earthwork, civil work, structural work, architectural work, mechanical and electrical installation etc.
as per authority stadard and req
Allow for design irrigation reservoir and pumpstation including all necessary Design
1 Please provide scope description. for earthwork, civil work, structural work, architectural work, Mechanical and
electrical etc. as per authority standard and requirements
2 We assume that topographic survey will be provided by contractors and not included in scope. Please confirm Will provided by main contractor
3 We assume that soil investigation will be provided by contractors and not included in scope. Please confirm. Will provided by main contractor
4 We assume that irrigation network design is not part of the scope. Please confirm. Confirmed
5 Clarify the payment terms. to be provided by supplier and to be discussed prior to contract agreement
6 Clarify the contract, will it be Musanada or Binhafeez? Binhafeez
1/1