Statement of Work Accomplishment (Swa) Asof:: % Relativ E WT
Statement of Work Accomplishment (Swa) Asof:: % Relativ E WT
%
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL RELATIV QUANTITY ACCOMPLISHMENT
E Wt. PREV. THIS PERIOD
101(2) Removal of Existing Headwalls (stone Masonry) 6.48 cu.m. -
101(4) Removal of Existing RCPC 610mm dia. (24'' dia. RCPC)(Removal of Existing ACP) 28.00 ln.m. -
102(2) Surplus Common Excavation 27,283.00 cu.m. -
103 Structure Excavation 791.51 cu.m. -
103(3) Foundation Fill 12.00 cu.m. -
103(6) Pipe Culvert and Drain Excavation 67.00 cu.m. -
104(1) Embankment from Excavation 8,543.00 cu.m. -
105 Subgrade Preparation 15,531.00 sq. m. -
200 Aggregate Sub-base Course, .30m. Thick 7,203.00 cu. m. -
300 Aggregate Surface Course, 0.15m. Thick 433.00 cu. m. -
311a PCCP, 0.28m Thick 13,196.00 sq. m. -
311b PCCP, 0.15m Thick 3,007.00 sq. m. -
404 Reinforcing Steel Bar, Grade 40 14,821.00 kg. -
405 Structural Concrete, Class A 366.00 cu.m. -
500 Reinf. Conc. Culvert Pipe, (610mm dia.) 18.00 ln.m. -
500(1) Reinf. Conc. Culvert Pipe, (910mm dia.) 95.00 ln.m. -
502(3) Catch Basin 6.00 each -
502(4) Concrete Cover 6.00 each -
503 Metal Frame & Grating 6.00 set -
505(5) Grouted Riprap, Class ''A'' 19.00 cu.m. -
506 Stone Masonry 121.00 cu.m. -
600(3) Concrete Curb and Gutter 122.00 ln.m. -
601 Sidewalk 244.00 sq. m. -
605(3) Informatory Signs 2.00 each -
611(1) Trees(Furnishing and Transplanting) 159.00 each -
612(1) Reflectorized Thermoplastic Pavement markings (white) 425.00 sq. m. -
612(2) Reflectorized Thermoplastic Pavement markings (yellow) 60.00 sq. m. -
622(1a) Bio-Engineered Erosion Coco Fiber Erosion Control Net (CGN 700) 3,055.28 sq. m. -
622(1b) Bio-Engineered Erosion Coco Fiber Erosion Control Net (CGN 400) 853.06 sq. m. -
622(2) Bio-Engineered Erosion Coco Logs/ Fascine Control System 447.70 ln.m. -
622(3) Bio-Engineered Erosion Control System (Vegetation) 3,908.33 sq. m. -
FEA 1.1a Bunkhouse, (7.00 x 9.00) 1.00 LS -
FEA 1.1b Facilities for the Engineers 1.00 LS -
FEA 1.2 Provision of a service vehicle for engineers 1.00 LS -
FEA 1.3 Construction Survey and Staking 1.84 Km. -
FEA 1.4 Project Billboard 2.00 Unit -
FEA 1.5 Construction Safety and Health Program 1.00 LS -
SPL-1 Mobilization and Demobilization 1.00 LS -
TOTAL
_________
Date Started:
yag Road (Mahayag-Dumingag), Zamboanga del Sur 1st DEO Target Completion Date:
L) (Net Length=1841.70 Ln.m) % Proj. Accomp. To Date:
Slippage;
MPLISHMENT (SWA)
ACCOMPLISHMENT %
WEIGHT
QUANTITY ACCOMPLISHMENT % ACCOMPLISHMENT VALUE OF ACCOMPLISHMENT ED REMARKS
THIS PERIOD TO DATE PREV. THIS PERIODTO DATE PREV. THIS PERIOD TO DATE ACCOMP.
Approved by:
SUS A. MANIAGO JR. TESSIE J. YU
zed Managing Officer Proprietor