Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


Zamboanga del Sur 1st Engineering District
Pagadian City

Accomplishment no. _________


Contrat ID :14JO0050
Name of Project:Construction of New Permanent Senote Bridge and approaches, Eastern Bobongan - Sominot - Midsalip - Dumingag Road, Zamboanga del Sur
Station: : 1669+58.00 - 1670+440.00, Abutment-A: Sta. 1669+783.85; Abutment-B: Sta. 1669+874.69 (Bridge Length: 90.84 Ln.m)
Location :Midsalip, Zamboanga del Sur
Contractor: :Montano Construction and Development
Contrat Amount:: 38,024,766.50
Status:
STATEMENT OF WORK ACCOMPLISHMENT (SWA)
AS OF :

% ACCOMPLISHM
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL RELATIVE QUANTITY ACCOMPLISHMENT % ACCOMPLISHM
Wt. PREV. THIS PERIOD TO DATE PREV. THIS PERIOD
103 Structure Excavation 1.00 LS 129,080.00 129,080.00 0.339%
104(1) Embankment (from excavation) 167.00 Days 601.92 100,520.64 0.264%
104(2) Embankment (Common Borrow) 6,864.80 Cu.m. 134.92 926,198.82 2.436%
105 Subgrade Preparation 410.00 Cu.m. 134.15 55,001.50 0.145%
200 Aggregate Subbase 319.73 Cu.m. 132.55 42,380.21 0.111%
300 Gravel Surface Course (uncrushed) 25.00 Sq.m. 12,899.01 322,475.25 0.848%
311a PCCP (Plain)-Conventional Method, 280mm thick 3,431.84 Cu.m. 195.30 670,238.35 1.763%
103(2) Bridge Excavation Above Ordinary Water Level 5,032.50 Sq.m. 23.17 116,603.03 0.307%
103(1) Bridge Excavation below Ordinary Water Level 3,280.00 Cu.m. 901.02 2,955,329.91 7.772%
400(4) Precast Concrete Piles, Furnished 426.00 Cu.m. 1,084.15 461,847.90 1.215%
400(6) Structural Steel Sheet Piles, Furnished 5,639.00 Sq.m. 1,637.67 9,234,821.13 24.286%
400(12) Structural Steel Sheet Piles, Driven 900.00 M. 4,720.89 4,248,801.00 11.174%
400(14) Precast Concrete Piles, Driven 864.00 M. 1,937.20 1,673,740.80 4.402%
400(16)a Test Piles, Furnished and Driven (400mmx400mm) 50.00 M. 3,735.20 186,760.00 0.491%
400(16)b Test Piles, Furnished and Driven (Sheet Piles) 30.00 M. 4,123.82 123,714.60 0.325%
401 Concrete railing 1,364.00 Kg. 99.10 135,172.40 0.355%
402 Timber Structures (Craneway) 1,803.92 Kg. 71.78 129,485.38 0.341%
404b Reinforcing Steel, Grade 60 55,316.10 Kg. 73.59 4,070,711.80 10.705%
404a Reinforcing Steel, Grade 40 224.72 Cu.m. 6,766.40 1,520,544.40 3.999%
405 Strcutural Concrete, Class A 119.16 Cu.m. 7,425.87 884,866.67 2.327%
406a PSC Girder, AASHTO Type IV-B, L=27.0 7.73 Cu.m. 6,560.69 50,714.13 0.133%
407 Lean Concrete 4.00 Each 1,011,552.50 4,046,210.00 10.641%
412 Elastomeric Bearing pad 8.00 Each 22,592.50 180,740.00 0.475%
414 Forms and Falsework 705.00 Cu.m. 3,492.65 2,462,318.25 6.476%
505 Grouted Riprap, Class A 170.00 Cu.m. 3,173.80 539,546.00 1.419%
507 Rubble Concrete, 0.30m. Thick 259.40 Cu.m. 3,594.34 932,371.80 2.452%
508 Hand Laid Rock Embankment 410.02 Cu.m. 2,000.50 820,245.01 2.157%
603(3)a Metal Guardrail (Metal Beam) including post 1,650.00 Sq.m. 292.15 482,047.50 1.268%
603(3)b Metal Beam End Piece 1,650.00 Sq.m. 185.61 306,256.50 0.805%
611(2) Trees Transplanting 2.00 Each 12,111.76 24,223.52 0.064%
620 Chevron Signs 1.00 LS 191,800.00 191,800.00 0.504%
FEA 1.1a Bunkhouse, (7.00 x 9.00) 2.00 LS 95,900.50 191,801.00 #DIV/0!
FEA 1.1b Facilities for the Engineers 3.00 LS 63,934.00 191,802.00 #DIV/0!
FEA 1.3 Project Billboard 4.00 LS 47,950.75 191,803.00 #DIV/0!
FEA 1.4 Construction safety and Health Program 5.00 LS 38,360.80 191,804.00 #DIV/0!
SPL-2 Mobilization & Demobilization 6.00 LS 31,967.50 191,805.00 #DIV/0!
SPL-3 Construction Survey and Staking 7.00 LS 27,400.86 191,806.00 #DIV/0!
612(1) Reflectorized Thermoplastic Pavement Markings (White) 8.00 LS 23,975.88 191,807.00 #DIV/0!
622(1) Bio-Engineering Erosion Coco Fiber Erosion Control Net 9.00 LS 21,312.00 191,808.00 #DIV/0!
622(2) Bio-Engineering Erosion Coco Logs/Fascine Control System 10.00 LS 19,180.90 191,809.00 #DIV/0!
622(3) Bio-Engineering Erosion Control System Vegetation 11.00 LS 17,437.27 191,810.00 #DIV/0!
TOTAL 38,024,766.50 100.00%

Prepared by: Checked & Verified by: Approved by


ENGR. JESUS A. MANIAGO JR.
Project Engineer Authorized Managing Officer
Project Duration: 288 CD

Date Started:
Target Completion Date:
% Proj. Accomp. To Date:
Slippage;

T OF WORK ACCOMPLISHMENT (SWA)


AS OF :

ACCOMPLISHMENT
% Wt. REMARKS
% ACCOMPLISHMENT VALUE OF ACCOMPLISHMENT ACCOMP.
THIS PERIOD TO DATE PREV. THIS PERIOD TO DATE

Approved by:
TESSIE J. YU
Proprietor