TECHNICAL AND COMMERCIAL OFFER | April 2019 | rev.

00
Enquiry No.219010 - Battery N4 Oven 199 through wall repair.
Appendix 3. Work schedule COB#4 199-200 AMSA NewCastle Rev 0

Work schedule AMSA NewCastle Battery N4 Oven 199 through wall repair (FW Enquiry - N219010)

Calendar days of repair


№ Description

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
1
2
3
4
5
6
7
8
9
1 Preparation works before cooling of heating
walls 199,200- inspection of anchorage
system, bracing of backstays, installing of
packages for passage of coal charging car and
crossover, coke pushing from chambers under
repair 198,199,200 and buffer chambers 197,
installing of façade and front bridges

2 Switch off heating, cooling and dismantling


heating walls 199,200 under repair

3 Removal/installing equipment under repaired


chambers 198,199,200 and heating walls
199,200 (gas outlet standpipes, frames, flash
plates, upper part of backstay, upper tie-rods,
frames of charging hole)

4 Bricklaying of heating walls 199,200 and


roofing of chamber 198,199,200

5 Heating up of heating walls 199,200 through


temporary stoves

6 Works executed from the beginning of heating


up till start of operation of buffer chamber
under repair. Control of load pressure of
reinforcing, blowing and pouring grooves of
transverse tie bars, removing of packages for
passage of coal charging machine, crossover,
fixing beam for backstays and tie rods,
removing bracing bulkheads from buffer and
chamber under repair, blowing of coke
chamber sole(bottom)

7 Coke charging of buffer ovens and repaired


ovens 197, 198, 199,200