I. CONCRETTING WORKS
1.0 CHB 5" 177.75 pcs 14.94 14.94 2,655.59
2.0 Cement 20.76 pcs 226.60 226.60 4,703.31
3.0 Sand 1.78 cu.m. 824.00 824.00 1,470.02
4.0 Gravel 0.95 cu.m. 1,339.00 1,339.00 1,272.05
5.0 Formworks 1.00 lot 711.94 711.94
6.0 Labor 1.00 lot 2,020.19
7.0 Demolition of affected Sidewalk 1.00 lot 212.00 212.00
8.0 Installation of new inlet 1.00 lot 212.00 212.00
9.0 Restoration of affected Sidewalk 1.00 lot 1,500.00 1,500.00
Total Cost per Manhole 14,757.09
Affected Manholes - approx. 85 units
TOTAL COST OF RESTORATION 85.00 14,757.09 1,254,352.88