Professional Documents
Culture Documents
Itemized Cost of Revision: Proposed Variation Order No. 01
Itemized Cost of Revision: Proposed Variation Order No. 01
Itemized Cost of Revision: Proposed Variation Order No. 01
Contract ID :
Project : ROAD UPGRADING (GRAVEL TO CONCRETE) OF EASTERN BOBONGAN-SOMINOT MIDSALIP-DUMINGAG ROAD
Location : ZAMBOANGA DEL SUR
Contractor : ESR DEVELOPMENT AND CONSTRUCTION
ORIGINAL CONTRACT DATA REVISED (Proposed Variation Order No. 01) DIFFERENCE
ITEM DESCRIPTION REMARKS
QTY UNIT UNIT PRICE AMOUNT QTY UNIT UNIT PRICE AMOUNT QTY AMOUNT
101(3a) Removal of Structures and Obstruction (RCBC) 0.96 Sq.m 7,037.78 6,756.27 0.96 cu.m. 7,037.78 6,756.27 - -
101(3b) Removal of Structures and Obstruction (Irrigation Canal L=10.50m.) 0.68 Sq.m 2,483.93 1,689.07 0.68 sq..m. 2,483.93 1,689.07 - -
101(3c) Removal of Structures and Obstruction (Irrigation Canal L=22.40m.) 0.24 Sq.m 3,451.25 828.30 0.24 cu.m. 3,451.25 828.30 - -
101(4b) Removal of Structures and Obstruction (RCPC 610mm. Dia.meter) 9.00 Ln.M. 332.65 2,993.85 9.00 cu.m. 332.65 2,993.85 - -
102(2) Excavation ( Common Excavation ) Cu.m 0.00 698.47 cu.m. 248.79 173,772.35 (+) 698.47 (+) 173,772.35 INCREASED
103 Structure Excavation 182.00 Cu.m 236.19 42,986.58 198.63 cu.m. 331.05 65,756.46 (+) 16.63 (+) 22,769.88 INCREASED
103(3) Foundation Fill 1.50 Cu.m 997.96 1,496.94 5.50 cu.m. 997.96 5,488.78 (+) 4.00 (+) 3,991.84 INCREASED
103(6) Pipe Culverts and Drain Excavation 17.60 Cu.m 425.26 7,484.58 85.00 sq.m. 425.26 36,147.10 (+) 67.40 (+) 28,662.52 INCREASED
104(1) Embankment from Excavation 1,367.00 Cu.m 319.74 437,084.58 488.93 cu.m. 319.74 156,330.48 (-) (878.07) (-) (280,754.10) DECREASED
104(2) Embankment (Common Borrow) 4,918.00 Cu.m 669.12 3,290,732.16 8,055.06 cu.m. 669.12 5,389,801.75 (+) 3,137.06 (+) 2,099,069.59 INCREASED
105 Subgrade Preparation 6,190.00 Sq.m 29.48 182,481.20 5,982.98 sq.m. 29.48 176,378.25 (-) (207.02) (-) (6,102.95) DECREASED
200 Aggregate Subbase Course 5,552.50 Cu.m 1,146.79 6,367,551.48 5,625.13 cu.m. 1,146.79 6,450,842.83 (+) 72.63 (+) 83,291.36 INCREASED
300 Aggregate Surface Course 784.00 Cu.m 1,332.28 1,044,507.52 754.72 cu.m. 1,332.28 1,005,498.36 (-) (29.28) (-) (39,009.16) DECREASED
311 a Portland Cement concrete Pavement 0.23m Thick 10,665.50 Sq.m 1,692.78 18,054,345.09 10,683.36 sq.m. 1,692.78 18,084,578.14 (+) 17.86 (+) 30,233.05 INCREASED
404 a Reinforcing Steel Bar, Grade 40 12,209.00 Kg 79.88 975,254.92 11,745.42 Kg 79.88 938,224.15 (-) (463.58) (-) (37,030.77) DECREASED
405 Structural Concrete Class A 150.00 Cu.m 8,992.73 1,348,909.50 182.21 cu.m. 8,992.73 1,638,565.33 (+) 32.21 (+) 289,655.83 INCREASED
407 Lean Concrete 6.50 Cu.m 5,358.22 34,828.43 11.53 cu.m. 5,358.22 61,780.28 (+) 5.03 (+) 26,951.85 INCREASED
500 Pipe Culverts, 910mm. Dia.(36" dia) 31.00 l.m 6,273.90 194,490.90 55.00 cu.m. 6,273.90 345,064.50 (+) 24.00 (+) 150,573.60 INCREASED
505(5) Grouted RipRap, Class A 2,470.00 Cu.m 4,316.87 10,662,668.90 2550.31 cu.m. 4,316.87 11,009,356.73 (+) 80.31 (+) 346,687.83 INCREASED
506 Stone Masonry 9.50 Cu.m 5,106.81 48,514.70 42.27 each 5,106.81 215,864.86 (+) 32.77 (+) 167,350.16 INCREASED
611 (2) Trees, (Transplanting) 159.00 Each 492.59 78,321.81 (-) (159.00) (-) (78,321.81) DELETED
FEA 1.1 Bunkhouse, CL School Bldg. Dep-Ed Type&Complete 1.00 LS 1,121,395.97 1,121,395.97 1.00 each 745,300.00 745,300.00 - (-) (376,095.97) DECREASED
FEA 1.2 Project Billboard 2.00 Unit 5,273.87 10,547.74 2.00 sq.m. 5,273.87 10,547.74 - -
FEA 1.3 Construction Safety and Health Program 1.00 LS 200,390.40 200,390.40 1.00 ln.m. 200,390.40 200,390.40 - -
FEA 1.4 Provision of a Service Vehicle for the Engineers 4.50 Mon. 201,923.28 908,654.76 4.50 sq.m. 201,923.28 908,654.76 - -
SPL-1 Mobilization & Demobilization 1.00 LS 402,192.00 402,192.00 1.00 L.S 402,192.00 402,192.00 - -
603 Guardrails 140.00 pcs 4,748.06 664,728.40 (+) 140.00 (+) 664,728.40 NEW ITEM
RENATO V. CABABAT ANSELMO J. OBEDENCIA, JR. LEONCIO B. SOLAMILLO NENITA A. ROBLES, CESO IV JORGE U. SEBASTIAN, JR., CESO III
Project Engineer Project Engineer III Chief, Construction Division Assistant Regional Director Regional Director
ESR DEV. AND CONST. CORP.
Republic of the Philippines
Department of Public Works & Highways
OFFICE OF THE REGIONAL DIRECTOR
Region IX
Tetuan,Zamboanga City
Name of Project: ROAD UPGRADING (GRAVEL TO CONCRETE) OF EASTERN BOBONGAN-SOMINOT MIDSALIP-DUMINGAG ROAD
We are submitting herein described changes from the Plans and Specifications, or do the following described work not included in the Plans and Specifications.
We the undersigned contractor have given careful consideration to the change proposed & hereby agree, if this PREPARED & SUBMITTED BY : ANSELMO J. OBEDENCIA, JR.
proposal is approved, that will provide all requirements, furnished all materials except as may otherwise be noted above & TITLE : Project Engineer III
perform all services shown on the reverse side of this sheet.
ITEMIZED QUANTITIES AND COST REVISION ON REVERSE SIDE IF THIS SHEET CHECKED AND REVIEWED : LEONCIO B. SOLAMILLO
Difference in cost this change( -/+ ) (+) 3,270,423.51 TITLE : Chief, Construction Division
Net cost previous change
Original contract amount 45,427,107.64
Estimated revised contract amount 48,697,531.14
By reason of this proposed change 60 calendar days extension RECOMMENDING APPROVAL: NENITA A. ROBLES, CESO IV
of contract time will be allowed. Total extension of time to date including TITLE : Assistant Regional Director
this Change Order 60 calendar days.