
JUMLAH TENAGA KERJA 32,351.51
B BAHAN
Kayu balok 5/7 m3 0.02 1,000,000.00 20,000.00
Paku 2”-3” Kg 0.02 40,000.00 800.00
Kayu papan 3/20 m3 0.007 1,000,000.00 7,000.00
JUMLAH HARGA BAHAN 27,800.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,151.51


E Overhead & Profit 20 % x D maksimum 12,030.30
F Harga Satuan Pekerjaan (D+E) 72,181.81
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A. 2.2 Pembersihan 1 m2 Lapangan dan Perataan


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.1 138,077.00 13,807.70
Mandor L.04 OH 0.05 185,025.00 9,251.25
JUMLAH TENAGA KERJA 23,058.95
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,058.95


E Overhead & Profit 20 % x D maksimum 4,611.79
F Harga Satuan Pekerjaan (D+E) 27,670.74

.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.75 138,077.00 103,557.75
Mandor L.04 OH 0.025 185,025.00 4,625.63
JUMLAH TENAGA KERJA 108,183.38
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 108,183.38


E Overhead & Profit 20 % x D maksimum 21,636.68
F Harga Satuan Pekerjaan (D+E) 129,820.05
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A. 2.2.1.5. Pembuatan 1 m2 kantor sementara lantai plesteran


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.2 138,077.00 165,692.40
Tukang Kayu L.02 OH 0.4 158,789.00 63,515.60
Tukang batu L.02 OH 0.4 158,789.00 63,515.60
Kepala Tukang L.03 OH 0.04 173,978.00 6,959.12
Mandor L.04 OH 0.12 185,025.00 22,203.00
JUMLAH TENAGA KERJA 321,885.72
B BAHAN
Dolken kayu diameter
Batang 1 41,400.00 51,750.00
8-10/400 cm
Kayu m3 0.28 1,000,000.00 280,000.00
Paku biasa Kg 0.08 40,000.00 3,200.00
Besi strip Kg 5 12,800.00 64,000.00
Semen Portland Kg 46 1,950.00 89,700.00
Pasir pasang m3 0.15 210,000.00 31,500.00
Pasir beton m3 0.1 225,000.00 22,500.00
Koral beton m 3
0.15 278,000.00 41,700.00
Bata merah Bh 0 8,190.00 -
Seng plat Lbr 0.25 113,000.00 28,250.00
Jendela naco Bh 0.2 -
Kaca polos 3mm m2 0.08 94,500.00 7,560.00
Kunci tanam Bh 0.05 167,000.00 8,350.00
Plywood 4mm Lbr 0.06 66,000.00 3,960.00
JUMLAH HARGA BAHAN 632,470.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 954,355.72


E Overhead & Profit 20 % x D maksimum 190,871.14
F Harga Satuan Pekerjaan (D+E) 1,145,226.86
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A. 2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.2 138,077.00 27,615.40
Tukang Kayu L.02 OH 0.4 158,789.00 63,515.60
Kepala Tukang L.03 OH 0.02 173,978.00 3,479.56
Mandor L.04 OH 0.02 185,025.00 3,700.50
JUMLAH TENAGA KERJA 98,311.06
B BAHAN
Dolken kayu
Batang 1.25 41,400.00
f 8-10/400 cm
Semen portland Kg 2.5 1,950.00 4,875.00
Seng gelombang Lbr 1.2 113,000.00 135,600.00
Pasir beton m3 0.005 225,000.00 1,125.00
Koral beton m3 0.009 278,000.00 2,502.00
Kayu 5/7 m 3
0.072 1,000,000.00 72,000.00
Paku biasa 2” – 5” Kg 0.06 40,000.00 2,400.00
Meni besi Liter 0.45 67,000.00 30,150.00
JUMLAH HARGA BAHAN 248,652.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 346,963.06


E Overhead & Profit 20 % x D maksimum 69,392.61
F Harga Satuan Pekerjaan (D+E) 416,355.67

A.2.3.1.9. Pengurugan kembali 1 m 3 galian tanah


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.5 138,077.00 69,038.50
Mandor L.04 OH 0.05 185,025.00 9,251.25
JUMLAH TENAGA KERJA 78,289.75
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 78,289.75
E Overhead & Profit 20 % x D maksimum 15,657.95
F Harga Satuan Pekerjaan (D+E) 93,947.70
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.2.3.1.10. Pemadatan tanah 1 m3 tanah ( per 20 cm)


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.5 138,077.00 69,038.50
Mandor L.04 OH 0.05 185,025.00 9,251.25
JUMLAH TENAGA KERJA 78,289.75
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 78,289.75
E Overhead & Profit 20 % x D maksimum 15,657.95
F Harga Satuan Pekerjaan (D+E) 93,947.70

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.3 138,077.00 41,423.10
Mandor L.04 OH 0.01 185,025.00 1,850.25
JUMLAH TENAGA KERJA 43,273.35
B BAHAN
Pasir urug 1.20 215,000.00 258,000.00
JUMLAH HARGA BAHAN 258,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 301,273.35
E Overhead & Profit 20 % x D maksimum 60,254.67
F Harga Satuan Pekerjaan (D+E) 361,528.02
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A. 2.2.1.10. Pembuatan 1 m2 steger/perancah dari bambu


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1 138,077.00 138,077.00
Tukang Kayu L.02 OH 2 158,789.00 317,578.00
Kepala Tukang L.03 OH 0.2 173,978.00 34,795.60
Mandor L.04 OH 0.05 185,025.00 9,251.25
TENAGA KERJA 499,701.85
B BAHAN
Bambu diameter 6-
Batang 1.25 18,000.00 22,500.00
8/600 cm
Tali ijuk m3 0.186 2,000.00 372.00

HARGA BAHAN 22,872.00


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 499,701.85


E Overhead & Profit 20 % x D maksimum 99,940.37
F Harga Satuan Pekerjaan (D+E) 599,642.22

A.2.3.1.14. Pengurugan 1 m3 sirtu padat


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.25 138,077.00 34,519.25
Mandor L.04 OH 0.025 185,025.00 4,625.63
JUMLAH TENAGA KERJA 39,144.88
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Excavator JAM 1 160,000.00 160,000.00
JUMLAH HARGA ALAT 160,000.00

D Jumlah (A+B+C) 199,144.88


E Overhead & Profit 20 % x D maksimum 39,828.98
F Harga Satuan Pekerjaan (D+E) 238,973.85
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping)

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.78 138,077.00 107,700.06
Tukang Batu L.02 OH 0.39 158,789.00 61,927.71
Kepala Tukang L.03 OH 0.039 173,978.00 6,785.14
Mandor L.04 OH 0.039 185,025.00 7,215.98
JUMLAH TENAGA KERJA 183,628.89
B BAHAN
Batu belah m3 1.20 168,000.00 201,600.00
Pasir urug m3 0.432 215,000.00 92,880.00
JUMLAH HARGA BAHAN 294,480.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 478,108.89


E Overhead & Profit 20 % x D maksimum 95,621.78
F Harga Satuan Pekerjaan (D+E) 573,730.66

A. A.4.1.1.6 Membuat 1 m3 beton mutu f’c = 21.7 MPa (K 250)

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.65 138,077.00 227,827.05
Tukang Batu L.02 OH 0.275 158,789.00 43,666.98
Kepala Tukang L.03 OH 0.028 173,978.00 4,871.38
Mandor L.04 OH 0.083 185,025.00 15,357.08
JUMLAH TENAGA 291,722.48
B BAHAN
Semen Portland kg 384 1,950.00 748,800.00
Pasir Beton kg 692 187.50 129,750.00
Kerikil kg 1039 154.44 160,467.78
Air Liter 215 800.00 172,000.00
JUMLAH BAHAN 1,211,017.78
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,502,740.26


E Overhead & Profit 20 % x D maksimum 300,548.05
F Harga Satuan Pekerjaan (D+E) 1,803,288.31
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.1.1.17 Pembesian 10 kg dengan besi polos


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.07 138,077.00 9,665.39
Tukang Besi L.02 OH 0.07 158,789.00 11,115.23
Kepala Tukang L.03 OH 0.007 173,978.00 1,217.85
Mandor L.04 OH 0.004 185,025.00 740.10
JUMLAH TENAGA 22,738.57
B BAHAN
Besi beton (polos/ulir) kg 10.50 12,800.00 134,400.00
Kawat beton kg 0.15 28,000.00 4,200.00
JUMLAH BAHAN 138,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 161,338.57


E Overhead & Profit 20 % x D maksimum 32,267.71
F Harga Satuan Pekerjaan (D+E) 193,606.28

A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof / kolom praktis


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.62 138,077.00 85,607.74
Tukang Kayu L.02 OH 0.26 158,789.00 41,285.14
Kepala Tukang L.03 OH 0.026 173,978.00 4,523.43
Mandor L.04 OH 0.026 185,025.00 4,810.65
JUMLAH TENAGA 136,226.96
B BAHAN
Kayu kelas III m3 0.045 1,500,000.00 67,500.00
Paku 5 cm – 10 cm kg 0.3 40,000.00 12,000.00
Minyak bekisting Liter 0.1 40,000.00 4,000.00
JUMLAH BAHAN 83,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 219,726.96


E Overhead & Profit 20 % x D maksimum 43,945.39
F Harga Satuan Pekerjaan (D+E) 263,672.35
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.1.1.22 Pemasangan 1 m2 bekisting untuk bak air dalam tanah


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.66 138,077.00 91,130.82
Tukang Kayu L.02 OH 0.33 158,789.00 52,400.37
Kepala Tukang L.03 OH 0.033 173,978.00 5,741.27
Mandor L.04 OH 0.033 185,025.00 6,105.83
JUMLAH TENAGA 155,378.29
B BAHAN
Kayu kelas III m3 0.04 1,500,000.00 60,000.00
Paku 5 cm – 12 cm kg 0.4 40,000.00 16,000.00
Minyak bekisting Liter 0.2 40,000.00 8,000.00
Balok kayu kelas II m3 0.015 3,400,000.00 51,000.00
Plywood tebal 9 mm Lbr 0.35 104,000.00 36,400.00
Dolken kayu dia 6 Batang 2,000 41,400.00 171,400.00

JUMLAH BAHAN 342,800.00


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 498,178.29


E Overhead & Profit 20 % x D maksimum 99,635.66
F Harga Satuan Pekerjaan (D+E) 597,813.95
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.66 138,077.00 91,130.82
Tukang Kayu L.02 OH 0.33 158,789.00 52,400.37
Kepala Tukang L.03 OH 0.033 173,978.00 5,741.27
Mandor L.04 OH 0.033 185,025.00 6,105.83
JUMLAH TENAGA 155,378.29
B BAHAN
Kayu kelas III m3 0.04 1,500,000.00 60,000.00
Paku 5 cm – 12 cm kg 0.4 40,000.00 16,000.00
Minyak bekisting Liter 0.2 40,000.00 8,000.00
Balok kayu kelas II m3 0.018 3,400,000.00 61,200.00
Plywood tebal 9 mm Lbr 0.35 104,000.00 36,400.00
Dolken kayu g Batang 2 41,400.00

JUMLAH BAHAN 181,600.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 336,978.29
E Overhead & Profit 20 % x D maksimum 67,395.66
F Harga Satuan Pekerjaan (D+E) 404,373.95
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.1.1.29 Membuat 1 m3 sloof beton bertulang


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 2.65 138,077.00 365,904.05
Tukang batu L.02 OH 0.275 158,789.00 43,666.98
Tukang kayu L.02 OH 0.20 158,789.00 31,757.80
Tukang besi L.02 OH 0.10 158,789.00 15,878.90
Kepala tukang L.03 OH 0.323 173,978.00 56,194.89
Mandor L.04 OH 0.283 185,025.00 52,362.08
JUMLAH TENAGA KERJA 565,764.69
B BAHAN
Kayu kelas III m3 0.37 1,500,000.00 555,000.00
Paku 5 cm – 12 cm kg 2 40,000.00 80,000.00
Minyak bekisting Liter 0.6 40,000.00 24,000.00
Besi beton polos kg 250 12,800.00 3,200,000.00
Kawat beton kg 3 28,000.00 84,000.00
Semen Portland kg 336 1,950.00 655,200.00
Pasir Beton m3 0.66 225,000.00 148,500.00
Kerikil m3 1.039 278,000.00 288,842.00
JUMLAH HARGA BAHAN 5,035,542.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,601,306.69
E Overhead & Profit 20 % x D maksimum 1,120,261.34
F Harga Satuan Pekerjaan (D+E) 6,721,568.03
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.1.1.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 6.35 138,077.00 876,788.95
Tukang batu L.02 OH 0.275 158,789.00 43,666.98
Tukang kayu L.02 OH 1.65 158,789.00 262,001.85
Tukang besi L.02 OH 1.40 158,789.00 222,304.60
Kepala tukang L.03 OH 0.333 173,978.00 57,934.67
Mandor L.04 OH 0.318 185,025.00 58,837.95
JUMLAH TENAGA 1,521,535.00
B BAHAN
Kayu kelas III m3 0.32 1,000,000.00 320,000.00
Paku 5 cm – 12 cm kg 3 40,000.00 128,000.00
Minyak bekisting Liter 2 40,000.00 64,000.00
Besi beton polos kg 210 12,800.00 2,688,000.00
Kawat beton kg 3 28,000.00 84,000.00
Semen Portland kg 336 1,950.00 655,200.00
Pasir Beton m3 0.54 225,000.00 121,500.00
Kerikil m3 0.81 278,000.00 225,180.00
Kayu kelas II balok m3 0.14 3,400,000.00 476,000.00
Plywood 9 mm Lembar 2.80 104,000.00 291,200.00
Dolken kayu Batang 16 41,400.00 662,400.00

JUMLAH BAHAN 5,715,480.00


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 7,237,015.00


E Overhead & Profit 20 % x D maksimum 1,447,403.00
F Harga Satuan Pekerjaan (D+E) 8,684,418.00
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.4.3.35.Pemasangan 1m2 lantai keramik ukuran 30cm x 30cm


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.6 138,077.00 82,846.20
Tukang Batu L.02 OH 0.3 158,789.00 47,636.70
Kepala tukang L.03 OH 0.035 173,978.00 6,089.23
Mandor L.04 OH 0.035 185,025.00 6,475.88
JUMLAH TENAGA 143,048.01
B BAHAN
Ubin keramik M2 1.1 85,000.00 93,500.00
Semen Portland Kg 8 1,950.00 15,600.00
Pasir pasang M3 0.045 210,000.00 9,450.00
Semen warna Kg 1 15,000.00 15,000.00
JUMLAH BAHAN 133,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 276,598.01


E Overhead & Profit 20 % x D maksimum 55,319.60
F Harga Satuan Pekerjaan (D+E) 331,917.61

A.4.4.3.36.Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm antislip


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.6 138,077.00 82,846.20
Tukang Batu L.02 OH 0.3 158,789.00 47,636.70
Kepala tukang L.03 OH 0.035 173,978.00 6,089.23
Mandor L.04 OH 0.035 185,025.00 6,475.88
JUMLAH TENAGA 143,048.01
B BAHAN
Ubin keramik 20x20 M2 1.1 59,000.00 64,900.00
Semen Portlan Kg 10.4 1,950.00 20,280.00
Pasir pasang M3 0.045 210,000.00 9,450.00
Semen warna Kg 1.62 15,000.00 24,300.00
JUMLAH BAHAN 118,930.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 261,978.01


E Overhead & Profit 20 % x D maksimum 52,395.60
F Harga Satuan Pekerjaan (D+E) 314,373.61

A.4.4.3.54.Pemasangan 1 m2 dinding keramik 20cm x 20cm


ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.9 138,077.00 124,269.30
Tukang Batu L.02 OH 0.45 158,789.00 71,455.05
Kepala tukang L.03 OH 0.045 173,978.00 7,829.01
Mandor L.04 OH 0.045 185,025.00 8,326.13
JUMLAH TENAGA 211,879.49
B BAHAN
Keramik artistik Bh 26.5 59,000.00 1,563,500.00
Semen Portlan Kg 9.3 1,950.00 18,135.00
Pasir Pasang M3 0.018 210,000.00 3,780.00
Semen warna Kg 1.94 15,000.00 29,100.00
JUMLAH BAHAN 1,614,515.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,826,394.49


E Overhead & Profit 20 % x D maksimum 365,278.90
F Harga Satuan Pekerjaan (D+E) 2,191,673.38

A.4.4.3.39.Pemasangan 1 m’ plint keramik ukuran 10cm x 20cm


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.09 138,077.00 12,426.93
Tukang Batu L.02 OH 0.09 158,789.00 14,291.01
Kepala tukang L.03 OH 0.035 173,978.00 6,089.23
Mandor L.04 OH 0.005 185,025.00 925.13
JUMLAH TENAGA 33,732.30
B BAHAN
Plint keramik Bh 5.3 120,000.00 636,000.00
Semen Portlan Kg 1.14 1,950.00 2,223.00
Pasir pasang M3 0.003 210,000.00 630.00
Semen warna Kg 0.025 15,000.00 375.00
JUMLAH BAHAN 639,228.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 672,960.30


E Overhead & Profit 20 % x D maksimum 134,592.06
F Harga Satuan Pekerjaan (D+E) 807,552.35
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.5.1.1. Pemasangan 1 m2 langit-langit serat semen, tebal 4 mm, 5 mm, dan 6 mm


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.03 138,077.00 4,142.31
Tukang kayu L.02 OH 0.07 158,789.00 11,115.23
Kepala tukang L.03 OH 0.007 173,978.00 1,217.85
Mandor L.04 OH 0.004 185,025.00 740.10
JUMLAH TENAGA 17,215.49
B BAHAN
Asbes semen m2 1.10 113,000.00 124,300.00
Paku tripleks kg 0.01 33,000.00 330.00
JUMLAH BAHAN 124,630.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 141,845.49


E Overhead & Profit 20 % x D maksimum 28,369.10
F Harga Satuan Pekerjaan (D+E) 170,214.58

A.4.5.1.5. Pemasangan 1 m2 langit-langit tripleks tebal 3 mm, 4 mm & 6 mm


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.1 138,077.00 13,807.70
Tukang kayu L.02 OH 0.1 158,789.00 15,878.90
Kepala tukang L.03 OH 0.01 173,978.00 1,739.78
Mandor L.04 OH 0.005 185,025.00 925.13
JUMLAH TENAGA 32,351.51
B BAHAN
Tripleks Lembar 0.375 45,000.00 16,875.00
Paku tripleks kg 0.03 33,000.00 990.00
JUMLAH BAHAN 17,865.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,604.78


E Overhead & Profit 20 % x D maksimum 3,920.96
F Harga Satuan Pekerjaan (D+E) 23,525.74
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN PED.
AHSP BID. PU

A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.1 138,077.00 13,807.70
Tukang kayu L.02 OH 0.05 158,789.00 7,939.45
Kepala tukang L.03 OH 0.005 173,978.00 869.89
Mandor L.04 OH 0.005 185,025.00 925.13
JUMLAH TENAGA KERJA 23,542.17
B BAHAN
Gypsum board Lembar 0.364 110,000.00 40,040.00
Paku skrup kg 0.11 40,000.00 4,400.00
JUMLAH HARGA BAHAN 44,440.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 67,982.17


E Overhead & Profit 20 % x D maksimum 13,596.43
F Harga Satuan Pekerjaan (D+E) 81,578.60

A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.05 -
Tukang Kayu L.02 OH 0.05 -
Kepala tukang L.03 OH 0.005 -
Mandor L.04 OH 0.003 -
JUMLAH KERJA -
B BAHAN
List kayu profil m 1.05 -
Paku kg 0.01 -
JUMLAH BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 20 % x D maksimum -
F Harga Satuan Pekerjaan (D+E) -

A.4.6.1.2.Pembuatan dan pemasangan 1 m 3 kusen pintu / jendela, kayu kelas I


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 6 138,077.00 828,462.00
Tukang kayu L.03 OH 18 158,789.00 2,858,202.00
Kepala tukang L.03 OH 1.80 173,978.00 313,160.40
Mandor L.04 OH 0.3 185,025.00 55,507.50
JUMLAH TENAGA 4,055,331.90
B BAHAN
RENCANA ANGGARAN BIAYA

Harga Satuan Jumlah Harga Bobot


No. Uraian Pekerjaan Volume Satuan
(Rp) (Rp) %

I PEKERJAAN PENDAHULUAN DAN TANAH


1 Papan Nama proyek 1.00 buah 500,000.00 500,000.00 0.03
2 Pembersihan dan penyiapan lapangan lapangan 500.00 m2 27,670.74 13,835,370.00 0.94
3 Pembuatan pagar sementara dari seng gelombang 90.00 m' 208,177.84 18,736,005.24 1.28
4 Pek. Pembuatan Direksi Keet ukuran 3 x 4 m 12.00 m2 1,145,226.86 13,742,722.37 0.94
5 Pek. Pembuatan Gudang dan barak pekerja UK. 3 X 4 m 12.00 m2 1,145,226.86 13,742,722.37 0.94
6 Penyediaan Air Kerja 1.00 Ls 2,250,000.00 2,250,000.00 0.15
7 Penyediaan Listrik Kerja 1.00 Ls 2,500,000.00 2,500,000.00 0.17
8 Pek. Ukur Lapangan dan Bowplank 68.00 m' 72,181.81 4,908,362.81 0.33
9 Pek. Galian Tanah 68.40 m3 129,820.05 8,879,691.42 0.61
10 Pek. Urugan Kembali dan pemadatan 30.60 m3 238,973.85 7,312,599.81 0.50
11 Pek. Mobilisasi dan Demobilisasi Alat 1.00 Ls 5,000,000.00 5,000,000.00 0.34

Subtotal 91,407,474.01 6.23


II PEKERJAAN PONDASI
1 Pek. Pondasi Titik Beton Bertulang 3.17 m3 6,721,568.03 21,273,762.82 1.45
2 Pek. Pondasi Menerus Pasangan Batu Kali adukan 1 : 3 46.98 m3 1,121,006.97 52,664,907.45 3.59
3 Pek. Sloof Beton Bertulang ( 20 x 35 cm) 4.90 m3 4,436,234.90 21,737,551.02 1.48
4 Pek. Pembesian Angkur Ø 22 mm 32.00 bh 67,000.00 2,144,000.00 0.15

Subtotal 97,820,221.29 6.67


III PEKERJAAN KOLOM
1 Pek. Kolom H Beam 200x200x8x12 2595.67 Kg 31,000.00 80,465,666.67 5.49
2 Pek Base plate tebal 12 mm uk. 290 x 290 mm 63.38 Kg 31,000.00 1,964,625.00 0.13
3 Pek. Reagle CNP 150x65x20x3.2 360.80 Kg 31,000.00 11,184,800.00 0.76

Subtotal 93,615,091.67 6.38


IV PEKERJAAN RAFTER
1 Pek. Rafter H Beam 150x150x7x10 5191.33 Kg 31,000.00 160,931,333.33 10.97
2 Pek. Ring balok H Beam 100x100x6x8 515.00 Kg 31,000.00 15,965,000.00 1.09
3 Accessories baut 1.00 Ls 2,500,000.00 2,500,000.00 0.17

Subtotal 179,396,333.33 12.23


V PEKERJAAN ROOFING
1 Pek. Gording CNP 125x50x20x3.2 1558.00 Kg 31,000.00 48,298,000.00 3.29
2 Pek.Treck Stang Besi 12 mm 60.00 m' 31,000.00 1,860,000.00 0.13
3 Pek. Breasing Besi 12 mm 40.00 btg 20,000.00 800,000.00 0.05
4 Pek. Penutup Atap Zincalum t. 0,35 288.90 m2 90,000.00 26,001,000.00 1.77
5 Pek. Nok Atap Zincalum 17.00 m' 120,000.00 2,040,000.00 0.14

Subtotal 78,999,000.00 5.39


VI PEKERJAAN TALANG BANGUNAN
1 Pekerjaan Talang Air Hujan Plat Zincalum 56.00 m' 120,000.00 6,720,000.00 0.46
2 Pekerjaan Plat Strip uk. 5 x 50 mm 34.00 m 120,000.00 4,080,000.00 0.28
3 Pekerjaan Corong Talang 4" 4.00 bh 135,561.65 542,246.62 0.04
4 Pekerjaan Pipa PVC 4" AW ex WAVIN 9.70 btg 135,561.65 1,314,948.04 0.09
5 Pekerjaan Fitting PVC AW ex WAVIN 1.00 Ls 31,000.00 31,000.00 0.00

Subtotal 12,688,194.66 0.86


VII PEKERJAAN VENTILATOR UDARA
1 Pek. Pasang Ventilator Udara di Atap 6.00 bh 1,500,000.00 9,000,000.00 0.61

Subtotal 9,000,000.00 0.61


RENCANA ANGGARAN BIAYA

Harga Satuan Jumlah Harga Bobot


No. Uraian Pekerjaan Volume Satuan
(Rp) (Rp) %

VIII PEKERJAAN DINDING DAN PINTU


1 Pek. Pasangan Bata ringan 180.70 m2 122,098.00 22,063,108.60 1.50
2 Pek. Pasangan Bata ringan 21.00 m2 160,000.00 3,360,000.00 0.23
3 Pek. Ring Balk Beton Bertulang (15x20 cm) 3.77 m3 4,436,234.90 16,724,605.58 1.14
4 Pek. Kolom Praktis Beton bertulang (15x15 cm) 0.10 m3 4,436,234.90 425,139.18 0.03
5 Pek. Plesteran 1 Semen : 3 Pasir + Acian 361.40 m2 103,434.35 37,381,175.54 2.55
6 Pek. Pasang Dinding Zincalume Tinggi = 2,5 m + rangka 125.00 m2 188,000.00 23,500,000.00 1.60
7 Pek. Pasang Kawat Ram 2 cm - T = 1 m + rangka 50.00 m2 62,000.00 3,100,000.00 0.21
8 Pek. Kusen Alum. + Pintu Kaca 1.00 Set 2,000,000.00 2,000,000.00 0.14
9 Pek. Pintu Besi Powder Coating (t=1,5mm) 3.00 Set 4,700,000.00 14,100,000.00 0.96
10 pintu PCV 1.00 set 700,000.00 700,000.00 0.05
11 Bouvenlis alumunium 5.00 Set 1,200,000.00 6,000,000.00 0.41
12 Pek. Kusen Alum. + jendela Kaca 3.00 Set 2,000,000.00 6,000,000.00 0.41

Subtotal 135,354,028.89 9.23


IX PEKERJAAN LANTAI
1 Pek. Urugan Tanah 58.55 m3 238,973.85 13,992,205.69 0.95
2 Pek. Urugan Pasir urug 14.64 m3 361,528.02 5,291,974.85 0.36
3 Pek. Urugan Sirtu 29.28 m3 238,973.85 6,996,102.84 0.48
4 Pek. lantai kerja beton mutu K100, tebal 5 cm 7.32 m3 1,335,000.00 9,770,731.50 0.67
5 Pek. Cor Lantai Beton K-250 tebal 20 cm 29.28 m3 6,721,568.03 196,777,937.10 13.41
6 Pek. Wermesh Tulangan Lantai 6x150x150 146.38 m2 47,000.00 6,879,766.00 0.47

Subtotal 239,708,717.98 16.34


X PEKERJAAN PENGECATAN BANGUNAN
1 Pek. Cat Dasar (Sinkromat) 6.00 peil 360,000.00 2,160,000.00 0.15
2 Pek. Pencampur Tinner 2.00 drum 1,000,000.00 2,000,000.00 0.14
3 Pek. Cat Besi Finishing 4.00 peil 442,000.00 1,768,000.00 0.12
4 Pek. Pengecatan Dinding Dalam Bangunan 180.70 m2 45,000.00 8,131,500.00 0.55
5 Pek. Pengecatan Dinding Luar Bangunan 180.70 m2 45,000.00 8,131,500.00 0.55
6 Pek. Alat Bantu Pengecatan 1.00 Ls 379,000.00 379,000.00 0.03

Subtotal 22,570,000.00 1.54


XI PEKERJAAN LISTRIK BANGUNAN
1 Pek. Instalasi Listrik Penerangan 14.00 titik 290,000.00 4,060,000.00 0.28
2 Pek. Instalasi Listrik Stop Kontak 4.00 titik 290,000.00 1,160,000.00 0.08
3 Pek. Rumah Lampu Insdustri - ex ARTOLITE 6.00 Set 640,000.00 3,840,000.00 0.26
4 Pek. Rumah Lampu Exterior - ex ARTOLITE 8.00 Set 640,000.00 5,120,000.00 0.35
5 Box Panel Kontrol 2.00 Set 3,000,000.00 6,000,000.00 0.41

Subtotal 20,180,000.00 1.38


XIII PEKERJAAN TERAS PARKIR
1 Pek. Urugan Sirtu 19.20 m3 238,973.85 4,588,297.92 0.31
2 Pek. Urugan Pasir urug 9.60 m3 361,528.02 3,470,668.99 0.24
3 Pek. lantai kerja beton mutu K100, tebal 5 cm 4.80 m3 1,335,000.00 6,408,000.00 0.44
4 Pek. Cor Lantai Beton K-250 tebal 25 cm 47.76 m3 6,721,568.03 321,005,285.33 21.88
5 Pek. Wermesh Tulangan Lantai 6x150x150 172.38 m2 47,000.00 8,101,860.00 0.55

Subtotal 343,574,112.24 23.42


XV PEKERJAAN KOLAM AIR LINDI
1 Pek. Membuat Kolam Air Lindi 10.00 m3 3,000,000.00 30,000,000.00 2.05
(Semen Penutup Kolam dapat di lepas)

Subtotal 30,000,000.00 2.05


RENCANA ANGGARAN BIAYA

Harga Satuan Jumlah Harga Bobot


No. Uraian Pekerjaan Volume Satuan
(Rp) (Rp) %

XVI PEKERJAAN CELL KOMPOS (1,5X2X5 UNIT)


1 Pek. Kolom Praktis Beton Tulang (15x15 cm) 0.41 m3 4,436,234.90 1,796,675.14 0.12
2 Pek. Ring Balk Beton Bertulang (15x20 cm) 0.75 m3 4,436,234.90 3,327,176.18 0.23
3 Pek.Pasang Bata Merah 41.10 m2 122,098.00 5,018,227.80 0.34
4 Pek. Plesteran 1 Semen : 3 Pasir + Acian 88.37 m2 80,000.00 7,069,200.00 0.48
Subtotal 17,211,279.11 1.17
XVII PEKERJAAN PENUTUP CELL KOMPOS
1 Pek. Rangka Penutup hollow 4x4 10.00 btg 31,000.00 310,000.00 0.02
2 Pek. Penutup Atap Zincalume t. 0,35 15.00 m2 90,000.00 1,350,000.00 0.09

Subtotal 1,660,000.00 0.11


XVIII PEKERJAAN PAGAR BRC
1 Pek. Pondasi Titik Beton Bertulang 2.90 m3 4,436,234.90 12,865,081.21 0.88
2 Pek. Sloof Beton Bertulang ( 15 x 20 cm) 6.66 m3 4,436,234.90 29,545,324.44 2.01
3 Pasang pagar BRC tinggi 160 cm 90.00 m 570,000.00 51,300,000.00 3.50

Subtotal 93,710,406 6.39


Total 1,466,894,858.85 100.00
PPN 10 % 146,689,485.89
Total Termasuk PPN 10% 1,613,584,344.74

Pembulatan 1,613,584,300.00
Analisa 1m3 Beton (In. Beton, Bekisting dan Besi)
a. Sloof 20 x 35
1 m Beton 0.07 = 1x Rp 1,803,288.31
1m Bekisting 0.9 = 12.85714 x Rp 263,672.35
1m Besi 19Kg/m3 = 19 x Rp 19,360.63

b. Sloof 15 x 20
1 m Beton 0.03 = 1x Rp 1,803,288.31
1m Bekisting 0.55 = 18.33333 x Rp 263,672.35
1m Besi 19Kg/m3 = 19 x Rp 19,360.63

c. Sloof 15 x 15
1 m Beton 0.0225 = 1x Rp 1,803,288.31
1m Bekisting 0.6 = 26.66667 x Rp 263,672.35
1m Besi 19Kg/m3 = 19 x Rp 8,560.77
Rp 1,803,288.31
Rp 3,390,073.07
Rp 367,851.93
Rp 5,561,213.31

Rp 1,803,288.31
Rp 4,833,993.08
Rp 367,851.93
Rp 7,005,133.32

Rp 1,803,288.31
Rp 7,031,262.66
Rp 162,654.71
Rp 8,997,205.68
RENCANA ANGGARAN BIAYA

No. Uraian Pekerjaan Volume

I PEKERJAAN PENDAHULUAN DAN TANAH


1 Papan Nama proyek 1.00
2 Pembersihan dan penyiapan lapangan lapangan 500.00
3 Pembuatan pagar sementara dari seng gelombang 80.00
4 Pek. Pembuatan Direksi Keet ukuran 3 x 4 m 12.00
5 Pek. Pembuatan Gudang dan barak pekerja UK. 3 X 4 m 12.00
6 Penyediaan Air Kerja 1.00
7 Penyediaan Listrik Kerja 1.00
8 Pek. Ukur Lapangan dan Bowplank 64.00
9 Mobilisasi dan Demobilisasi Alat 1.00
Subtotal

III. PEKERJAAN KOLOM


1 Pek. Kolom CNP 125x50x20x2 883.00
2 Pek Base plate tebal 12 mm uk. 120 x 200 mm 36.00
3 Pek. Reagle CNP 150x65x20x3.2 401.60
4 Pek. Wall Breasing besi 12 mm 101.00
Subtotal

IV. PEKERJAAN RAFTER


1 Pek. Rafter Siku 50X50X5 1,089.00
2 Pek. Ring balok CNP 125X50X20X2 368.00
3 Pek. Rafter CNP 125X50X20X2 220.68
4 Accessories baut 1.00
Subtotal

V. PEKERJAAN ROOFING
1 Pek. Gording CNP 125x50x20x3.2 1,558.00
2 Pek.Treck Stang Besi 12 mm 59.50
3 Pek. Breasing Besi 12 mm 97.60
4 Pek. Penutup Atap Zincalum t. 0,35 244.80
5 Pek. Nok Atap Zincalum 30.50
6 Pekerjaan Rangka atap baja ringan 86.00
7 Pek. Atap Genteng metal berpasir 86.00
8 Pekerjaan Lisplang Zincalum lebar= 40 cm 64.00
9 Pekerjaan Talang Air Hujan Plat Zincalum 34.00
10 Pekerjaan Plat Strip uk. 5 mm x 50 mm 34.00
11 Pekerjaan Corong Talang 4" 4.00
12 Pekerjaan Pipa PVC 4" AW 40.00
13 Pekerjaan Fitting pipa PVC AW 4" 1.00
14 Pek. Pasang Ventilator Udara di Atap 6.00
Subtotal

VI. PEKERJAAN DINDING DAN PINTU


1 Pek. Dinding pasangan bata ringan 284.90
2 Pek. Ring Balk Beton Bertulang (15x20 cm) 2.59
3 Pek. Kolom Praktis Beton bertulang (15x15 cm) 2.42
4 Pek. Plesteran 1 Semen : 3 Pasir + Acian 418.00
5 Pek. Pasang Dinding Zincalume Tinggi = 2,5 m + rangka 100.00
6 Pek. Pasang Dinding Zincalume Sopi-sopi + rangka 11.80
7 Pek. Pasang Kawat Ram 2 cm - T = 1 m + rangka 50.00
8 Pasang plafond gypsum tebal 9 mm + rangka 21.00
9 Pasang plafond GRC tebal 3 mm + rangka 21.27
10 Pasang list plafond 64.00
11 Pasang lisplang GRC lebar 25 cm 18.00
12 Pek. Kusen Alum. + Pintu 1.00
13 Pek. Pintu Besi Powder Coating (t=1,5mm) uk. 2.4 x 2.5 m 2.00
14 Pek. Pintu Besi Powder Coating (t=1,5mm) uk. 1.1 x 2.1 m 1.00
15 Pintu KM PVC 1.00
16 Bouvenlight alumunium 5.00
17 Pek. Kusen Alum. + jendela Kaca 3.00
Subtotal

VII. PEKERJAAN LANTAI


1 Pek. Urugan Tanah 40.00
2 Pek. Urugan Pasir urug 16.00
3 Pek. Urugan Sirtu 29.72
4 Pek. lantai kerja beton mutu K100, tebal 5 cm 7.42
5 Pek. Cor Lantai Beton K-250 tebal 20 cm 29.72
6 Pek. Wiremesh Tulangan Lantai M 6x150x150 148.63
7 Rabat lantai beton tebal 10 cm 4.45
8 Pek. Keramik lantai uk. 30 x 30 cm 21.00
9 Pek. Keramik lantai KM uk. 20 x 20 cm 2.77
Subtotal

VIII. PEKERJAAN PENGECATAN BANGUNAN


1 Pek. Cat Sinkromat dan cat finish baja 7,060.27
2 Pek. Pengecatan Dinding Dalam Bangunan 333.40
3 Pek. Pengecatan Dinding Luar Bangunan 263.17
Subtotal

IX. PEKERJAAN LISTRIK BANGUNAN


1 Pek. Instalasi Listrik Penerangan 22.00
2 Pek. Instalasi Listrik Stop Kontak 6.00
3 Pek. Rumah Lampu Insdustri Interior 6.00
4 Pek. Rumah Lampu Industri Exterior 8.00
5 Pasang lampu NL 9 Watt 8.00
6 Panel MCB 1.00
Subtotal

X. PEKERJAAN SANITASI DAN PLUMBING


1 Instalasi Air bersih pipa PVC AW dia. 1/2" 47.00
2 Instalasi Air kotor PVC AW dia 3" 16.00
3 Floor drain 1.00
4 Kloset duduk setara Toto 1.00
5 Kran air 1/2" 4.00
6 Pekerjaan pantek air bersih 1.00
7 Pompa air bersih kap. 30 ltr/menit 1.00
8 Septic tank bio kap. 1000 ltr 1.00
9 Sumur Resapan buis beton dia. 100 cm h =1.5 m 1.00
10 Pek. Saluran air hujan buis beton dia. 30 cm 52.00
11 Bak kontrol uk.60 x 60 cm 4.00
Subtotal

XI. PEKERJAAN TERAS PARKIR


1 Pek. Urugan Sirtu 19.20
2 Pek. Urugan Pasir urug 9.60
3 Pek. lantai kerja beton mutu K100, tebal 5 cm 4.80
4 Pek. Cor Lantai Beton K-250 tebal 25 cm 24.00
5 Pek. Wiremesh Tulangan Lantai 6x150x150 96.00
Subtotal

XII. PEKERJAAN KOLAM AIR LINDI


1 Urugan pasir dibawah lantai 0.60
2 Lantai kerja tebal 5 cm 0.30
3 Beton sloof uk. 15 x 20 cm K 250 0.64
4 Beton bertulang Lantai kolam lindi tebal 12 cm 0.68
5 Beton bertulang dinding kolam lindi tebal 12 cm 2.93
6 Beton bertulang tutup kolam lindi tebal 12 cm 0.69

Subtotal

XIII. PEKERJAAN CELL KOMPOS (1,5X2X5 UNIT)


1 Pek. Pondasi Menerus Pasangan Batu Kali adukan 1 : 3 2.97
2 Pek. Sloof Beton Bertulang ( 15 x 20 cm) 0.84
3 Pek. lantai kerja beton mutu K100, tebal 5 cm 0.62
4 Pek. Cor Lantai Cell Kompos tebal 10 cm 1.24
5 Pek. Rabat lantai depan cell kompos 1.20
6 Pek. Floor drain 5.00
7 Pek. Pipa PVC 3" + Fitting 15.00
8 Pek. Kolom Praktis Beton Tulang (15x15 cm) 0.40
9 Pek. Ring Balk Beton Bertulang (15x20 cm) 0.75
10 Pek.Pasang Bata ringan 41.10
11 Pek. Plesteran 1 Semen : 3 Pasir + Acian 82.20
12 Pek. Tutup cell kompos Zincalume t. 0,35 + rangka hollow 4x4 15.00
13 Pek. Rangka atap baja ringan cell kompos 20.00
14 Pek. Penutup Atap Zincalum t. 0,35 20.00
15 Pek. Pintu Bak Cell Kompos 5.00
Subtotal

XIV. PEKERJAAN PAGAR BRC


1 Pek. Pondasi Titik Beton Bertulang 2.30
2 Pek. Sloof Beton Bertulang ( 15 x 20 cm) 2.85
3 Pasang pagar BRC tinggi 150 cm 85.00
4 Pek. Gerbang BRC 5.00

Subtotal
AN BIAYA

Harga Satuan Jumlah Harga


Satuan
(Rp) (Rp)

buah 500,000.00 500,000.00


m2 27,670.74 13,835,370.00
m' 208,177.84 16,654,226.88
m2 1,145,226.86 13,742,722.36
m2 1,145,226.86 13,742,722.36
Ls 2,000,000.00 2,000,000.00
Ls 2,500,000.00 2,500,000.00
m' 72,181.81 4,619,635.58
Ls 6,000,000.00 6,000,000.00
73,594,677.18

Kg 34,500.00 30,463,500.00
Kg 34,500.00 1,242,000.00
Kg 34,500.00 13,855,200.00
Kg 34,500.00 3,484,500.00
49,045,200.00

Kg 34,500.00 37,570,500.00
Kg 34,500.00 12,696,000.00
Kg 34,500.00 7,613,460.00
Ls 3,000,000.00 3,000,000.00
60,879,960.00

Kg 34,500.00 53,751,000.00
kg 34,500.00 2,052,750.00
kg 34,500.00 3,367,200.00
m2 150,000.00 36,720,000.00
m' 130,000.00 3,965,000.00
m2 195,000.00 16,770,000.00
m2 210,000.00 18,060,000.00
m' 135,000.00 8,640,000.00
m' 164,131.00 5,580,454.00
m 98,000.00 3,332,000.00
bh 156,000.00 624,000.00
m 148,015.00 5,920,600.00
Ls 300,000.00 300,000.00
bh 1,500,000.00 9,000,000.00
168,083,004.00

m2 175,934.00 50,123,596.60
m3 #REF! #REF!
m3 8,997,205.68 21,773,237.73
m2 160,323.25 67,015,117.95
m2 235,000.00 23,500,000.00
m2 235,000.00 2,773,000.00
m2 168,000.00 8,400,000.00
m2 205,000.00 4,305,000.00
m2 220,000.00 4,679,400.00
m 38,000.00 2,432,000.00
m 105,000.00 1,890,000.00
Set 1,500,000.00 1,500,000.00
Set 8,600,000.00 17,200,000.00
Set 3,800,000.00 3,800,000.00
set 1,200,000.00 1,200,000.00
Set 1,200,000.00 6,000,000.00
Set 3,200,000.00 9,600,000.00
#REF!

m3 238,973.85 9,558,954.00
m3 345,000.00 5,520,000.00
m3 361,528.02 10,744,612.75
m3 #REF! #REF!
m3 1,803,288.31 53,593,728.69
m2 77,400.00 11,503,962.00
m3 1,423,844.00 6,336,105.80
m2 331,917.61 6,970,269.72
m2 331,917.61 919,411.76
#REF!

kg 1,250.00 8,825,337.50
m2 47,168.00 15,725,811.20
m2 49,261.00 12,964,017.37
37,515,166.07

titik 320,000.00 7,040,000.00


titik 320,000.00 1,920,000.00
Set 750,000.00 4,500,000.00
Set 750,000.00 6,000,000.00
bh 200,000.00 1,600,000.00
Set 3,000,000.00 3,000,000.00
24,060,000.00

m' 28,000.00 1,316,000.00


m' 121,278.00 1,940,448.00
bh 355,000.00 355,000.00
bh 4,200,000.00 4,200,000.00
bh 120,000.00 480,000.00
ls 10,000,000.00 10,000,000.00
bh 4,000,000.00 4,000,000.00
bh 5,500,000.00 5,500,000.00
bh 4,150,000.00 4,150,000.00
m' 330,000.00 17,160,000.00
bh 1,200,000.00 4,800,000.00
53,901,448.00

m3 361,528.02 6,941,337.98
m3 345,000.00 3,312,000.00
m3 #REF! #REF!
m3 1,803,288.31 43,278,919.53
m2 77,400.00 7,430,400.00
#REF!

m3 345,000.00 207,000.00
m3 #REF! #REF!
m3 #REF! #REF!
m3 5,285,000.00 3,593,800.00
m3 #REF! #REF!
m3 #REF! #REF!

#REF!

m3 #REF! #REF!
m3 #REF! #REF!
m3 #REF! #REF!
m3 1,803,288.31 2,236,077.50
m3 1,423,844.00 1,708,612.80
bh 355,000.00 1,775,000.00
m 121,278.00 1,819,170.00
m3 8,997,205.68 3,598,882.27
m3 #REF! #REF!
m2 175,934.00 7,230,887.40
m2 160,323.25 13,178,571.04
m2 325,000.00 4,875,000.00
m2 195,000.00 3,900,000.00
m2 150,000.00 3,000,000.00
bh 750,000.00 3,750,000.00
#REF!

m3 #REF! #REF!
m3 #REF! #REF!
m 556,000.00 47,260,000.00 PPH dan PPN 12%
m 800,000.00 4,000,000.00 #REF! #REF!
PENAWARAN 50%
#REF! #REF! #REF!
Total #REF! PENAWARAN 40%
PPN 10 % #REF! #REF! #REF!
Total Termasuk PPN 10% #REF! PENAWARAN 35%
Pembulatan #REF! #REF! #REF!
Uang O 14%
#REF! #REF!
1,406,027,265.00 ###

Profit 35% #REF!


Profit 40% #REF!
Profit 50% #REF!
R

No. Uraian Pekerjaan

I PEKERJAAN PENDAHULUAN DAN TANAH

II. PEKERJAAN PONDASI

III. PEKERJAAN KOLOM

IV. PEKERJAAN RAFTER

V. PEKERJAAN ROOFING

VI. PEKERJAAN DINDING DAN PINTU

VII. PEKERJAAN LANTAI

VIII. PEKERJAAN PENGECATAN BANGUNAN

IX. PEKERJAAN LISTRIK BANGUNAN

X. PEKERJAAN SANITASI DAN PLUMBING

XI. PEKERJAAN TERAS PARKIR

XII. PEKERJAAN KOLAM AIR LINDI

XIII. PEKERJAAN CELL KOMPOS (1,5X2X5 UNIT)

XIV. PEKERJAAN PAGAR BRC

Subtotal
Bobot
Bobot Kumulatif
RENCANA ANGGARAN BIAYA

Jadwal Pelaksanaan
Jumlah Harga Bobot
Bulan ke-1 Bulan ke-2
(Rp) % 1 2 3 4 5

73,594,677.18 7.418 3.71 3.7088505

#NAME? 8.603 4.30 4.3013098

49,045,200.00 8.198 4.10 4.0989728

60,879,960.00 6.865 3.43 3.4325747

168,083,004.00 13.120 4.37

#REF! 18.860

#REF! 8.847

37,515,166.07 2.884

24,060,000.00 1.850

53,901,448.00 4.144

#REF! 5.192

#REF! 2.543

#REF! 4.799

#REF! 6.677

100.00
Bobot 3.71 8.01 8.40 7.53 7.81
Bobot Kumulatif 3.71 11.72 20.12 27.65 35.46
Jadwal Pelaksanaan
Bulan ke-2 Bulan ke-3
6 7 8 9 10 11 12

4.3734212 4.3734212

6.29 6.2866027 6.2866027

4.42 4.4236106

1.44 1.4421112

0.92 0.9248845

2.07 2.0720122

2.60 2.596247

1.27 1.2713266

2.40 2.399397

3.34 3.3386672

10.66 16.53 15.15 5.59 6.27 7.01 3.34


46.12 62.64 77.79 83.38 89.65 96.66 100.00
REKAPITULASI PERHITUNGAN TINGKAT KOMP

Nilai Gabungan
Barang / Jasa (Rp) TKDN
Uraian Pekerjaan
DN LN

(1) (2) (3)


Barang
#REF! -
I Material Lan

II. Peralatan (Ba 4,083,722,548.62

A. Sub Total Ba #REF!

Jasa Manajemen
Proyek dan #REF! -
III
Perekayasa
an
IV Alat Kerja/Fa #REF! -
V Kostruksi da #REF! -
VI Jasa Umum #REF! -

B Subtotal Jasa #REF! -

C TOTAL Biaya #REF! -

Formulasi Perhitungan :
% TKDN Barang =

% TKDN Jasa =

=
% TKDN (Gabungan Barang dan Jasa) =
HITUNGAN TINGKAT KOMPONEN DALAM NEGERI ( TKDN)

Nilai Gabungan
TKDN
Barang / Jasa (Rp) TKDN
Total
Barang Jasa Gabungan
Ribu Rp % KDN
(4) (5) (6) (7)

#REF! 77.0% #REF! #REF!

4,083,722,548.62 3% 4,083,722,548.62 4,083,722,548.62

#REF! 80% #REF! #REF!

#REF! 2% #REF! #REF!

#REF! 15% #REF! #REF!


#REF! 2% #REF! #REF!
#REF! 1% #REF! #REF!

#REF! 20% #REF! #REF!

#REF! 100% #REF! #REF!

Nilai Barang Total (3C)-Nilai Barang Luar Negeri (3B)


Nilai Gabungan Barang dan Jasa (9C)
#REF! - - x 100
#REF!
#REF!

Nilai Jasa Total (8C)-Nilai Jasa Luar Negeri (8B)


Nilai Gabungan Barang dan Jasa (9C)
#REF! - - x 100
#REF!
#REF!
#REF! %
DI ganti Di SINI
#REF!
Nilai Sebelum PPN

7,424,950,088.39
4,574,356,859.92
DAFTAR USULAN PEKERJAAN YANG DI SUB KONTRAKK

No. JENIS PEKERJAAN

NIHIL
JUMLAH
AN YANG DI SUB KONTRAKKAN

PRESENTASE DARI
VOLUME SATUAN HARGA PENAWARAN Keterangan
(%)

L
0.000
28
800
22400
9600
56000

88000
siku 50 14.66666667
22.68 16
362.88 kg
1088.64
cnp 125
36.78 12
882.72 kg

cnp 75 18
19.5 15
270
45
877.5 kg

roof .45 15
17
280.5 m2

160
200
12
3.0144 kg

You might also like