Itemized Cost of Revision: Proposed Variation Order No. 01

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

ITEMIZED COST OF REVISION

Proposed Variation Order No. 01

Contract ID :
Project : ROAD UPGRADING (GRAVEL TO CONCRETE) OF EASTERN BOBONGAN-SOMINOT MIDSALIP-DUMINGAG ROAD
Location : ZAMBOANGA DEL SUR
Contractor : ESR DEVELOPMENT AND CONSTRUCTION
ORIGINAL CONTRACT DATA REVISED (Proposed Variation Order No. 01) DIFFERENCE
ITEM DESCRIPTION REMARKS
QTY UNIT UNIT PRICE AMOUNT QTY UNIT UNIT PRICE AMOUNT QTY AMOUNT
101(3a) Removal of Structures and Obstruction (RCBC) 0.96 Sq.m 7,037.78 6,756.27 0.96 cu.m. 7,037.78 6,756.27 - -
101(3b) Removal of Structures and Obstruction (Irrigation Canal L=10.50m.) 0.68 Sq.m 2,483.93 1,689.07 0.68 sq..m. 2,483.93 1,689.07 - -
101(3c) Removal of Structures and Obstruction (Irrigation Canal L=22.40m.) 0.24 Sq.m 3,451.25 828.30 0.24 cu.m. 3,451.25 828.30 - -
101(4b) Removal of Structures and Obstruction (RCPC 610mm. Dia.meter) 9.00 Ln.M. 332.65 2,993.85 9.00 cu.m. 332.65 2,993.85 - -
102(2) Excavation ( Common Excavation ) Cu.m 0.00 698.47 cu.m. 248.79 173,772.35 (+) 698.47 (+) 173,772.35 INCREASED
103 Structure Excavation 182.00 Cu.m 236.19 42,986.58 198.63 cu.m. 331.05 65,756.46 (+) 16.63 (+) 22,769.88 INCREASED
103(3) Foundation Fill 1.50 Cu.m 997.96 1,496.94 5.50 cu.m. 997.96 5,488.78 (+) 4.00 (+) 3,991.84 INCREASED
103(6) Pipe Culverts and Drain Excavation 17.60 Cu.m 425.26 7,484.58 85.00 sq.m. 425.26 36,147.10 (+) 67.40 (+) 28,662.52 INCREASED
104(1) Embankment from Excavation 1,367.00 Cu.m 319.74 437,084.58 488.93 cu.m. 319.74 156,330.48 (-) (878.07) (-) (280,754.10) DECREASED
104(2) Embankment (Common Borrow) 4,918.00 Cu.m 669.12 3,290,732.16 8,055.06 cu.m. 669.12 5,389,801.75 (+) 3,137.06 (+) 2,099,069.59 INCREASED
105 Subgrade Preparation 6,190.00 Sq.m 29.48 182,481.20 5,982.98 sq.m. 29.48 176,378.25 (-) (207.02) (-) (6,102.95) DECREASED
200 Aggregate Subbase Course 5,552.50 Cu.m 1,146.79 6,367,551.48 5,625.13 cu.m. 1,146.79 6,450,842.83 (+) 72.63 (+) 83,291.36 INCREASED
300 Aggregate Surface Course 784.00 Cu.m 1,332.28 1,044,507.52 754.72 cu.m. 1,332.28 1,005,498.36 (-) (29.28) (-) (39,009.16) DECREASED
311 a Portland Cement concrete Pavement 0.23m Thick 10,665.50 Sq.m 1,692.78 18,054,345.09 10,683.36 sq.m. 1,692.78 18,084,578.14 (+) 17.86 (+) 30,233.05 INCREASED
404 a Reinforcing Steel Bar, Grade 40 12,209.00 Kg 79.88 975,254.92 11,745.42 Kg 79.88 938,224.15 (-) (463.58) (-) (37,030.77) DECREASED
405 Structural Concrete Class A 150.00 Cu.m 8,992.73 1,348,909.50 182.21 cu.m. 8,992.73 1,638,565.33 (+) 32.21 (+) 289,655.83 INCREASED
407 Lean Concrete 6.50 Cu.m 5,358.22 34,828.43 11.53 cu.m. 5,358.22 61,780.28 (+) 5.03 (+) 26,951.85 INCREASED
500 Pipe Culverts, 910mm. Dia.(36" dia) 31.00 l.m 6,273.90 194,490.90 55.00 cu.m. 6,273.90 345,064.50 (+) 24.00 (+) 150,573.60 INCREASED
505(5) Grouted RipRap, Class A 2,470.00 Cu.m 4,316.87 10,662,668.90 2550.31 cu.m. 4,316.87 11,009,356.73 (+) 80.31 (+) 346,687.83 INCREASED
506 Stone Masonry 9.50 Cu.m 5,106.81 48,514.70 42.27 each 5,106.81 215,864.86 (+) 32.77 (+) 167,350.16 INCREASED
611 (2) Trees, (Transplanting) 159.00 Each 492.59 78,321.81 (-) (159.00) (-) (78,321.81) DELETED
FEA 1.1 Bunkhouse, CL School Bldg. Dep-Ed Type&Complete 1.00 LS 1,121,395.97 1,121,395.97 1.00 each 745,300.00 745,300.00 - (-) (376,095.97) DECREASED
FEA 1.2 Project Billboard 2.00 Unit 5,273.87 10,547.74 2.00 sq.m. 5,273.87 10,547.74 - -
FEA 1.3 Construction Safety and Health Program 1.00 LS 200,390.40 200,390.40 1.00 ln.m. 200,390.40 200,390.40 - -
FEA 1.4 Provision of a Service Vehicle for the Engineers 4.50 Mon. 201,923.28 908,654.76 4.50 sq.m. 201,923.28 908,654.76 - -
SPL-1 Mobilization & Demobilization 1.00 LS 402,192.00 402,192.00 1.00 L.S 402,192.00 402,192.00 - -
603 Guardrails 140.00 pcs 4,748.06 664,728.40 (+) 140.00 (+) 664,728.40 NEW ITEM

45,427,107.64 48,697,531.14 (+) 3,270,423.51


Original Contract Cost 45,427,107.64
New Sum Involed in this Revision 48,697,531.14
Difference in Cost (Plus or Minus) (+) 3,270,423.51

Prepared by: Concurred by: Submitted: Recommending Approval Approved by:

RENATO V. CABABAT ANSELMO J. OBEDENCIA, JR. LEONCIO B. SOLAMILLO NENITA A. ROBLES, CESO IV JORGE U. SEBASTIAN, JR., CESO III
Project Engineer Project Engineer III Chief, Construction Division Assistant Regional Director Regional Director
ESR DEV. AND CONST. CORP.
Republic of the Philippines
Department of Public Works & Highways
OFFICE OF THE REGIONAL DIRECTOR
Region IX
Tetuan,Zamboanga City

VARIATION ORDER NO. 01

Name of Project: ROAD UPGRADING (GRAVEL TO CONCRETE) OF EASTERN BOBONGAN-SOMINOT MIDSALIP-DUMINGAG ROAD

TO: The Manager, ESR CONSTRUCTION & DEVELOPMENT CORPORATION

We are submitting herein described changes from the Plans and Specifications, or do the following described work not included in the Plans and Specifications.

DESCRIPTION OF WORK TO BE DONE:


INCREASED ITEM 102(2) Surplus Common Excavation, 105 Subgrade Preparation, 200 Aggregate Subbase Course, 300 Aggregate Surface Course,
311(a) PCCP, 0.28m. Thick; NEW ITEM 101(3) Removal of Existing Pavement

REASON FOR CHANGE:


To utilize the extra amount coming from variance as mandated per DO# 47, S - 2011 and to recompensate the extra works suiting actual site
condition. Additional of 210 meters of Two lanes for item 311, removal of Existing PCCP 4m width x 210m length Two lanes and increased Grouted Riprap. The final project limit
extends for 210 meters backward with Sta.1685+540.91 to 1689+600 and a total of 3,879.18 Linear meters net length.

CHANGE REQUESTED BY : ESR CONSTRUCTION & DEVELOPMENT CORPORATION

We the undersigned contractor have given careful consideration to the change proposed & hereby agree, if this PREPARED & SUBMITTED BY : ANSELMO J. OBEDENCIA, JR.
proposal is approved, that will provide all requirements, furnished all materials except as may otherwise be noted above & TITLE : Project Engineer III
perform all services shown on the reverse side of this sheet.

ITEMIZED QUANTITIES AND COST REVISION ON REVERSE SIDE IF THIS SHEET CHECKED AND REVIEWED : LEONCIO B. SOLAMILLO
Difference in cost this change( -/+ ) (+) 3,270,423.51 TITLE : Chief, Construction Division
Net cost previous change
Original contract amount 45,427,107.64
Estimated revised contract amount 48,697,531.14
By reason of this proposed change 60 calendar days extension RECOMMENDING APPROVAL: NENITA A. ROBLES, CESO IV
of contract time will be allowed. Total extension of time to date including TITLE : Assistant Regional Director
this Change Order 60 calendar days.

APPROVED : JORGE U. SEBASTIAN, JR., CESO III


Accepted by: EDMARIO S. REVELO TITLE : Regional Director
Contractor/General Manager Date :
Date :
Note : This Change/Extra Work is not valid until Approved