Enquiry N219012 - Battery N4 Ovens 195-198 through wall repair
Work Shedule AMSA NewCastle Battery N4 Oven 195-198 through wall repair (FW Enquiry - N219012)
Calendar days
№ Description
01 - 10 11 - 20 21 - 30 31 - 40 41 - 50 51 - 60 61 - 70 71 - 80 81 - 90 91 - 100 101 - 110 111 - 120 121 - 130 131 - 140 141 - 150 151 - 160 161 - 170 171 - 180
Section 1. Heating wall № 197,198 through wall
Preparation works before cooling of heating walls 197,198- inspection of
anchorage system, bracing of backstays, installing of packages for passage of
1 coal charging car and crossover, coke pushing from chambers under repair
196,197,198 and buffer chambers 195 and 199, installing of façade and front
bridges.
Switch off heating, cooling and dismantling heating walls 197,198 under
2
repair
Removal/installing equipment under repaired chambers 196,197,198 and
3 heating walls 197,198 (gas outlet standpipes, frames, flash plates, upper
part of backstay, upper tie-rods, frames of charging hole)