Professional Documents
Culture Documents
REPORT Slump Test
REPORT Slump Test
GROUP 1
MEMBERS;
1) AMIRUL RASYID BIN SHANSUL BAHRI BEQ 110003
2) FATIN KHAIRUNNISA BT MOHD NASIR BEQ 110011
3) HARUN AL RASHID BIN MUHANI BEQ 110015
4) MOHD HAFIZ BIN MOHD SAPIEE BEQ 110023
5) MUHAMMAD AZRUL HAZMAN BIN HAMDAN BEQ 110024
6) NAZIHAH BT YUSOP BEQ 110026
7) SHAHRIN BIN MOHAMAD BEQ 110037
8) MOHD RIJALUDDIN RABBANI MOHD NASIR BEQ 110047
9) MUHAMAD AKMAL
10) AMIN ALI DOSTI
OBJECTIVE: To determine the strength and workability of concrete mixture
THEORY: To determine the concrete fulfils the required specification, 2 types of concrete testing to be
conducted are slump test and cube test (compression test).
Slump test
This is a site test to determine the workability of the ready mixed concrete just before its placing to final
position inside the formwork, and is always conducted by the supervisor on site. However in mid of
concreting process , should the site supervisor visually finds that the green concrete becomes dry or the
placement of concrete has been interrupted , a re-test on the remaining concrete should be conducted
in particular of the pour for congested reinforcement area
APPARATUS
Compression test
The Compression Test is a laboratory test to determine the characteristic strength of the concrete but
the making of test cubes is sometimes carried out by the supervisor on site. This cube test result is very
important to the acceptance of insitu concrete work since it demonstrates the strength of the design
mix.
APPARATUS
SLUMP TEST REPORT
Relevant Standards: BS 1881: Part 125: 1983. Testing concrete- Methods for mixing and sampling fresh
concrete in the laboratory.
1. The quantity of concrete produced was 10% more than required for the proposed tests.
2. The aggregates were in laboratory dry condition. Adjustment was made to the concrete mix
proportion to allow for adsorption of mix water by aggregates.
Step 2: Mixing
8. The paddles were cleaned and material was mixed thoroughly by hand.
9. The remaining water was added and the material was mixed for further 2 minutes.
10. For ensuring homogeneity, the material was mixed by hand.
Step 3: Testing.
3. The test was repeated, return used concrete to the mixer and re-mix for 30 seconds.
4. For the second slump test. Our group got shear slump.
5. The test was repeated again, return used concrete to the mixer and re-mix for 30 seconds.
6. For the third slump test, our group successfully got true slump with 7-10 mm slump.
SLUMP TEST REPORT
1. 150 mm standard cube mold is to be used for concrete mix and 100 mm standard cube mold is
to be used for grout mix.
2. Make sure the apparatus and associated equipment are clean before test and free from
hardened concrete and superfluous water .
3. Assemble the cube mold correctly and ensure all nuts are tightened.
4. Apply a light coat of proprietary mold oil on the internal faces of the mold.
5. Place the mold on level firm ground and fill with sampled concrete to a layer of about 50 mm
thick.
6. Compact the layer of concrete thoroughly by tamping the whole surface area with the Standard
Tamping Bar. (Note that no less than 35 tamps / layer for 150 mm mold and no less than 25
tamps / layer for 100 mm mold).
7. Repeat Steps 5 & 6 until the mold is all filled. (Note that 3 layers to be proceeded for 150 mm
mold and 2 layers for 100 mm mold).
8. Remove the surplus concrete after the mold is fully filled and trowel the top surface flush with
the mold.
9. Mark the cube surface with an identification number (say simply 1, 2, 3, etc) with a nail or
match stick and record these numbers in respect with the concrete truck and location of pour
where the sampled concrete is obtained.
10. Cover the cube surface with a piece of damp cloth or polythene sheeting and keep the cube in a
place free from vibration for about 24 hours to allow initial set .
11. Strip off the mold pieces in about 24 hours after the respective pour is cast. Press the concrete
surface with the thumb to see any denting to ensure the concrete is sufficiently hardened, or
otherwise de-molding has to be delayed for one more day
If the slump is not within the desired range, or the mixture is obviously either too fluid or too stiff, the
proportions of the mixture must be change. To make more fluid and increase the slump, increase the
proportion of water and cement without changing the water/cement ratio. To make the mixture stiffer
and decrease the slump, increase the proportion of aggregates without changing the fine/course
aggregate ratio. Do not just add water to make the mix more fluid; this will weaken the concrete.