TECHNICAL AND COMMERCIAL OFFER | April 2019 | rev.

00
Enquiry N219012 - Battery N4 Ovens 195-198 through wall repair

Work Shedule AMSA NewCastle Battery N4 Oven 195-198 through wall repair (FW Enquiry - N219012)
Calendar days
№ Description
01 - 10 11 - 20 21 - 30 31 - 40 41 - 50 51 - 60 61 - 70 71 - 80 81 - 90 91 - 100 101 - 110 111 - 120 121 - 130 131 - 140 141 - 150 151 - 160 161 - 170 171 - 180
Section 1. Heating wall № 197,198 through wall
Preparation works before cooling of heating walls 197,198- inspection of
anchorage system, bracing of backstays, installing of packages for passage of
1 coal charging car and crossover, coke pushing from chambers under repair
196,197,198 and buffer chambers 195 and 199, installing of façade and front
bridges.
Switch off heating, cooling and dismantling heating walls 197,198 under
2
repair
Removal/installing equipment under repaired chambers 196,197,198 and
3 heating walls 197,198 (gas outlet standpipes, frames, flash plates, upper
part of backstay, upper tie-rods, frames of charging hole)

4 Bricklaying of heating walls 197,198 and roofing of chamber 196,197,198

Section 2. Heating wall №195,196 through wall


Preparation works before cooling of heating walls 195,196- inspection of
anchorage system, bracing of backstays, installing of packages for passage of
5 coal charging machine and crossover, coke pushing from repaired chambers
194,195,196 and buffer chambers 193 and 197, installing of façade and
bridges under repair
Switch off heating, cooling and dismantling heating walls 195,196 under
6
repair
Removal/Installing equipment under repaired chambers 194,195,196 and
7 heating walls 195,196 (gas outlet standpipes, frames, flash plates, upper
part of backstay, upper tie-rods, frames of charging hole) stage-by-stage.

8 Bricklaying of heating walls 195,196 and roofing of chamber 194,195,196

Final works for stage 1 & 2


9 Heating up of heating walls 195,196,197,198 through temporary stoves

Works executed from the beginning of heating up till start of operation of


buffer chamber under repair. Control of load pressure of reinforcing,
blowing and pouring grooves of transverse tie bars, removing of packages
10
for passage of coal charging machine, crossover, fixing beam for backstays
and tie rods, removing bracing bulkheads from buffer and chamber under
repair, blowing of coke chamber sole(bottom)

Coke charging of buffer ovens and repaired ovens 193,194,195, 196,


11
197, 198, 199