Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 127

Republic of the Philippines

Municipality of IPIL
BARANGAY :MAASIN

SUB- PROJECT PROGRAM OF WOR

Sub-Project TTitle Construction of Livelihood Training Center


Category Public Goods
Physical Target 54.00 sq. m.
Total Sub-Project Cost Php #NAME?
Cost Parameter #NAME?
PROJECT DESCRIPTION: Sub-Project Duration

Equipment/ Tools Needed


6m x 8m floor area, 1.5m x 2.50m Corridor CR/room, 1.5m x 1.5,
painting, installation of plumbing,electrical and tile Works.
Technical Personnel

Item no. Scope of Work ( Direct Cost ) % Wt. Quantity

I #NAME? #NAME? #NAME?


II CONCRETE WORKS #NAME? 3.44
III REINFORCING STEEL BARS #NAME? 322.79
IV FORMWORKS & SCAFFOLDING #NAME? 80.00
V MASONRY WORKS #NAME? 22.00
VI ROOFING WORKS #NAME? 41.00
VII CARPENTRY WORKS #NAME? 286.66
VIII DOORS AND WINDOWS #NAME? 18.00
IX #NAME? #NAME? 2.00
X #NAME? #NAME? #NAME?
XI #NAME? #NAME? #NAME?
XII #NAME? #NAME? 8.00
XIII #NAME? #NAME? #NAME?
IVX #NAME? #NAME? #NAME?
Total Direct Cost #NAME?

Breakdown of Estimated Total


Project Cost Construction KALAHI- Community

Cost CIDSS Grant Cash


A. Direct Cost
Materials 69,937.33 69,937.33
Equipment/Tools - -
Labor -
1) Skilled 12,650.00 10,550.00
2) Unskilled 8,400.00 5,586.00
Construction Forman - -
Signage #NAME? #NAME?

Sub-Total ( A ) #NAME? #NAME? -


B. Indirect Cost
Pre Engineering ( blue printing of plans) 3,000.00 -
Engineer's Supervision 2,000.00 -
Material Testing and Quality Control 3,000.00 -
Permits & Licences 3,000.00 -
Administrative and Overhead Expenses 22,000.00 -
#NAME? #NAME? #NAME?
Environmental Safety Requirements/PPE 3,000.00 -
Treasurer's Bond 5,000.00 -
CONTINGENCY 10,000.00 10,000.00

Sub-Total ( B ) #NAME? #NAME? -

TOTAL ( A+ B ) #NAME? #NAME? -

% Cost Sharing #NAME? #NAME? #NAME?


TOTAL ESTIMATED COST #NAME? #NAME? -
#NAME?

Prepared by : Checked & Reviewed by:

ENGR. PETER GER


Project Preparation Team Leader CTF

Recommended by:
ERNESTO JOSE C. BABIERA,CE CHIDEE S. RI
Municipal Engineer MCT-DAC

Concurred by :

HON. ELDWIN M. ALIBUTDAN


Municipal Mayor/ MIBF Chair
Philippines
of IPIL
MAASIN

RAM OF WORKS

69 CALINDAR DAYS

DAC/ME
Foreman

uantity Unit Unit Price Total Amount

sq.m. #NAME? #NAME?


Cu.m. 4,166.18 14,340.00
kgs. 61.68 19,910.00
bd.ft 39.95 3,196.00
sq.m. 728.64 16,030.00
sq.m. 533.45 21,871.33
bd.ft 35.21 10,094.00
sq.m. 321.00 5,778.00
Units #NAME? #NAME?
sq.m. #NAME? #NAME?
sq.m. #NAME? #NAME?
assy. #NAME? #NAME?
lot #NAME? #NAME?
C.D. #NAME? #NAME?
#NAME?

Source of Fund
mmunity BLGU MLGU PLGU
Other
In-Kind Cash In-Kind Cash In-Kind Sources
2,100.00
2,814.00

10,000.00

4,914.00 - - 10,000.00 - -

3,000.00
2,000.00
3,000.00
3,000.00
22,000.00
4,865.00
3,000.00
5,000.00

- - - 40,865.00 5,000.00 -

4,914.00 - - 50,865.00 5,000.00 -

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


4,914.00 - - 50,865.00 5,000.00
(12,665.00)

Approved by :

PETER GERONILLA
CTF BSPMC Chairman

Concurred by:
HIDEE S. RICO
MCT-DAC Barangay Chairman

Noted by:

ENGR. ROLEISTE C. FALSIS


Regional Community Infrastructure Specialist
NAME OF

ITEM NO. ITEM DESCRIPTION

I CONCRETE WORKS
Volume
Structure width (Meters)

1 Wall Footing 0.30


2 Column Footing-1 0.60
3 Column-1 0.20
4 Floor Area 14.00
Using Class "A" Mixture:
CEMENT-9.08 bags/cu.m. of concrete+5% wastage
SAND-0.58 cu.m./cu.m. of concrete+10% wastage
GRAVEL-0.77 cu.m./cu.m. of concrete+10% wastage
MATERIALS
Portland Cement
Washed Sand
Washed Gravel

Using Capability Output:


For Concrete Pouring use 2.5 cu.m./man-day

Mason
Laborer

TOTAL FOR CONCRETING

III REINFORCING STEEL BARS


6.00 Number of RSB

16mm dia. by 6m RSB


Structure
(pcs.)

1 Wall Footing
2 Masonry Wall (Vert.&Hor.)
3 Column Footing-1
4 Column-1
0.00
Columns: 12mm x 6.0m RSB
Col. Footing: 12mm x 6.0m RSB
Masonry Wall (Vert.&Hor.) 10mm x 6.0m RSb

MATERIALS
12mm dia. x 6.0m RSB
10mm dia. x 6.0m RSB
# 16 G.I. Tie Wire
Hacksaw Blade

Using Capability Output:


For Steel Works: Cut,Bend & Place RSB: 80 kgs.man-days (1 Gang: 1 Steel
LABOR
Steelman
Laborer

TOTAL FOR REINFORCING BA

IV FORMWORKS & SCAFFOLDING


1.00 TWO USE
10pcs. - 2"x3"x8' Form Lumber
15 pcs.- 2"x2"x8' Form Lumber
1/4 thk. 4'x8' Ordinary Plywood
#4 CWN
#3 CWN
#1 CWN

Using Capability Output:


For Fabrication, Placing & dismantling of forms:
1 Gang: 2-carpenters & 4 Laborers = 2.50cu.m. /day
Volume of concrete = 3.44
LABOR
Carpenter
Laborer

TOTAL FOR FORMWORKS AND SCAF

V MASONRY WORKS
4.50 V-1. CHB Laying

Structure Ext. Wall Area (sq.m.)

Wall Area 22.00


Terrace
C.R. Partition 0.00
Septic Vault Area 0.00

Using Class "B" Mixture:


CEMENT - 0.525 bags/sq.m. of concrete + 5% wastage
SAND - 0.0435 cu.m./sq.m. of concrete + 10% wastage(for 4")
SAND - 0.0844 cu.m./sq.m. of concrete + 10% wastage( for 6")
MATERIALS
Portland Cement
Washed Sand
Washed Sand
4" x 8' x 16" CHB

Using Capability Output:


Crew: 2men lay 100 pcs./day
Mason
Laborer

V-2. Plastering

Structure Ext. Wall Area (sq.m.)

Wall Area 22.00


Terrace 0.00
C.R. Partition 0.00

Using Class "A" Mixture:


For 20mm thick :
Cement - 0.36 bags / sq.m. + 5% wastage
Sand - 0.020 cu.m./ sq.m. + 10% wastage
MATERIALS
Portland Cement
Screened Sand
Using Capability Output:
For Plain/Fine Finish Crew: 2 men plaster 8 sq.m./day
LABOR
Mason
Laborer

TOTAL FOR MASONRY

ROOFING WORKS
5.00 Roof Framing (TIMBER)
A. Materials
24pcs. - 2"x4"x10' Good Lumber
24pcs. - 2"x5"x10' Good Lumber
54pcs. - 2"x3"x10' Good Lumber
#5 CWN
#4 CWN
Sub-Total

B. Labor
Carpenter
Laborer

A. Materials
Corrugated G.I.Sheet,0.70 x 8'(Galvalum)
GI PLANE SHEET Ridge Roll 8'
Roof Nails
Using Capability Output:
Roof Coverings (G.I. Sheets)= 30 pcs./man-days
Total # of sheets = 30.00
No. of days = 77/30 2.56 say 3.0 days
Installation of Ridge Cap = 10 length / man-days
No. of ridge cap= 3.0 length
No. of days = 1.0 day
LABOR
Carpenters
Laborer

TOTAL FOR ROOFING

CARPENTRY WORKS
MATERIALS
2" x 4" x10' Good lumber
2" x 2" x10' Good lumber
1/4" x 4' x 8' Marine Plywood
4" CW Nails
1 " CW Nails

Using Capability Output:


Ceiling Joist and Hangers 16 sq.m./man-days
Area = 91.3
No. of days = 91.3/16 sq.m = 5.7 days Say 6.0 Days
Ceiling Boards (4' x 8' Plywood) 30 sq.m./man-days

Area = 91.3
No. of days = 91.3/30sq.m
No. of days = 3.00
Carpenters
Laborer

TOTAL FOR CARPENTRY WOR

VI DOORS AND WINDOWS


#REF! DOORS
MATERIALS
D-1, (1.0m x 2.10m) Solid Panel Door
WOODEN JALOUSIE
DOOR LOCK
(4" x 4") loose pin hinges

Using Capability Output:


Door Installation = 1 pannel /man-day
LABOR
Carpenters
Laborer

TOTAL FOR DOORS & WINDO


A MATERIALS COST
B EQUIPMENTS
C LABOR COST
Skilled
Unskilled
D SIGNAGE
E Construction Foreman
DIRECT COST
INDIRECT COST
F Pre Engineering ( blue printing of plans)
G Engineer's Supervision
H Material Testing and Quality Control
I Permits & Licences
J Administrative and Overhead Expenses
L Environmental Safety Requirements/PPE
M Treasurer's Bond
N CONTINGENCY
TOTAL INDIRECT COST

TOTAL CONSTRUCTION COST


Prepared by :

Project Preparation Team Leader

Recommended by:

ERNESTO JOSE C. BABIERA,CE


Municipal Engineer

Concurred by :

HON. ELDWIN M. ALIBUTDAN


Municipal Mayor/ MIBF Chair
AME OF SUB-PROJECT: CONSTRUCTION OF LI
TRAINING CENTER

BILL OF QUANTITIES

No. of Crew/
RIPTION QUANTITY UNIT
Labor

3.44 cu.m.
Volume
number of
length (Meters) depth (Meters) Total Unit
structure
21.20 0.15 1.00 0.95 cu.m.
0.60 0.20 8.00 0.58 cu.m.
0.20 1.60 8.00 0.51 cu.m.
00 0.10 1.00 1.40 cu.m.
TOTAL 3.44 cu.m.
IALS
32.00 Bags
3.00 Cu.m.
3.00 Cu.m.
SUB-TOTAL

2.00 Day/s 2.00


2.00 Day/s 2.00
SUB-TOTAL
ONCRETING

322.79 KGS
mber of RSB

12mm dia. by 6m 10mm dia. by 8mm dia. by


RSB (pcs.) 6m RSB (pcs.) 6m RSB (pcs.)

15
17
8
13 25
21.00 57.00 0.00
unit
unit wt./m wt./6 m qnty.
rsb

0.888 5.33 21
0.617 3.70 57
TOTAL WEIGHT 1.505 9.028 78.000
IALS
21.00 Length
57.00 Length
7.00 Kgs.
2.00 Pcs.
SUB-TOTAL

1 Gang: 1 Steelman and 1 Labor)


OR
6.00 Day/s 2.00
6.00 Day/s 2.00
SUB-TOTAL
FORCING BAR

80.00 Bd.Ft

40.00 Bd.Ft
40.00 Bd.Ft
2.00 shts.
1.00 Kgs.
1.00 Kgs.
2.00 Kgs.
SUB-TOTAL

cu.m.
OR
1.00 Day/s 2.00
1.00 Day/s 2.00
SUB-TOTAL
KS AND SCAFOLDING

22.00 sq.m.
WALL AREA
W5
W2 Area W3 Area W4 Area D1 Area
W1 Area (sq.m.) Area
(sq.m.) (sq.m.) (sq.m.) (sq.m.)
(sq.m.)
0.00 0.00 0.00 0.00 0.00

TOTAL
12.0 Bags
1.0 Cu.m.
2.0 Cu.m.
275.0 Pcs
SUB-TOTAL

3.00 Day/s 2.00


3.00 Day/s 2.00
SUB-TOTAL
190.00 sq.m.
WALL AREA
W6
W2 Area W3 Area W5 Area D1 Area
W1 Area (sq.m.) Area
(sq.m.) (sq.m.) (sq.m.) (sq.m.)
(sq.m.)
0.00 0.00 0.00 0.00 0.00 0.00

TOTAL AREA

IALS
8.00 Bags 1.00
1.00 Cu.m. 1.00
SUB-TOTAL
OR
1.50 Day/s 2.00
1.50 Day/s 2.00
SUB-TOTAL
MASONRY

41.00 sq.m. -

66.67 Bd.Ft
125.00 Bd.Ft
140.00 Bd.Ft
4.00 Kgs.
2.00 Kgs.

2 Days 2.00
2 Days 2.00
Sub-Total

30.00 Shts.
1.00 Sht.
5.00 kls.
SUB-TOTAL

OR
3.00 Day/s 2.00
3.00 Day/s 2.00
SUB-TOTAL
ROOFING

286.66 Bd.Ft.
IALS
100.00 Bd. Ft.
144.00 Bd. Ft.
19.00 Shts.
3.00 Kgs.
5.00 Kgs.
SUB-TOTAL

s Say 6.0 Days


ddddd
2.00 Day/s 2.00
2.00 Day/s 2.00
SUB-TOTAL
ENTRY WORKS

18.00 sq-m

IALS
2 Sets
5 Sets
2 Sets
6 Sets
SUB-TOTAL

OR
1 Days 1.00
1 Days 1.00
SUB-TOTAL
RS & WINDOWS
COST
Checked & Reviewed by:

ENGR. PETER GERONIL


Community Technical Facilita

CE CHIDEE S. RICO
MCT-CTF

N
ON OF LIVELIHOOD

Freight & Handling


RATE PER
DAY/ TOTAL
UNIT COST supplier pob. To Total Total
to Pob. brgy. Hauling Cost
260.00 8,320.00
620.00 1,860.00
720.00 2,160.00
12,340.00

300.00 1,200.00
200.00 800.00
2,000.00
14,340.00
total wt.

-
111.89
210.90
322.788

228.00 4,788.00
148.00 8,436.00
78.00 546.00
70.00 140.00
13,910.00

300.00 3,600.00
200.00 2,400.00
6,000.00
19,910.00

18.00 720.00
18.00 720.00
250.00 500.00
58.00 58.00
58.00 58.00
70.00 140.00
2,196.00

300.00 600.00
200.00 400.00
1,000.00
3,196.00

D2 Area
Area Total (sq.m.)
(sq.m.)

- 22.00
-
-
-
22.00
260.00 3,120.00
620.00 620.00
620.00 1,240.00
14.00 3,850.00
8,830.00

300.00 1,800.00
200.00 1,200.00
3,000.00

D2 Area
Area Total (sq.m.)
(sq.m.)

0.00 22.00
-
-
22.00

260.00 2,080.00
620.00 620.00
2,700.00
300.00 900.00
200.00 600.00
1,500.00
16,030.00

20.00 1,333.33
20.00 2,500.00
20.00 2,800.00
58.00 232.00
58.00 116.00
6,981.33

300.00 1,200.00
200.00 800.00
2,000.00

308.00 9,240.00
300.00 300.00
70.00 350.00
9,890.00

300.00 1,800.00
200.00 1,200.00
3,000.00
21,871.33

19.00 1,900.00
20.00 2,880.00
250.00 4,750.00
58.00 174.00
58.00 290.00
8,094.00
300.00 1,200.00
200.00 800.00
2,000.00
10,094.00

930.00 1,860.00
500.00 2,500.00
380.00 760.00
18.00 108.00
5,228.00

350.00 350.00
200.00 200.00
550.00
5,778.00
TOTAL
69,937.33

12,650.00
8,400.00

90,987.33

3,000.00
2,000.00
3,000.00
3,000.00
22,000.00
3,000.00
5,000.00
10,000.00
51,000.00

141,987.33
Approved by :

ER GERONILLA
echnical Facilitator BSPMC Chairman

Concurred by:

EE S. RICO
CT-CTF Barangay Chairman

Noted by:

ENGR. ROLEISTE C. F
Regional Community Infrastructure Specialis
COST SHARING

COMMUNITY
CONTRIBUTION LGU OT
NCDDP
HE
GRANT
RS
In-kind BRGY.MUN.
PROV.
1,200.00 200.00
800.00 268.00 Unskilled
3,600.00 600.00
2,400.00 804.00 Unskilled
600.00 100.00
400.00 134.00 Unskilled
1,800.00 300.00
1,200.00 402.00 Unskilled
900.00 150.00
600.00 201.00 Unskilled

1,200.00 200.00
800.00 268.00 Unskilled
1,800.00 300.00
1,200.00 402.00 Unskilled
1,200.00 200.00
800.00 268.00 Unskilled

300.00 50.00
200.00 67.00 Unskilled
21,000.00 4,914.00

12,600.00 2,100.00
8,400.00 2,814.00
BSPMC Chairman

Barangay Chairman

ENGR. ROLEISTE C. FALSIS


ommunity Infrastructure Specialist
PROJECT TITLE: ONE STOREY RESIDENTIAL BUILDING
PROJECT LOCATION BRGY. NAPOLAN, PAGADIA CITY, ZAMBOANGA DEL SUR

BILL OF LABOR AND MATERIALS


RATE PER
No. of Crew/
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT
Labor
DAY/ TOTAL
UNIT COST

Roof Framing (timber)


A. Materials
2"x4"x10' Good Lumber 66.67 Bd.Ft 25.00 1,666.67
2"x5"x10' Good Lumber 125.00 Bd.Ft 25.00 3,125.00
2"x3"x10' Good Lumber 140.00 Bd.Ft 25.00 3,500.00
#5 CWN 4.00 Kgs. 58.00 232.00
#4 CWN 2.00 Kgs. 58.00 116.00
#3 CWN 3.00 Kgs. 58.00 174.00
Corrugated G.I.Sheet,1.00 x 10'(Galvalum) 30.00 Shts. 308.00 9,240.00
G.I Plane Sheet GA #24 1.00 Pcs. 300.00 300.00
Roof Nails 5.00 kls. 70.00 350.00
MATERIALS SUB-TOTAL 18,703.67
LABOR SUB-TOTAL 3,000.00
TOTAL FOR ROOFING 21,703.67
VI CARPENTRY WORKS 286.66 Bd.Ft.
A. Materials
6" x 6" x 10' 240.00 Bd.ft 28.00 6,720.00
2" x 2" x 10' 144.00 Bd.ft 18.00 2,592.00
4" CW Nails 3.00 kls 80.00 240.00
1" CW Nails 5.00 kls 80.00 400.00
MATERIALS Sub-Total 9,552.00
LABOR Sub-Total 2,000.00
TOTAL FOR CARPENTRY WORKS 11,552.00
VII DOORS AND WINDOWS 18.00 sq-m
DOORS
D-1, (1.0m x 2.10m) Solid Panel Door 2 Sets 930 1860
WOODEN JALOUSIE 5 Sets 500 2500
DOOR LOCK 2 Sets 380 760
(4" x 4") loose pin hinges 6 Sets 18 108

MATERIALS SUB-TOTAL 5,228.00


LABOR SUB-TOTAL 550.00
TOTAL FOR DOORS & WINDOWS 5,778.00
A MATERIALS COST 33,483.67
C LABOR COST 5,550.00
TOTAL CONSTRUCTION COST 39,033.67

Prepared by :

ALJIE S. CANETE
CIVIL ENGINEER
PROJECT TITLE: ONE STOREY RESIDENTIAL B
PROJECT LOCATION STA. MARIA, PAGADIA CITY Z
SUBJECT: BILL OF LABOR AND MATERI
ITEM ELECTRICAL WORKS
1 4" x 4" Juncton Boxes PVC w/Cover
2 3/4" dia. RSC Pipe
3 5.5mm2 THW Stranded
2.0mm2 THW Stranded
4 3.5mm2 THW Stranded
5 PVC Clamp 3/4"
6 Flexible tube 3/4" dia
7 Electrical Tape (Big)
8 CFL 15 watts
9 2 Gang Switch
10 1 Gang Switcth
11 2 Gang Con. Outlet
12 Ligthing Outlet ( 4" Plastic Receptacle w/Cover)
13 Entrance Cap # 3/4" dia.
14 2B Panel Board w/Circuit Breaker ( 1-20A,1-15A)

MATERIALS SUB-TOTAL
LABOR SUB-TOTAL
TOTAL FOR ELECTRICAL WORKS

Prepared by :

ENGR. ARNEL CANTER


PROFESSIONAL ELECTRICAL EN
ESIDENTIAL BUILDING
GADIA CITY ZDS
AND MATERIALS
fixtures
3.00 pcs. 35.00 105.00
1.00 length 300.00 300.00
20.00 m 53.00 1,060.00
1.00 box 2,950.00 2,950.00
1.00 box 3,550.00 3,550.00
7.00 Pcs. 3.00 21.00
1.00 Roll 1,200.00 1,200.00
2.00 Pcs. 30.00 60.00
9.00 sets 178.00 1,602.00
4.00 Pcs. 102.00 408.00
1.00 Pcs. 20.00 20.00
7.00 Pcs. 64.00 448.00
9.00 Pcs. 21.00 189.00
1.00 pcs. 53.00 53.00
1.00 Set 2,067.00 2,067.00

14,033.00
1,713.00
15,746.00

NEL CANTERO
ELECTRICAL ENGINEER
#NAME? #NAME? #NAME? #NAME?
4" x 8' x 16" CHB 275.00 Pcs 3,850.00
#NAME? #NAME? #NAME? #NAME?
Screened Sand 1.00 Cu.m. 620.00
Washed Gravel 3.00 Cu.m. 2,160.00
Washed Sand 3.00 Cu.m. 1,860.00
Washed Sand 1.00 Cu.m. 620.00
Washed Sand 2.00 Cu.m. 1,240.00

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
(4" x 4") loose pin hinges 6.00 Sets 108.00
D-1, (1.0m x 2.10m) Solid Panel Door 2.00 Sets 1,860.00
WOODEN JALOUSIE 5.00 Sets 2,500.00
#NAME? #NAME? #NAME? #NAME?
DOOR LOCK 2.00 Sets 760.00

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME?

Portland Cement 32.00 Bags 8,320.00


Portland Cement 12.00 Bags 3,120.00
Portland Cement 8.00 Bags 2,080.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
# 16 G.I. Tie Wire 7.00 Kgs. 546.00
#NAME? #NAME? #NAME? #NAME?
#1 CWN 2.00 Kgs. 140.00
1 " CW Nails 5.00 Kgs. 290.00
#3 CWN 1.00 Kgs. 58.00
#4 CWN 1.00 Kgs. 58.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
4" CW Nails 3.00 Kgs. 174.00
#NAME? #NAME? #NAME? #NAME?
10mm dia. x 6.0m RSB 57.00 Length 8,436.00
12mm dia. x 6.0m RSB 21.00 Length 4,788.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Hacksaw Blade 2.00 Pcs. 140.00
#NAME? #NAME? #NAME? #NAME?
1/4 thk. 4'x8' Ordinary Plywood 2.00 shts. 500.00
1/4" x 4' x 8' Marine Plywood 19.00 Shts. 4,750.00

#NAME? #NAME? #NAME? #NAME?


15 pcs.- 2"x2"x8' Form Lumber 40.00 Bd.Ft 720.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
10pcs. - 2"x3"x8' Form Lumber 40.00 Bd.Ft 720.00
2" x 2" x10' Good lumber 144.00 Bd. Ft. 2,880.00

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Roof Nails 5.00 kls. 350.00
#NAME? #NAME? #NAME? #NAME?
54pcs. - 2"x3"x10' Good Lumber 140.00 Bd.Ft 2,800.00
#NAME? #NAME? #NAME? #NAME?
GI PLANE SHEET Ridge Roll 8' 1.00 Sht. 300.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
24pcs. - 2"x5"x10' Good Lumber 125.00 Bd.Ft 2,500.00
24pcs. - 2"x4"x10' Good Lumber 66.67 Bd.Ft 1,333.33
#4 CWN 2.00 Kgs. 116.00
#NAME? #NAME? #NAME? #NAME?
Corrugated G.I.Sheet,0.70 x 8'(Galvalum) 30.00 Shts. 9,240.00

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME?
#NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
- 3.44 cu.m. -
- - - 12,340.00
- - - -
- - - 2,000.00
- - - -
- - - -
- unit wt./m unit wt./6 m -
- 1.50 9.03 -
- - - 13,910.00
- - - 6,000.00
- - - -
- - - 2,196.00
- - - 1,000.00
- - - -
- - - 22.00
- - - 8,830.00
- - - 3,000.00
- - - 22.00
- - - -
- - - 2,700.00
- - - 1,500.00
- - - -
- - - -
- - - 2,000.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
- - - -
- - - 9,890.00
- - - 3,000.00
- - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
- - - 8,094.00
- - - 2,000.00
- - - -
- - - 5,228.00
- - - 550.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
- - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Laborer 2.00 Days 800.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
MASONRY WORKS - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
1 Gang: 2-carpenters & 4 Laborers = 2.50cu.m. /day - - -
#NAME? #NAME? #NAME? #NAME?
A. Materials - - -
A. Materials - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Area = - - -
Area = - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
B. Labor - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
C.R. Partition - - -
C.R. Partition - - -
#NAME? #NAME? #NAME? #NAME?
Carpenter 1.00 Day/s 600.00
Carpenter 2.00 Days 1,200.00
Carpenters 3.00 Day/s 1,800.00
Carpenters 2.00 Day/s 1,200.00
Carpenters 1.00 Days 350.00
#NAME? #NAME? #NAME? #NAME?
CARPENTRY WORKS - - -
Ceiling Boards (4' x 8' Plywood) - - -
Ceiling Joist and Hangers - - -
Cement - 0.36 bags / sq.m. + 5% wastage - - -
CEMENT - 0.525 bags/sq.m. of concrete + 5% wastage - - -
CEMENT-9.08 bags/cu.m. of concrete+5% wastage - - -
Col. Footing: 0.89 5.33 -
#NAME? #NAME? #NAME? #NAME?
Column Footing-1 0.58 cu.m. -
Column Footing-1 - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Column-1 0.51 cu.m. -
Column-1 - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Columns: - - -
#NAME? #NAME? #NAME? #NAME?
CONCRETE WORKS 3.44 cu.m. -
#NAME? #NAME? #NAME? #NAME?
Crew: 2men lay 100 pcs./day - - -
Door Installation = 1 pannel /man-day - - -
DOORS - - -
DOORS AND WINDOWS 18.00 sq-m -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Floor Area 1.40 cu.m. -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
For 20mm thick : - - -
For Concrete Pouring use 2.5 cu.m./man-day - - -
For Fabrication, Placing & dismantling of forms: - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
For Plain/Fine Finish Crew: 2 men plaster 8 sq.m./day - - -
#NAME? #NAME? #NAME? #NAME?
For Steel Works: Cut,Bend & Place RSB: 80 kgs.man-days (1 Gang: 1 S - - -
#NAME? #NAME? #NAME? #NAME?
FORMWORKS & SCAFFOLDING 80.00 Bd.Ft -
GRAVEL-0.77 cu.m./cu.m. of concrete+10% wastage - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Installation of Ridge Cap = - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
LABOR - - -
LABOR - - -
LABOR - - -
LABOR - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
LABOR - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Laborer 2.00 Day/s 800.00
Laborer 6.00 Day/s 2,400.00
Laborer 1.00 Day/s 400.00
Laborer 3.00 Day/s 1,200.00
Laborer 1.50 Day/s 600.00
Laborer 3.00 Day/s 1,200.00
Laborer 2.00 Day/s 800.00
Laborer 1.00 Days 200.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Mason 2.00 Day/s 1,200.00
Mason 3.00 Day/s 1,800.00
Mason 1.50 Day/s 900.00
#NAME? #NAME? #NAME? #NAME?
Masonry Wall (Vert.&Hor.) - - -
Masonry Wall (Vert.&Hor.) 0.62 3.70 -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
MATERIALS - - -
MATERIALS - - -
MATERIALS - - -
MATERIALS - - -
MATERIALS - - -
MATERIALS - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
No. of days = - - -
No. of days = - - -
#NAME? #NAME? #NAME? #NAME?
No. of days = - - -
No. of days = - - -
No. of days = - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
No. of ridge cap= - - -
#NAME? #NAME? #NAME? #NAME?
Number of RSB - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
REINFORCING STEEL BARS 322.79 KGS -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Roof Coverings (G.I. Sheets)= - - -
Roof Framing (TIMBER) - - -
ROOFING WORKS - - -
Sand - 0.020 cu.m./ sq.m. + 10% wastage - - -
SAND - 0.0435 cu.m./sq.m. of concrete + 10% wastage(for 4") - - -
SAND - 0.0844 cu.m./sq.m. of concrete + 10% wastage( for 6") - - -
SAND-0.58 cu.m./cu.m. of concrete+10% wastage - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Septic Vault Area - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Steelman 6.00 Day/s 3,600.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Structure Total Unit -
Structure - - -
Structure W4 Area (s W5 Area (s Area Total (sq
Structure W5 Area (s W6 Area (s Area Total (sq
#NAME? #NAME? #NAME? #NAME?
Sub-Total - - 6,981.33
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Terrace - - -
Terrace - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Total # of sheets = - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
TOTAL FOR CARPENTRY WORKS - - 10,094.00
TOTAL FOR CONCRETING - - 14,340.00
TOTAL FOR DOORS & WINDOWS - - 5,778.00
#NAME? #NAME? #NAME? #NAME?
TOTAL FOR FORMWORKS AND SCAFOLDING - - 3,196.00
#NAME? #NAME? #NAME? #NAME?
TOTAL FOR MASONRY - - 16,030.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
TOTAL FOR REINFORCING BAR - - 19,910.00
TOTAL FOR ROOFING - - 21,871.33
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
TWO USE - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Using Capability Output: - - -
Using Capability Output: - - -
Using Capability Output: - - -
Using Capability Output: - - -
Using Capability Output: - - -
Using Capability Output: - - -
Using Capability Output: - - -
Using Capability Output: - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Using Class "A" Mixture: - - -
Using Class "A" Mixture: - - -
Using Class "B" Mixture: - - -
V-1. CHB Laying 22.00 sq.m. -
V-2. Plastering 190.00 sq.m. -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Volume - - -
#NAME? #NAME? #NAME? #NAME?
Volume of concrete = - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
WALL AREA - - -
Wall Area - - 22.00
WALL AREA - - -
Wall Area - - 22.00
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME?
Wall Footing 0.95 cu.m. -
Wall Footing - - -
#NAME? #NAME? #NAME? #NAME?
#NAME? A
MATERIALS COST A
#NAME? A
MATERIALS COST A
MATERIALS COST A
MATERIALS COST A
MATERIALS COST A
MATERIALS COST A

#NAME? DW
#NAME? DW
#NAME? DW
#NAME? DW
#NAME? DW
#NAME? DW
#NAME? DW
#NAME? DW
#NAME? DW
MATERIALS COST DW
MATERIALS COST DW
MATERIALS COST DW
#NAME? DW
MATERIALS COST DW

#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E
#NAME? E

#NAME? F

MATERIALS COST H
MATERIALS COST H
MATERIALS COST H
#NAME? TW
#NAME? H
MATERIALS COST H
#NAME? H
MATERIALS COST H
MATERIALS COST H
MATERIALS COST H
MATERIALS COST H
#NAME? H
#NAME? H
#NAME? H
#NAME? H
MATERIALS COST H
#NAME? H
MATERIALS COST H
MATERIALS COST H
#NAME? H
#NAME? H
MATERIALS COST H
#NAME? H
MATERIALS COST H
MATERIALS COST H

#NAME? L
MATERIALS COST L
#NAME? L
#NAME? L
MATERIALS COST L
MATERIALS COST L

#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL
#NAME? PL

#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW
#NAME? PW

#NAME? R
#NAME? R
#NAME? R
#NAME? R
MATERIALS COST R
#NAME? R
MATERIALS COST R
#NAME? R
MATERIALS COST R
#NAME? R
#NAME? R
MATERIALS COST R
MATERIALS COST R
MATERIALS COST R
#NAME? R
MATERIALS COST R

#NAME? TW
#NAME? TW
#NAME? TW
#NAME? TW

#NAME? EQ
#NAME? EQ

#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
#NAME?
#NAME?
#NAME?
-
-
-
-
#NAME?
#NAME?
-
-
-
-
-
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
Unskilled
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
-
#NAME?
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
-
-
#NAME?
Skilled
Skilled
Skilled
Skilled
Skilled
#NAME?
-
-
-
-
-
-
-
#NAME?
-
-
#NAME?
#NAME?
#NAME?
#NAME?
-
-
#NAME?
#NAME?
#NAME?
-
#NAME?
-
#NAME?
-
-
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
#NAME?
#NAME?
-
#NAME?
-
#NAME?
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
Unskilled
Unskilled
Unskilled
Unskilled
Unskilled
Unskilled
Unskilled
Unskilled
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
Skilled
Skilled
Skilled
#NAME?
-
-
#NAME?
#NAME?
#NAME?
-
-
-
-
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
#NAME?
-
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
-
-
-
-
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
Skilled
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
-
#NAME?
-
#NAME?
#NAME?
#NAME?
-
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
#NAME?
-
#NAME?
-
#NAME?
#NAME?
-
-
#NAME?
#NAME?
#NAME?
-
#NAME?
#NAME?
#NAME?
-
-
-
-
-
-
-
-
#NAME?
#NAME?
#NAME?
-
-
-
-
-
#NAME?
#NAME?
#NAME?
#NAME?
-
#NAME?
-
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
-
-
-
-
#NAME?
#NAME?
#NAME?
-
-
#NAME?
SCHEDULE OF IN-KIND LOCAL COUNTERPART CONTRIBUT

November 11, 2014


Barangay : MAASIN Construction of Livelihood Training Center
Municipality : IPIL #NAME?
Province : Zamboanga Sibug 69 CALINDAR DAYS
Estimated Cost 1st Tranche 7,931.20
2nd Tranche 991.40
Mode of Implementation: 3rd Tranche 991.40

PROCURE ESTIMATED COST INVOLVED


PACKAG
PACKAGE ITEMS TOTAL AMOUNT MENT 1st Tranche 2nd Tranche
E
METHOD In-Kind In-Kind
1) Skilled 2,100.00 CFA 1,680.00 210.00
P-9
2) Unskilled 2,814.00 CFA 2,251.20 281.40
Engineer's Supervision 2,000.00 CFA 1,600.00 200.00
Permits & Licences 3,000.00 CFA 2,400.00 300.00

TOTAL 9,914.00 7,931.20 991.40

Prepared by: Checked & Reviewed by:

ENGR. PETER GERONILLA CHIDEE S. RICO


Procurement Team Head CTF MCTF
Name & Signature
ART CONTRIBUTION

aining Center

LCC (In-Kind) : 9,914.00

IMPLEMENTATION
COST INVOLVED & SCHEDULE OF DELIVERY SCHEDULE
2nd Tranche 3rd Tranche MONTH
TOTAL
In-Kind In-Kind 1 2 3 4 5 6
210.00 2,100.00
281.40 2,814.00
200.00 2,000.00
300.00 3,000.00

-
991.40 991.40 9,914.00

Recommended by: Approved by:

ERNESTO JOSE C. BABIERA, CE


Municipal Engineer BSPMC Chairperson
Item Description of Works Total Cost W% Duration 1 2 3 4 5
1 #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
2 CONCRETE WORKS 14,340.00 #NAME? 0.00
3 REINFORCING STEEL BARS 19,910.00 #NAME? 6.00 #NAME? #NAME? #NAME?
FORMWORKS &
4 3,196.00 #NAME? 1.00
SCAFFOLDING
5 MASONRY WORKS 16,030.00 #NAME? 4.50
6 ROOFING WORKS 21,871.33 #NAME? 5.00
7 CARPENTRY WORKS 10,094.00 #NAME? #NAME?
8 DOORS AND WINDOWS 5,778.00 #NAME? #REF!
9 #NAME? #NAME? #NAME? #NAME?
10 #NAME? #NAME? #NAME? #NAME?
11 #NAME? #NAME? #NAME? #NAME?
12 #NAME? #NAME? #NAME? #NAME?
13 #NAME? #NAME? #NAME? 1.00 #NAME?

14 #NAME? #NAME? #NAME? 48.00 #NAME? #NAME? #NAME? #NAME? #NAME?


Total Direct Cost #NAME? #NAME? Plan #NAME? #NAME? #NAME? #NAME? #NAME?
Plan Communlative Total: #NAME? #NAME? #NAME? #NAME? #NAME?
Actual

Prepared by: Reviewed by:

ENGR. PETER GERON


PPT Chair Community Technical Fac

Noted by:

ENGR. CHERRY VILLANUEVA


Community Procurement Officer
CONSTRU
Construction o
Barang

6 7 8 9 10 11 12 13 14 15 16 17 18 19
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

1st Tranche 2nd Tranche Request


Request

Checked by:

PETER GERONILLA ERNESTO


nity Technical Facilitator Muni

VA
nt Officer
CONSTRUCTION SCHEDULE
Construction of Livelihood Training Center
Barangay Maasin , Ipil, ZS.

20 21 22 23 24 25 26 27

#NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?

#NAME?

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

3rd Tranche Request

Request for 2nd Tranche

ERNESTO JOSE C. BABIERA, CE


Municipal Engineer

Approved by:

BSPMC Chairperso
28 29 30 31 32 33 34 35 36 37 38 39 40

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?

###

#NAME?
#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

Request for 2nd Tranche

NUMBER OF WORKING DAYS : 48 Days


NUMBER OF SUNDAY : 6 Days
UNWORKABLE WEATHER CONDITION : 15 Days
DURATION : 69 Calendar Days

BSPMC Chairperson
1.2

41 42 43 44 45 46 47 48 1

0.8

a
t
u
0.6 a
l

#NAME? #NAME? R
#NAME? #NAME? 0.4 o
w

#NAME? #NAME? #NAME? #NAME? #NAME? 4


4
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
0.2

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


0
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

Request for Final Tranche

Days
1.2

0.8

a
t
u
0.6 a
l

R
0.4 o
w
4
4

0.2

0
KALAHI - CIDSS NATIONAL COMMUNITY
COMMUNITY PROCURE

Name of Proposed Community Project: Construction of Livelihood Training Cent


Barangay: MAASIN Municipality:
Total Estimated Cost: #NAME? KC/Grant Cost:
Community Project Duration: 69 CALINDAR DAYS
Estimated Cost: 1st Tranche : #NAME? 2nd Tranche :
ITEM NO.
PACKAGE

PACKAGE ITEMS QTY


S

P-1 1 SIGNAGE 1.00


Pre-Fab. Signages w/ Lettering including Installation

(Description: 1.22mx2.44m ,#24 Plain sheet signboard,framed with 1/4"thk x 1" angle
bar supported w/ Grade 40 x 2 1/2" dia. G.I Pipe,founded on concrete pedestal)

Sub-Total
AGGREGATE MATERIALS
P-2 1 #NAME? #NAME?
2 4" x 8' x 16" CHB 275.00
3 #NAME? #NAME?
4 Screened Sand 1.00
5 Washed Gravel 3.00
6 Washed Sand 6.00

Sub-Total

P-3 LUMBER MATERIALS


1 #NAME? #NAME?
2 15 pcs.- 2"x2"x8' Form Lumber 40.00
3 #NAME? #NAME?
4 #NAME? #NAME?
5 10pcs. - 2"x3"x8' Form Lumber 40.00
6 2" x 2" x10' Good lumber 144.00
-
Sub-Total
P-4 FILLING MATERIALS
Filling Materials #NAME?
Sub-Total
HARDWARE MATERIALS
1 Portland Cement #NAME?
2 #NAME? #NAME?
3 # 16 G.I. Tie Wire 7.00
4 #NAME? #NAME?
5 #3 CWN 1.00
6 #4 CWN 1.00
7 #NAME? #NAME?
8 #NAME? #NAME?
9 #NAME? #NAME?
10 #NAME? #NAME?
11 10mm dia. x 6.0m RSB 57.00
12 12mm dia. x 6.0m RSB 21.00
13 #NAME? #NAME?
14 #NAME? #NAME?
15 Hacksaw Blade 2.00
16 #NAME? #NAME?
17 1/4 thk. 4'x8' Ordinary Plywood 2.00
18 1/4" x 4' x 8' Marine Plywood 19.00
19 #NAME? #NAME?
20 #NAME? #NAME?
21 #NAME? #NAME?
22 #NAME? #NAME?
23 54pcs. - 2"x3"x10' Good Lumber 140.00
24 #NAME? #NAME?
25 GI PLANE SHEET Ridge Roll 8' 1.00
26 #NAME? #NAME?
27 #NAME? #NAME?
28 24pcs. - 2"x5"x10' Good Lumber 125.00
29 24pcs. - 2"x4"x10' Good Lumber 66.67
30 #4 CWN 2.00
31 #NAME? #NAME?
32 Corrugated G.I.Sheet,0.70 x 8'(Galvalum) 30.00
33 #NAME? #NAME?
P
A 34 (4" x 4") loose pin hinges 6.00
C 35 D-1, (1.0m x 2.10m) Solid Panel Door 2.00
K 36 WOODEN JALOUSIE 5.00
A 37 #NAME? #NAME?
G
E 38 DOOR LOCK 2.00
39 #NAME? #NAME?
- 40 #NAME? #NAME?
41 #NAME? #NAME?
5 42 #NAME? #NAME?
43 #NAME? #NAME?
44 Roof Nails 5.00
45 #NAME? #NAME?

46 #NAME? #NAME?
47 #NAME? #NAME?
48 #NAME? #NAME?
49 #NAME? #NAME?
50 #NAME? #NAME?
51 #NAME? #NAME?
52 #NAME? #NAME?
53 #NAME? #NAME?
54 #NAME? #NAME?
55 #NAME? #NAME?
56 #NAME? #NAME?
57 #NAME? #NAME?
58 #NAME? #NAME?
59 #NAME? #NAME?
60 #NAME? #NAME?
61 #NAME? #NAME?
62 #NAME? #NAME?
63 #NAME? #NAME?
64 #NAME? #NAME?
65 #NAME? #NAME?
66 #NAME? #NAME?
67 #NAME? #NAME?
68 #NAME? #NAME?
69 #NAME? #NAME?
70 #NAME? #NAME?
71 #NAME? #NAME?

Sub-Total
P Windows Materials
A
1 #NAME? #NAME?
C
K 2 #NAME? #NAME?
A 3 #NAME? #NAME?
G 4 #NAME? #NAME?
E
5 #NAME? #NAME?
- 6 #NAME? #NAME?
7 #NAME? #NAME?
6
Sub-Total
PAINTING & ELECTRICAL MATERIALS
1 #NAME? #NAME?
2 #NAME? #NAME?
3 #NAME? #NAME?
4 #NAME? #NAME?
5 #NAME? #NAME?
6 #NAME? #NAME?
7 #NAME? #NAME?
8 #NAME? #NAME?
9 #NAME? #NAME?
10 #NAME? #NAME?
11 #NAME? #NAME?
12 #NAME? #NAME?
13 #NAME? #NAME?
14 #NAME? #NAME?
P 15 #NAME? #NAME?
A 16 #NAME? #NAME?
C
K 17 #NAME? #NAME?
A 18 #NAME? #NAME?
G 19 #NAME? #NAME?
E 20 #NAME? #NAME?
- 21 #NAME? #NAME?
7 22 #NAME? #NAME?
23 #NAME? #NAME?
24 #NAME? #NAME?
25 #NAME? #NAME?
26 #NAME? #NAME?
27 #NAME? #NAME?
28 #NAME? #NAME?
29 #NAME? #NAME?
30 #NAME? #NAME?
31 #NAME? #NAME?
32 #NAME? #NAME?
33 #NAME? #NAME?
34 #NAME? #NAME?
35 #NAME? #NAME?
36 #NAME? #NAME?

Sub-Total

EQUIPMENTS
1 #NAME? #NAME?
8
P-

2 #NAME? #NAME?
Sub-Total
LABOR
1.0 Skilled Labor 1.00
P-9
2.0 Unskilled Labor 1.00
Sub-Total
CONSTRUCTION FORMAN
P - 10 1.0 Construction Forman #NAME?
Sub-Total

P - 11 1.0 Pre Engineering ( blue printing of plans) Lumpsum


P - 12 2.0 Material Testing and Quality Control Lumpsum
P - 13 3.0 Administrative and Overhead Expenses Lumpsum
P - 14 4.0 Hand Tools Lumpsum
P - 15 5.0 Environmental Safety Requirements/PPE Lumpsum
P - 16 6.0 Treasurer's Bond Lumpsum
P - 17 7.0 CONTINGENCY Lumpsum
Sub-Total
G-Total

Prepared by : Checked & Reviewed by:

ENGR. PETER GERO


Procurement Team Head CTF

Recommended by: Noted by:

ERNESTO JOSE C. BABIERA,CE ENGR. CHERRY VILL


Municipal Engineer Community Procuremen
L COMMUNITY DRIVEN DEVELOPMENT PROJECT
NITY PROCUREMENT PLAN (CPP)
ivelihood Training Center Date Prepared : Tuesday, November 11, 2014
cipality: IPIL Province : Zamboanga Sibugay
ant Cost: #NAME? LCC (CASH) 50,865.00
Proposed Project Implementation Schedule:
#NAME? 3rd Tranche : #NAME?

ESTIMATED COST INVOLVED and SCHEDUL SCHEDUL


PROC. SCHEDULE OF DELIVERY E OF E OF
UNIT TOTAL
METHOD TOTAL FUND PROCURE
GRANT LCC Cash RELEASE MENT

LOT 10,000.00 - 10,000.00 1


- - s
t
- -
- - T
- - r
G a
LS
- -
n
- -
c
h
e
10,000.00 - -
- - 1
#NAME? #NAME? #NAME? - s
t
Pcs 3,850.00 3,850.00 -
#NAME? #NAME? #NAME? - T
Cu.m. 620.00 620.00 - r
G

- a
LS

Cu.m. 2,160.00 2,160.00


Cu.m. 3,720.00 3,720.00 - n
c
h
#NAME? - - e
- -
- - 1
#NAME? #NAME? #NAME? - s
Bd.Ft 720.00 720.00 - t
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? - T
G
LS

r
Bd.Ft 720.00 720.00 - a
Bd. Ft. 2,880.00 2,880.00 - n
- - - - c
#NAME? - - h
1
se
- - t
#NAME? #NAME? #NAME? - T
G
LS

#NAME? - - r
a
- - n
Bags #NAME? #NAME? - c
h
#NAME? #NAME? #NAME? - e
Kgs. 546.00 546.00 -
#NAME? #NAME? #NAME? -
Kgs. 58.00 58.00 -
Kgs. 58.00 58.00 -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
Length 8,436.00 8,436.00 -
Length 4,788.00 4,788.00 -
#NAME? #NAME? #NAME? - J
#NAME? #NAME? #NAME? - a
Pcs. 140.00 140.00 - n
#NAME? #NAME? #NAME? - u
shts. 500.00 500.00 - a
Shts. 4,750.00 4,750.00 - r
#NAME? #NAME? #NAME? - y
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
3
#NAME? #NAME? #NAME? -
-
Bd.Ft 2,800.00 2,800.00 -
#NAME? #NAME? #NAME? - 2
Sht. 300.00 300.00 - 8
#NAME? #NAME? #NAME? - ,
#NAME? #NAME? #NAME? - 2
Bd.Ft 2,500.00 L 2,500.00 - 0
Bd.Ft 1,333.33 O 1,333.33 - 1
Kgs. 116.00 C 116.00 - 5
A
#NAME? #NAME? L #NAME? -
Shts. 9,240.00 9,240.00 -
#NAME? #NAME? S #NAME? -
Sets 108.00 H 108.00 -
1
Sets 1,860.00 O 1,860.00 - s
P
Sets 2,500.00 P 2,500.00 - t
#NAME? #NAME? I #NAME? -
Sets 760.00 N 760.00 - T
G r
#NAME? #NAME? #NAME? - a
#NAME? #NAME? #NAME? - n
F
#NAME? #NAME? O #NAME? - c
#NAME? #NAME? R #NAME? - h
#NAME? #NAME? #NAME? - e
kls. 350.00 G 350.00 -
O
#NAME? #NAME? O #NAME? -
D
#NAME? #NAME? S #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
F
#NAME? e
b
r
#NAME? #NAME? #NAME? - 2 u
#NAME? #NAME? #NAME? - n a
d r
#NAME? #NAME? #NAME? -
L T y
#NAME? #NAME? S #NAME? - r
#NAME? #NAME? G #NAME? - a 6
n
#NAME? #NAME? #NAME? - c
-
#NAME? #NAME? #NAME? - h 1
e 3
,
#NAME? 2
0
#NAME? #NAME? #NAME? - 1
#NAME? #NAME? #NAME? - 5
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
L
#NAME? #NAME? #NAME? -
O
#NAME? #NAME? C #NAME? -
#NAME? #NAME? A #NAME? -
#NAME? #NAME? L #NAME? -
#NAME? #NAME? #NAME? - 3 M
S r a
#NAME? #NAME? H #NAME? -
d r
#NAME? #NAME? O #NAME? - c
#NAME? #NAME? P #NAME? - T h
#NAME? #NAME? P #NAME? - r
I a 5
#NAME? #NAME? N #NAME? -
n -
#NAME? #NAME? G #NAME? - 1
c
#NAME? #NAME? #NAME? - h 3
#NAME? #NAME? F #NAME? - e ,
O 2
#NAME? #NAME? #NAME? -
R 0
#NAME? #NAME? #NAME? - 1
G 5
O
O
D
S
O 2
R 0
1
#NAME? #NAME? G #NAME? - 5
#NAME? #NAME? O #NAME? -
#NAME? #NAME? O #NAME? -
D
#NAME? #NAME? #NAME? -
S
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -
#NAME? #NAME? #NAME? -

#NAME? - -

-
#NAME? #NAME? L #NAME? -
S
#NAME? #NAME? G #NAME? -
#NAME?
- -
L.S. 12,600.00 C 12,600.00 -
L.S. 8,400.00 F 8,400.00 -
21,000.00 A - -
- -
WD #NAME? C #NAME? -
F
#NAME? A - -
- -

- -
mpsum 3,000.00 - 3,000.00
mpsum 3,000.00 - 3,000.00
mpsum 22,000.00 - 22,000.00
mpsum 4,865.00 - 4,865.00
mpsum 3,000.00 - 3,000.00
mpsum 5,000.00 - 5,000.00
mpsum 10,000.00 10,000.00 -
50,865.00 - -
#NAME? #NAME? 50,865.00

#NAME?
ed by: Approved by:

NGR. PETER GERONILLA


CTF BSPMC Chairperson

GR. CHERRY VILLANUEVA


Community Procurement Officer
COMMENTS/R
EMARKS
n
SUB-PROJECT CONCEPT FORM
Barangay MAASIN Municipality IPIL Province: Zamb. Sibugay

A. GENERAL INFORMATION
Name of proposed sub-project:
Category: Public Goods Enterprise Human Resource Dev't.

What needs of the community will the proposed sub-project address?


1
2
3

B. TECHNICAL DESCRIPTION
Physical target: 54.00 Cost parameter:
Person/s who assisted in the preparation of techical proposal: M.E./CTF/CEF/AC
Proposed scope of works to be undertaken: #NAME? CONCRETE WORKS
FORMWORKS & SCAFFOLDING MASONRY WORKS ROOFING WORKS
DOORS AND WINDOWS #NAME?
#NAME? #NAME?
Manpower requirement / sources: (skilled) Foreman, carpenter, mason/steelman and welder
Equipment requirement / sources:
Other component included in the proposal (e.g. trainings) n/a

Procurement Method/s to be adopted: Local Shopping For Goods

C. FINANCIAL ECONOMIC ASPECT


Total Estimated Cost :
Cost Sharing Arrangement: Direct Cost Indirect Cost
Grant Amount #NAME? #NAME?
LCC: BLGU - -
Community 4,914.00
MLGU 10,000.00 45,865.00
PLGU/Others -
Sub-total #NAME? #NAME?
Total LCC Cash 10,000.00 40,865.00
Total LCC In-kind 4,914.00 5,000.00

Total number of Household (HH) in the barangay:

Number of HH currently without access to the needed services that can be served by the
proposed sub-project:

Current expenses without the proposed SP


Expected expenses after completion of proposed SP:
Other benefits can be derived from the proposed sub-project:
D. SAFEGUARD CONCERNS
Any displacement or relocation of community members during implementation? Yes
Acquisition of proposed site/location? Deed of Sale Donated LGU Ownd
Proposed site within the reservation areas? Yes No
Necessary permit/s accomplished? (e.g ECC, CNC) Yes No
Mitigating measures to be undertaken for the environmental impacts of the sub-project?

E. SP SUSTAINABILITY
Is there an existing O&M group or still to be organized?
Is the community willing to pay for Tariff and by How much? N/A
Other sources of funds for the operation and maintenance activities?
Identified capability building requirements for O&M group?
How do we plan to maintain the completed sub-project?

Prepared by: Approved for endorsement to the MIBF

Head, Project Preparation Team Brgy. Chairperson

Approved for endorsement to KALAHI-CIDSS:NCDDP Technical Verification by:

HON. ELDWIN M. ALIBUTDAN ENGR. PETER GERONILLA


Municipal Mayor/MIBF Convenor Deputy Area Coordinator
Region: IX

Human Resource Dev't.

#NAME?

REINFORCING STEEL BARS


CARPENTRY WORKS
#NAME? #NAME?

Total % total
#NAME? #NAME?
-
4,914.00 #NAME?
55,865.00 #NAME?
- #NAME?
#NAME? #NAME?
50,865.00 #NAME?
9,914.00 #NAME?

Total population
Male Female
% to total
No
others

EMP Only

BSPMC Chairperson

ERNESTO JOSE C. BABIERA,CE


MIAC Representative
BSPMC Form No. 0
KALAHI-CIDSS: KKB PR
Local Counterpart Contrib
Barangay : Maasin
Municipality of Ipi
Province of Zamboanga S

Sub-Project Title : Construction of Livelihood Training Center

No. of Per Unit Total Sub-Project Proposed Amount


Budget Item Unit Used
Units Cost Cost of Grant

A. DIRECT COSTS
Materials 69,937.33 69,937.33
Equipment Rental - -
Labor Costs:
a. Skilled 12,650.00 10,550.00
b. Unskilled 8,400.00 5,586.00
Construction Forman - -
Signage #NAME?
Sub-Total A #NAME? 86,073.33
B. INDIRECT COSTS
Pre Engineering ( blue printing of plans) 3,000.00
Engineer's Supervision 2,000.00
Material Testing and Quality Control 3,000.00
Permits & Licences 3,000.00
Administrative and Overhead Expenses 22,000.00
#NAME? #NAME?
Environmental Safety Requirements/PPE 3,000.00
Treasurer's Bond 5,000.00
CONTINGENCY 10,000.00 10,000.00

Sub-Total B #NAME? 10,000.00


GRAND TOTAL (A + B) #NAME? 96,073.33

Prepared By: Approved By:

__________________________ ______________________________
Barangay Treasurer BSPMC- Chairman
BSPMC Form No. 03
KALAHI-CIDSS: KKB PROJECT
ocal Counterpart Contribution Plan
Barangay : Maasin
Municipality of Ipil
Province of Zamboanga Sibugay

MLGU BLGU Community Total LCC


Cash Inkind Cash Inkind Inkind Cash Inkind

- -
- -
- -
2,100.00 - 2,100.00
2,814.00 - 2,814.00
- -
10,000.00 10,000.00 -
10,000.00 - - - 4,914.00 10,000.00 4,914.00

3,000.00 3,000.00 -
2,000.00 - 2,000.00
3,000.00 3,000.00 -
3,000.00 - 3,000.00
22,000.00 22,000.00
4,865.00 4,865.00
3,000.00 3,000.00
5,000.00 5,000.00 -
- -

40,865.00 5,000.00 - - - 40,865.00 5,000.00


50,865.00 5,000.00 - - 4,914.00 50,865.00 9,914.00

________________
Target Date of
Delivery

January 2015
January 2015

February 2015
February 2015
February 2015
January 2015

January 2015
February 2015
February 2015
February 2015
January 2015
January 2015
January 2015
January 2015
March 2015
DSWD-KALAHI-CIDSS: NCDDP
LCC FOR SUB-PROJECT IMPLEMENTATION MONITORING REPORT

Barangay: Maasin Total LCC Commited #NAME? Total Delivered #NAME?


Municipality: IPIL Cash #NAME? Cash #NAME?
Sub-Project: Construction of Livelihood Training Center In-Kind 9,914.00 In-Kind -
Schedule of Local Counterpart Contribution Delivered
1st tranche 2nd tranche 3rd tranche total
Package Items
Cash In-Kind Cash In-Kind Cash In-Kind Cash In-kind
Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
A. Direct Cost
Materials - - - -
Equipment - - - - -
Labor - - - - -
Skilled Labor 1,680.00 210.00 210.00 - - 2,100.00 -
Unskilled Labor 2,251.20 281.40 281.40 - - 2,814.00 -
Signage #NAME? #NAME? #NAME? #NAME? - -
CONSTRUCTION FORMAN - - - - -
Sub-Total #NAME? #NAME? 3,931.20 - - - 491.40 - - - 491.40 #NAME? #NAME? 4,914.00 -
B. Indirect Cost
Pre Engineering 3,000.00 3,000.00 3,000.00 3,000.00 - -
Material Testing 3,000.00 3,000.00 3,000.00 3,000.00 - -
Engineering Supervision - 1,600.00 200.00 200.00 - - 2,000.00 -
Permits & Licences - 2,400.00 300.00 300.00 - - 3,000.00 -
Administrative and Overhead E 22,000.00 23,000.00 22,000.00 23,000.00 - -
#NAME? 4,865.00 4,865.00 4,865.00 4,865.00 - -
Environmental Safety Requirem 5,000.00 5,000.00 5,000.00 5,000.00 - -
Treasurer's Bond 3,000.00 3,000.00 3,000.00 3,000.00
CONTINGENCY - - -
Sub-Total 40,865.00 41,865.00 4,000.00 - - - 500.00 - - - 500.00 - 40,865.00 41,865.00 5,000.00 -
TOTAL #NAME? #NAME? 7,931.20 - - - 991.40 - - - 991.40 - #NAME? #NAME? 9,914.00 -

Prepared By: Reviewed by: Certified Correct: Noted By:

GWENDOLYN C. LANG RONALD G. JAVA GARRY V. SANTOS, CPA ZENAIDA L. AREVALO, CESO IV
MFA Area Coordinator Regional Financial Analyst Regional Director
EQUIPMENT RENTAL RATES & CAPABILITIES, ACEL RATES January 2003 Ed.

Table 1: RENTAL RATES & CAPABILITIES WORKING HOURS PER DAY=8 HRS.

Computed Rental
Operated Rate per Rates
Description CA
Hour
rate per day
Asphaltic concrete Plant PhP77,184.00 Asphalt Batching
(Php 4824/mo. X Rated Cap. In Cu.M./Hr. = (4826/30 X 8 hrs X
60.0 Tons) = PhP
77,184.00
Portable Concrete Batching Plant PhP16,576.00 30 Min/Batch
(Php 6216/mo. X Rated Cap. In Cu.m. ={(6,216/30) X [(8 X
60) / 30] X 5.0
Cu.M. } = Php 16,576
per Day

Rock Crusher Portable Parker Php !,556.55 PhP12,452.40 Crushing


Aggregates
Bulldozer Komatsu D65A-8 PhP2,090.00 PhP16,720.00 Quarrying

Bulldozer with Ripper + 35% PhP2,808.00 PhP22,464.00 Quarrying

Backhoe Crawler MS180 PhP1,748.00 PhP13,984.00 Excavation

Backhoe Crawler with Breaker + 35% PhP2,359.80 PhP18,878.00 Excavation

Backhoe Crawler PC200-3 PhP1,814.00 PhP14,512.00 Excavation

Loader Crawler Komatsu D-60S-7/DD PhP1,418.00 PhP11,344.00 Loading

Loader Whell TCM/ Clark 75B PhP1,255.00 PhP10,040 Loading


Road Grader MG500 PhP1,101.00 PhP8,808.00 Spreading
Roller Bomag BW210DH PhP1,398.00 PhP11,184.00 Compacting
Crane Crawler Type PhP2,041.00 PhP16,328.00 Lifting / Pile
Driving
Crane Truck Mounted PhP2,095.00 PhP16,760.00 Lifting / Pile
Driving
Crane Hydraulic PhP2,452.00 PhP19,616.00 Lifting / Pile
Hammer Diesel MH25 PhP1,018.00 PhP8,144.00 Driving
Pile Driving
Hammer diesel MH35 PhP1,284 PhP10,272 Pile Driving
Hammer Vibratory PhP565.00 PhP4,520 Pile Driving
Transit Mixer 8-10 CU DYS PhP1,486.00 PhP11,888.00 Concrete
Transport
Concrete Mixer (1Bagger) PhP156.00 PhP1,248.00 Concrete Mixing
Concrete Paver Roller Screed PhP3,152.00 PhP25,216.00 Concrete Paving
Concrete Vibrator Gasoline PhP78.13 PhP625.04 Concrete Vibration
Concrete Saw Gasoline Self Propelled PhP332.03 PhP2,656.24 Concrete Cuttung
Plate Compactor (Vibratory) PhP150.67 PhP1,205.36 Compacting
Air Compressor 161-185 CFM PhP422.00 PhP3,376.00 Power Generation
Jack Hammer/ P. Breaker PhP322.00 PhP2,576.00 Breaking
Bar Shear/ Cutter PhP368.30 PhP2,946.40 Bar Cutting
Bar Bender PhP418.53 PhP3,348.24 Bar Bending
Water Pump Diesel PhP119.90 PhP959.20 Water Pumping
Wekding Machine Electric Driven/ DC output PhP355.00 PhP2,840.00 Weilding / Cutting

Oxy-Acetylene/Cutting outfit PhP64.00 PhP512.00 Cutting

Chainsaw w/out blade PhP561.25 PhP4,490.00 Cutting

Generator Set PhP126.42 PhP1,011.36 Power Generation

Dumpt truck (12-15 cu.Yds) PhP1,127.00 PhP9,016.00 Hauling /


Transporting

Water Truck ( 5000-6000 Gals) PhP1,794.00 PhP14,352.00 Water Supply

Trailer 60 Ton PhP4.25/HR./Km PhP9,562.50 PhP76,500.00 Transporting


( PhP 4.25 X Wt. (Min.=15T) X No. of KM. +
50% Surcharge, Return trip Example (100KM)
= (4.25 X 15 X 100) X 1.5 = PhP 16,576 per
Day

Cargo Truck ( 9-10 Tons) PhP918.00 PhP7,344.00 Hauling / Transporting

EQUIPMENT CAPABILITIES
Type of Equipment Average Capabilities
1. Bulldozer (108) (a) Clearing 500 sq.m./hr.
(b) Stripping 200 sq.m./hr.
© Excavation:
1. Common soil 45 cu.m./hr
2. Slightly Hard Materials 25 cu.m./hr.
(d) Quarrying:
107 Common Materials 50 cu.m./hr.
108 Aggregate 40 cu.m./hr.
Boulders 15 cu.m./hr.
200 Needs Screening
(e) Pushing 3 cu.m./hr.
(a) Subgrading 300 sq.m./hr.
2. Road Grader
(b) Spreading 50 cu.m./hr.
3. Payloader (a) Loading 30 cu.m./hr.
4. Crane Shovel (a) Loading 35 cu.m./hr.
(a) Satic rolling ( 12 passes- 15 cm. lift 15 cu.m./hr.
5. Sheep Foot Roller
(b) Vibratory Rolling ( 4 passes- 15 cm. lift) 135 cu.m./hr.
6. 3- Wheel Road Roller (a) Static Rolling ( 6 passes- 20 cm. lift) 24 cu.m./hr.
7. Tractor Drawn Roller (a) Vibratory Rolling (6 passes- 20 cm. lift) 24 cu.m./hr.
(a) Static Rolling ( 6 passes- 20 cm. lift) 24 cu.m./hr.
8. Tandem Roller
(b) Vibratory Rolling (6 passes- 60 cm. lift) 72 cu.m./hr.
(a) Hauling Common Borrow Base Course 3.5 cum./hr.
9. 9 1/2 T Dump Truck (b) Hauling Selected Borrow Base course 5.0 cu.m./hr.
© Hauling Concrete Batch Class 'A' 2 Batch/trip
(a) Hauling Common Borrow Base Course 2.5 cu.m./trip
10. 2 1/2 T Dump Truck (b) Hauling Selected Borrow Base course 4.0 cu.m./trip
© Hauling Concrete Batch Class 'A' 1 Batch/trip
11. Buggy (a) Hauling Concrete Mix 0.17 cu.m./trip
(a) Hauling Aggregates 0.17 cu.m./trip
12. Wheel Borrow
(b) Hauling Concrete Mix 0.05 cu.m./trip
13. Water Tuck (a) Watering 1,000 sq.m./trip
14. Conrete Mixer (a) Mixing Concrete 9 cu.m./hr.
15. Rock Crusher (a) Crushing Mixed Sand & Gravel 30 cu.m./hr.
16. Conrete Virator (a) Vibrating Concrete Mix 40 cu.m./hr.
17. Concrete Floor Finisher (a) Finishing Concrete Floor 140 cu.m./hr.
(a) Drilling Hard Rock 0.23 m./hr.
(b) Drilling Loose Rock 0.30 m./hr.
18. Percussioned Drilling © Drilling Limestone 0.38 m./hr.
(d) Drilling Sticky Clay 0.49 m./hr.
(e) Drilling Loose Clay 0.70 m./hr.

TASK RATES FOR LABOR - BASED PROJECTS


I. For Item 100 - Clearing & Grubbing
Activity Productivity
1) Bush Clearing Sq.m./man-day
Bush Type
a) light bush 200
b) medium bush 100
c) dense bush 50
2) Tree and Stump Removal One (1) man-day per cm. of trunk diameter
@ base of tree
3) Grubbing Sq.m./man-day
Vegetation Type
a) Dense vegetation in firm soil covering the
whole area 80
b) Spatse vegetation in loose soil 250

II. For Item 105 - Excavation for Roadway & Drainage


Activity Productivity
1) Excavation Cu.m./man-day ( Throwing distance in m.
Soil Type 0-4 m. 4-6 m.
a) Loose, rot sticky soil 5.0-6.0 4.5-5.5
b) Firm soil 3.5-4.5 3.4-4.0
c) Very hard soil, hard soil mixed with Stones 2.0-3.0 1.8-2.5
2) Loading Cu.m./man-day
Type of Soil
a) Loose 4.50-5.50
b) Firm 2.50-4.00
c) Hard 1.50-2.50

Excavation combined with loading of soil can be effectively carried out by laborers up to a
loading height of about 1.00 m. e.g. into wheel borrow or head baskets. Above that height, it is
preferable to have a separate group of loaders whose output must be matched with that of the
excavators.

Necessary output for the Loading Activity


Soil Type Loading Height Productivity cu.m./man-day
a) Loose 0-1 m. 12-15
b) Loose 1-2 m. 7-10
c) Loose Over 2 m. 4-5

III. For Item 106- Excavation for Structures


Activity Productivitty
1) Excavation Depending on the type of soil, they use similar data as those
used for Excavation in Item 105

IV. For Item 110- Foundation Fill


Activity Productivity
1) Backfilling & Tamping 3 cu.m./man-day

V. For Item 108- Aggregate Sub-base Course


Activitty Productivity
1) Quarrying ( Excavation & Gravel) 0.50-2.00 cu.m./man-day
2) Loading 7.00-10.00 cu.m./man-day
3) Spreading 8.00-12.00 cu.m./man-day
4) Compacting 8.00-12.00 cu.m./man-day
5) Hauling activity should be considered in this Item, hence, hauling distance has an important
beating on the cost of the gravelling operation, the maximum acceptable hauling distance has to be
considered from case to case.

VI. For Item 200- Aggregate Base Course


Activity Productivity
1) Quarrying 0.50-2.00 cu.m./man-day
2) Loading 7.00-10.00 cu.m./man-day
3) Spreading 8.00-12.00 cu.m./man-day
4) Compacting 8.00-12.00 cu.m./man-day
5) Hauling- please refer activity no.5 of item 108
6) Scrapping 3.00-5.00

VII. For Item 413 - Reinforced Concrete Pipe Culvert


Activity Productivity
1) Crushing of stone for aggregate 0.20 cu.m./man-day
2) Casting of culvert rings 2 man- day/ring
3) Laying of standard culvert (24 in. dia.) of 0.60 m.,
dia., length 6.00 m. including excavation, culvert bad
and backfill
4) Building of headwalls with masonry blocks 10 man-day/2 headwalls

If the length of a culvert exceeds 6 meters, the number of man-days has to be increased accordingly.

Culvert laying - this task consist of the excavation of the trench preparing the bed, laying of culvert,
backfilling and compaction. Number of man-days required varies with the volume of the excavation and the soil type.
FACTORS TO BE MULTIPLIED TO DETERMINE THE REQUIRED QUANTITY OF EACH MATERIAL CONCRETE

CLASS 'A' CONCRETE ( 3,000 psi)


CEMENT - 9.08 bags/cu.m. of concrete + 3-5% wastage
SAND - 0.58 cu.m./cu.m. of concrete + 8-10% wastage
GRAVEL - 0.77 cu.m./cu.m. of cocrete + 8-10% wastage

CLASS 'B' CONCRETE ( 2,500 psi)


CEMENT - 8.38 bags/cu.m. of concrete + 3-5% wastage
SAND - 0.45 cu.m./cu.m. of concrete + 8-10 wastage
GRAVEL - 0.82 cu.m./cu.m. of concrete + 8-10 wastage

CLASS 'C' CONCRETE ( 3,500 psi)


CEMENT - 9.77 bags/ cu.m. of concrete + 3-5% wastage
SAND - 0.53 cu.m./cu.m. of concrete + 8-10% wastage
GRAVEL - 0.70 cu.m./cu.m. of concrete + 8-10% wastage

CLASS 'D' CONCRETE ( 4,000 psi)


CEMENT - 11.17 bags/ cu.m. of concrete + 3-5% wastage
SAND - 0.44 cu.m./cu.m. of concrete + 8-10% wastage
GRAVEL - 0.68 cu.m/cu.m. of concrete + 8-10% wastage

FOR BRIDGE ESTIMATE


NUMBER for Falsework - 60 bd.ft./cu.m. of concrete
NAILS - 2 kilos/cu.m. of concrete
THE WIRES - 1.1 kilos/cu.m. of concrete
Painting Structural Steel - 3 gals./ton

AVERAGE FUEL CONSUMPTION PER DAY

FUEL ENGINE OIL GEAR OIL GREASE


Crane, 140 liters ( diesel ) 4 liters 1 liter 2 lbs.
Diesel Hammer, 20 liters ( diesel ) - - -
Bulldozer, 200 liters ( diesel ) 3 liters 1 liter 1 lb.
Payloader, 100 liters ( diesel ) 3 liters 1 liter 1 lb.
Grader, 120 liters ( diesel ) 3 liters 1 liter 1 lb.
Roller, 60 liters ( diesel ) 2 liters 1 liter/wk. 2 lbs./wk.
Dump Truck, 60 liters ( diesel ) 1 liter 2 liters/wk. 1 lb.
Mixer ( 1-bag ), 40 liters gasoline - - 0.5 lb.
Vibrator 15 liters (gasoline ) - - -
Water Pump 15 liters ( gasoline ) - - -
One Bagger Mixer - 100 bags/day
Crane - minimum of 2 piles/day ( 16 m. length including spotting )

VOLUME OF TRENCH CU.M.

Soil Type 7 7-10 10-13

In these cases, the work is split over two or more days. First, the trench should be excavated and
then the preparation of the bed, the laying, backfilling and compaction is done. Only 3 times. Therefore the volume
of the excavation has to be limited following rates and then applicable:

Soil Type Productivity


a) hard soil 3.50 cu.m./man-day
b) very hard, stony 2.00 cu.m./man-day

After completion of the trench approximately 4 man-days are needed to lay 6 rings, backfill and compact to finish road le

I. MECHANIZED ASPECT

A. CLEARING & GRUBBING


Dozer Production
Horse Dense of Vegetation ( No. of Trees/Hectares )
Power 0-50 51-100 101-200
120 360 250 190
140 420 290 220
160 480 330 255
180 540 375 285
200 600 420 310

B. EXCAVATION ( Common Materials )


B.1 CRANE
Tonnage's Capacity ( cu.m. /hr. ) Bank Volume
Canal Structure Creek
15 15 10 10
20 20 15 15
25 25 20 20
30 30 25 25

B.2 DOZER
Horse Production ( cu.m./hr. ) Bank Volume
Power Canal Structure
120 30 15
140 35 20
160 40 25
180 45 30
200 50 35

B.3 BACKHOE
Bucket ( cu.m.) Production ( cu.m./hr.) Bank Volume
Canal Structure Creek
0.5 20 15 15
0.75 30 20 20
1 40 30 30
1.25 50 40 40
1.5 60 45 45

C. QUARRYING
Dozer ( H.P.) Production ( cu.m./hr.) Bank Volume
Common Aggregate Cobbles/Boulders
140 55 60 27
160 60 65 29
180 65 70 31
200 70 75 33

D. LOADING
Bucket (cu.m.) Production ( cu.m./hr.) Bank Volume
Common Aggregate Cobbles/Boulders
1 50 55 35
1.5 75 80 55
2 100 110 75
2.5 125 135 90
3 150 165 110

E. SPREADING
Grader ( H.P.) Road ( cu.m./hr. ) cmp.
Common Aggregate
80-100 60 70
100-125 70 80
125-150 90 100
150-175 100 110

F. SIDE BORROW ( Common Materials)


Dozer ( H.P.) Production ( cu.m./hr.) Compacted Volume
140 35
160 40
180 45
200 50

G. STR BACKFILL WITH SPREADING & COMPACTION


Dozer ( H.P.) Production cu.m./hr. Compacted Volume
140 50
160 70
180 80
200 90

H. EMBANKMENT COMPACTION
Capacity ( cu.m./hr.) Compacted Volume
Tons Self- Propelled
Tam. Foot drum Vib. Drum
10 80 60
12 90 70
15 120 90

I. LOADING, SPOT & MANEUVER TIME


Using Loader with 1,00 cu.m. Bucket
Dump Truck Capacity Compacted Volume of Cobbles/ Boulders
Common Materials Road Surface Materials
4.00 cu.m. 7 min. 7 min. 10 min.
6.00 cu.m. 9 min. 9 min. 12 min.
8.00 cu.m. 11 min. 11 min. 15 min.
J. AVERAGE SPEED OF DUMP TRUCK
Type of Road Kilometer per hour
With load Without load
Concrete/Asphalt Road 35 45
Good Maintained Gravel Road 30 35
Poorly Maintained Gravel Road 20 25

K. DEMOLITION OF CONCRETE
160 CFN Compressor & two (2) Jack Hammer
Capacity - 8.00 cu.m./day for massive concrete
- 12.00 cu.m./day for slab & wall

L. DRIVING OF PILES
Steel Pipes : Crane 25 tons with 2-tons drop hammer, Capacity= 8 L.M./Hr.
Concrete Piles : Crane 25 tons with 2500 kgs.m. Pile hammer, Capacity= 2.00 L.M. per Hr.,
4.00 L.M./Hr. for thick & thin concrete piles.

M. MANUAL ASPECT

A. EXCAVATION
A.1. Common Materials
Capacity (cu.m./day) Bank Volume & Depth of Excavation
Type of Work ( meter )
Farmditchs 3.00 2.50 2.00
Canal 2.50 2.00 1.75
Structure 2.00 1.75 1.50

A.2. Slight hard materials (lnd.)


Type of Work Capacity ( cu.m./day/man) Bank Volume
Canal 1
Structure 0.75

B. LOADING CAPABILITIES OF FIVE ( 5) LABORERS


Sand and Gravel Common Cobbles Boulders
cu.m./hr. cu.m./hr. cu.m./hr. cu.m./hr.
4 5 3.5 3

C. UNLOADING CAPABILITIES OF FIVE ( 5 ) LABORERS


Sand and Gravel Common Cobbles Boulders
cu.m./hr. cu.m./hr. cu.m./hr. cu.m./hr.
6 6 5 4

D. CUT, BEND & PLACE RSB


Structure 1 Steelman & 1 Helper with Bar Cutter
Canal & Others 80 kgs/day

E. QUARRYING
Capability cu.m./day/man
Sand & Gravel Cobbles Boulder
3.5 2.5 2
F. DEMOLITION OF CONCRETE
Slab & Wall 0.50 cu.m./man-day
Massive Concrete 0.20 cu.m./man-day

G. SCREENING OF AGGREGATES
Gravel 4.00 cu.m./day/man
Sand 6.00 cu.m./day/man

H. MANUAL BACKFILL
Capacity : 3.00 cu.m./day/man

I. LAYING OF MATERIALS ( cu.m./day/man)


Cobbles - 2.00
Boulders - 1.50

J. SPREADING OF AGGREGATE
Capacity : 2.50 cu.m./day/man

K. RUBBLE MASONRY ( Concreting )


Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 6.00 cu.m./day

L. GROUTED RIPRAP
Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 7.50 cu.m./day

M. C.H.B. : Setting Capacity sq.m./day


Crew : 1- Mason, 2- Laborers
Fence Building
4" CHB 14 10
6"CHB 10 8

N. CONCRETE LINING
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, 10- Laborers with one (1) bagger mixer
Capacity : 4.50 cu.m./day

O. INSTALLATION OF STEEL GATES


Crew : 1- Mason & 5 - Laborers
16 x 16 to 24 x 24 2 assy/day
Above 24 x 24 1 assy/day
P. CONCRETE WORKS
P.1. Fabrication, Placing & Dismantling of Forms
Crew : 2- Carpenters & 4- Laborers; Capacity : 3.50 cu.m./day for 3000 psi
Crew : 1- Carpenter & 1- Laborer; Capacity : 4.50 cu.m./day Canal Lining

P.2. Concreting and Curing Capability


P.2.a. With concrete mixer
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, & 8- Laborers
Class "A" : 3.50 cu.m./day
Class "B" : 4.50 cu.m./day
Class "C" : 4.80 cu.m./day
Lean Concrete : 6.00 cu.m./day

P.2.b. Without concrete mixer


Crew : 1- Foreman, 2- Mason, & 10- Laborers
Class "A" : 2.50 cu.m./day
Class "B" : 3.70 cu.m./day
Class "C" : 4.80 cu.m./day
Lean Concrete : 4.50 cu.m./day

Q. PLASTERING OF CHB WALL


Crew : 2- Mason, & 2- Laborers
Capability : 12 sq.m./day (one side only)

R. REINFORCED CONCRETE PIPES


Crew Capability
Diameter
inch Cm. Fabrication
1- Foreman 12 30 15
1- Mason 18 46 11
1- Carpenter/ Steelman 24 61 9
12- Laborers with 30 76 6
1- Bagger Mixer 36 91 5
48 122 3
42 4

NOTE : TIME OF MIXER/DAY = BAGS OF CEMENT/DAY X 10 MIN./ BAG


60 MINUTES/HOUR

III. MATERIAL ASPECT


Class Strength Max. Aggre. Cement Sand
Size, in. bag/cu.m. cu.m./cu.m.
A. Concrete
a. 211 kgs. e 1.50 9.00 0.45
b.200 kgs e 2.00 7.00 0.50
Canal Lining
200 kgs e 1.00 7.5 0.48
B. Rubble Mason w/ 211 kgs e
211 kgs e - 4.50 0.225
C. Grouted Riprap - 4.20 0.35
Plain Riprap - - -
D. Lean Concrete - 5.00 0.50
1000 psi
E. Gravel Blanket - - -
F.Filter Drain - - -

OTHER MATERIALS
Class Type of Strength F. Lumber
Structure kgs e bd.ft./cu.m.
A Bridge/ Flume 211 40
A Siphon/Box Cul 211 25
A Other Str. @ me 211 25
A 211 5
B 200 5
A 211 15
B 200 5
A 211 5

REINFORCED CONCRETE PIPES


Diameter Fabrication Materials per p
Cement Sand Gravel
Inches Bag Cu.m. Cu.m.
12 0.58 0.22 0.05
48 1.22 0.05 0.10
24 1.82 0.08 0.15
30 2.56 0.11 0.21
36 3.33 0.14 0.28
42 4.26 0.18 0.36

INSTALLATION OF R.C. PIPES


Diameter Cement Sand Gravel
Inches Bags Cu.m. Cu.m.
12 0.21 0.01 0.02
18 0.45 0.02 0.04
24 0.72 0.03 0.06
30 0.93 0.04 0.08
36 1.11 0.05 0.1
42 1.32 0.06 0.12

PLASTERING C.H.B. BLOCK


Size Materials per sq.m. for two ( 2 ) sides
Sand Cement
4" & 6" 0.034 0.41

G. I. LAYING OF C.H.B.
Size Cement Sand
Bag/sq.m. Cu.m./sq.m.
4" 0.55 0.046
6" 1.07 0.089

RECOMMENDED INDIRECT COST


Estimated Direct Cost ( E.D.C.) Indirect Cost for OCM & Profit Max. Ranges Mobilization
O.C.M. % of E.D.C. C.P. % of E.D.C.
Up to 1 Million 13% 15% 2%
Above 1M to 5M 12% 14% 2%
Above 5M to 10M 12% 14% 2%
Above 10M to 20M 11% 12% 2%
Above 20M to 50M 11% 12% 2%

Note: The total contract price should be equal to or less than the total COA estimate plus 10% in order to sustain a finding of re
the contract price will be deemed excessive.

ACEL RATE 1998


Operated Equipment Description Rate/Day
Bulldozer Komatsu, D80A - 12DDP 9,160.00
Payloader 75 TCM /Clark, 1.53 cuP 10,010.00
Road Grader Mitsubishi MG 500 17 P 8,808.00
Dump Truck Japan & Other Make, 1P 9,016.00
Road Roller Ingersoll Rand SP48 MP 8,701.00
Crane All models,Truck mounP 11,296.00
Back Hoe Komatsu PC 120, Capa P 9,656.00
Transit Mixer Japan make 3.8 cu.m.,P 8,528.00
Air Compressor Gas/Diesel Engine, C P 1,376.00
Plate Compactor 12 Hp Engine Driven P 1,648.00
Asphalt Paver/Finisher Worthington 34 ( basicP 3,320.00
Asphalt Distributor Little Ford SprasmasteP 5,784.00

Bare Equipment Description Rate/Day


Pile Hammer (w/o crane) Domag D8 - 22 P 5,067.00
Drop Hammer (w/o crane) Two tons w/ Pile Ham P 100.00
Jack Hammer Stanley, Hydraulic w/oP 294.00
Welding Machine Gas/Diesel Driven 250P 300.00
Concrete Mixer 1- Bagger P 298.00
Concrete Vibrator Gas or Diesel Driven P 341.00
Chainsaw Nusquama, 2100 CD wP 180
Water Truck All Makes, 500-1000 GP 1,773
Water Pump All Models 3.5"-4" sizeP 199.00
Concrete Batch Plant With Cement Silo Manu P 5,113.00/
month x rated
Cap. Ln.cu.m/hr
LABOR OUTPUT CAPABILITIES

REMOVAL EXISTING STRUCTURES:


Lumpsum
Installation:
Timber:

Girts and Girder 0.10 - 0.15 cu.m./man-days


Floor Joist 150 L.M./man-days
Flooring Boards 15 - 18 sq.m./man-days
Post 0.14 cu.m./man-days
Walling/Siding:
Covering 30 sq.m./man-days
Framing, Studs 12 cu.m./man-days
( Multiply by the no. of days
Double walling )
Ceiling Joist and Hangers 16 sq.m./man-days
Ceiling Boards ( 4' x 8' Plywood ) 30 sq.m./man-days
Windows sashes:
Jambs Fabrication 4 sq.m./man-days
Frames Fabrication 2 sq.m./man-days
Jambs Installation 14 sq.m./man-days
Frames Installation 10 sq.m./man-days
Doors:
Jambs Fabrication/ Installation 2.5 sq.m./man-days
Door Fabrication/Installation 1panel/man-days

Paintings:
Paint Rollers 125 sq.m./man-days
Paint Brush 50 sq.m./man-days
Neutralizer 100 sq.m./man-days
Truss Fabrication 0.25 truss/man-days
Purlins Installation 60 L.M./man-days
Fascia Boards 0.05 cu.m./man-days
Roof Coverings ( G.I. sheets ) 35 pcs./man-days
Concrete Works:
Concrete Pouring 0.30 cu.m./man-days
Rebars 20 - 30 kgs.man-days
Finishing:
Rough Finish 10 sq.m./man-days
Plain/Fine Finish 8 sq.m./man-days
CHB Filling/Laying 6 - 8 sq.m./man-days

A. CEMENT MORTAR

Table- 1. Quantity of Cement and Sand for CHB Mortar per Square Meter Wall
Size of CHB No. per sq.m. 40 Kg. Mixture Cement Bag
B C
4 x 8 x 16 12.5 0.525 0.394
6 x 8 x 16 12.5 1.013 0.759
8 x 8 x 16 12.5 1.500 1.125

1. Find the area of the wall


Area = 3.00 x 4.00
A = 12 sq.m.
2. Refer to Table -1 along 4 x 8 x 16 CHB cement class "B" mixture; Multiply:
Cement : 12 x 0.525 = 6.3 say 7 bags
Sand : 12 x 0.0438

B. MORTAR FOR PLASTERING

Table- 2 Quantity of Cement and Sand for Plastering per Square Meter
40 kg. Cement Bags
Mixture Class 16 mm. thk. 20 mm. thk. 25 mm. thk.
A 0.288 0.360 0.450
B 0.192 0.240 0.300
C 0.144 0.180 0.225
D 0.120 0.150 0.188
Sand 0.016 0.020 0.025

1. Find the area of the wall ( two faces )


Area = 3.00 x 4.00 x 2 faces
A = 24 sq.m.
2. Refer to Table - 2 under 16 mm. thick plaster class "B" mixture; Multiply;
Cement = 24 x 0.192 = 4.6 bags
Sand = 24 x 0.016 = 0.384 cu.m.

C. CHB FOOTING

Table- 3. Quantity of Cement, Sand, and Gravel for CHB Footing per Meter Length
Dimension Cement in Bags Class Mixture
Centimeters 40 Kg. Cement
t w A B
10 30 0.27 0.225
10 35 0.315 0.263
10 40 0.36 0.3
10 50 0.45 0.38
15 40 0.54 0.45
15 45 0.608 0.506
15 50 0.675 0.563
15 60 0.81 0.675
20 40 0.72 0.6
20 50 0.9 0.75
20 60 1.08 0.9

1. Solve for the net length of the CHB wall


Net length = 40 m - ( 0.25 x 11 post )
= 37.25 meters
2. Refer to Table - 3 along the 15 x 50 cm footing dimension 40 Kg. Cement class "A"
Mixture; Multiply :
Cement : 37.25 x 0.675 = 25.14 say 26 bags
Sand : 37.25 x 0.038 = 1.4 say 1.5 cu.m.
Gravel : 37.25 x 0.075 = 2.8 say 3.0 cu.m.

TECHNICAL SERVICES DIVISION PERSONNEL

Celso U. Reyes Florenda T. Lonio Santiago O. Burdeos

Junrey E. Labatos Ronnie Valentino U. Tello Joehl Francisco E. Duarte

Dante M. Jabutay Alfredo Genaro C. Quintos Charito A. Samson

William C. Peguit Joseph P. Cagampang Alan G. Milan

MAINTENANCE BY CONTRACT
( MBC )
METHODS OF CONSTRUCTION

1. PATCHING POTHOLES - Should be done to the areas specified by the contracts and plans duly approved
by the Engineers. Materials to be used must be suitable to acquire best result when compacted.
SCHEDULE OF WORKS : MONTHLY

2. RESHAPING should also be done to areas required in the plan and contracts. All works should conform
to what will be described in the specification.
SCHEDULE OF WORKS : QUARTERLY

3. VEGETATION CONTROL AND CLEANING DITCHES - All objects subject for the obstruction of the designed
areas should be removed and cleared.
SCHEDULE OF WORKS : TWICE A YEAR

4. REGRAVELLING - All materials shall consist of hard, durable particles or fine divided mineral matter that can be compacted
reaching for stable sub-base. Using especially equipped vehicles material should be distributed in a continous uniform
layer. The uniform thickness of sub-base material shall be adjusted prior to the compaction by watering or by drying as
required in order to obtain the required compaction. Compaction shall continue until a field density of at least 100 per cent
of the maximum dry density.
SCHEDULE OF WORKS : ANNUAL

5. BLADING/GRADING - All unstable materials should be removed in areas subject for Blading/Grading. These areas should
be brought to a grade required in the plans and contracts. Compaction will follow using heavier compacting units until required
density can be obtained.
SCHEDULE OF WORKS : ANNUAL
TES January 2003 Ed.

CAPABILITIES

60 Tons TONS Per Day

5.00 Cu.M. Cu.M. Per Batch

100 TONS Per Hour

50 Cu.M. Per Hour

50 Cu.M. Per Hour

0.8 Cu.M. Capacity

0.8 Cu.M. Capacity

0.8 Cu.M. Capacity

1.8 Cu.M. Capacity

1.53 Cu.M. Capacity


50 Cu.M. Per Hour
11 TONS Capacity
46-50 TONS Capacity

46-50 TONS Capacity


46-50 TONS Capacity
7500 Kg.-M. Rated
Energy
10500 Kg.-M. Rated
Energy
9.17
6.12-7.65 Cu.M. Capacity

10-Jun Cu.M. Per Hour

50 mm
Max 6 3/4 Depth Capacity

161-185 CPM Capacity


Max 32mm G40 Capacity
Max 32mm G40 Capacity
900 LPM Capacity
500 APMS Capacity

64-125 KVA 51-100 HP

9.17-11.46 Cu.M. Capacity

5000-6000 Gals. Capacity

15 TONS Capacity

9-10 TONS Capacity

400

1080
192
576

oductivity
Throwing distance in m. )
6-8 m.
3.5-4.5
2.5-3.5
1.7-2.5
the soil type.
CONCRETE

OIL # 10
-
1 liter
1 liter
1 liter
1 liter
1 liter
1 liter
-
-
-
compact to finish road level.

ction
o. of Trees/Hectares )
201-250 251& >
160 130
185 150
210 170
240 195
265 215
Cement R.S. Bars Lumber Ply
bags/hr. kgs./hr. bd,ft./hr. pcs./hr.
300 6,000 4,000 250

Cement R.S. Bars Lumber Ply


bags/hr. kgs./hr. bd.ft/hr. pcs./hr.
300 7,000 4,000 250
Capability

Installation
16
14
12
10
8
6
7

Gravel Boulder
cu.m./cu.m. cu.m./cu.m.

0.90 -
1.00 -
0.96 -

0.45 0.75
0.05 1.00
0.10 1.00
1.00 -

1.00 -
- -

1/2 pl.wd Tie wr. Nail


pcs/cu.m. kgs./cu.m. kgs./cu.m.
1.00 1.25% RSB 2.50
1.25 1.20% RSB 2.00
1.25 1.10% RSB 2.00
0.10 - 0.50
- - 0.25
0.40 1.00% RSB 1.50
0.40 1.00% RSB 0.50
- - 0.25

brication Materials per pc.


G.I. Sheet F. Lumber Tie Wire C.W. Nails
Pc. Bd.ft. kgs. kgs.
0.12 0.34 9.28 0.10
0.19 0.36 7.72 0.20
0.24 0.48 9.75 0.30
0.30 0.60 23.22 0.40
0.34 0.72 50.43 0.50
0.40. 0.84 60.84 0.60

R.S.B. F. Lumber CWN & TW


kgs. Bd.ft. kgs.
- 2 0.2
3.65 2 0.2
4.52 3 0.3
5.26 3 0.3
6.01 4 0.4
6.79 4 0.4
o sustain a finding of reasonableness otherwise
g. Mixture Cement Bags
D Sand
0.328 0.0438
0.633 0.0844
0.938 0.1250

Aggregate
Sand Gravel
Cu.m. Cu.m.
0.015 0.03
0.018 0.035
0.02 0.04
0.02 0.05
0.03 0.06
0.034 0.068
0.038 0.075
0.045 0.09
0.04 0.08
0.05 0.1
0.06 0.12

o O. Burdeos

rancisco E. Duarte

A. Samson

ction of the designed

that can be compacted


ntinous uniform
or by drying as
least 100 per cent

g. These areas should


ting units until required

You might also like