ANALISA HARGA SATUAN

PEKERJAAN : PEMBANGUNAN PAGAR PEMBATAS LAHAN ITK


LOKASI : KAMPUS ITK KARANG JOANG
T.A : 2019

KO JUMLAH HARGA
DE URAIAN PEKERJAAN SAT. HARGA
SATUAN UPAH BAHAN JUMLAH
1 2 3 4 5 6 7
PENGGALIAN TANAH 1 m3
0.4000 oh Pekerja 90,000.00 36,000.00 36,000.00
0.0400 oh Mandor 128,000.00 5,120.00 5,120.00
Total 41,120.00
URUGAN KEMBALI 1 m3
0.1920 oh Pekerja 90,000.00 17,280.00 17,280.00
0.0190 oh Mandor 128,000.00 2,432.00 2,432.00
Total 19,712.00
PEMADATAN TANAH 1 m3
0.5000 oh Pekerja 90,000.00 45,000.00 45,000.00
0.0500 oh Mandor 128,000.00 6,400.00 6,400.00
Total 51,400.00
PEKERJAAN BETON
BETON MUTU K 175 1 m3
0.2750 oh Tukang 105,000.00 28,875.00 28,875.00
0.0280 oh Kepala Tukang 120,000.00 3,360.00 3,360.00
1.6500 oh Pekerja 90,000.00 148,500.00 148,500.00
0.0830 oh Mandor 128,000.00 10,624.00 10,624.00
0.7600 m3 Pasir beton 277,200.00 210,672.00 210,672.00
0.1029 m3 koral beton 423,500.00 43,578.15 43,578.15
0.2150 ltr air 385.00 82.78 82.78
326.0000 kg Semen 1,155.00 376,530.00 376,530.00
Total 822,221.93
COR BETON Camp. 1Pc : 2Ps : 3Kr 1 m3
1.0000 oh Tukang Batu 105,000.00 105,000.00 105,000.00
0.1000 oh Kepala Tukang Batu 120,000.00 12,000.00 12,000.00
0.6000 oh Pekerja 90,000.00 54,000.00 54,000.00
0.3000 oh Mandor 128,000.00 38,400.00 38,400.00
0.6500 m3 Pasir Beton 277,200.00 180,180.00 180,180.00 180,180.00
0.6500 m3 Agregat Pecah Mesin 8-10 & 10-20 mm 423,500.00 275,275.00 275,275.00 275,275.00
388.0000 kg Semen 1,155.00 448,140.00 448,140.00 448,140.00
Total 1,112,995.00
PEMBESIAN DGN BESI POLOS 1 kg
0.0070 oh Tukang Besi 105,000.00 735.00 735.00
0.0007 oh Kepala Tukang Besi 120,000.00 84.00 84.00
0.0070 oh Pekerja 90,000.00 630.00 630.00
0.0003 oh Mandor 128,000.00 38.40 38.40
1.0500 kg Besi beton polos 13,860.00 14,553.00 14,553.00 14,553.00
0.0150 kg Kawat Beton 19,250.00 288.75 288.75 288.75
Total 16,329.15
KO JUMLAH HARGA
DE URAIAN PEKERJAAN SAT. HARGA
SATUAN UPAH BAHAN JUMLAH
1 2 3 4 5 6 7
PASANG ULIN 10/10 - 400 titik
0.100 M3 Kayu ulin 8/8 - 400 160,160.00 16,016.00 16,016.00
1.000 BH Aalat bantu 45,000.00 45,000.00 45,000.00
0.200 OH Pekerja 90,000.00 18,000.00 18,000.00
0.010 OH Tukang kayu 120,000.00 1,200.00 1,200.00
0.001 OH Kepala Tukang 120,000.00 120.00 120.00
0.001 OH Mandor 128,000.00 128.00 128.00
Total 80,464.00
PASANG BEKISTING UNTUK PONDASI 1 m2
0.030 M3 Kayu papan meranti 2,310,000.00 69,300.00 69,300.00
0.019 M3 Kayu balok meranti 2,233,000.00 42,427.00 42,427.00
2.000 Btg Dolken kayu galam dia 8 7,700.00 15,400.00 15,400.00
0.400 Kg Paku Biasa 15,400.00 6,160.00 6,160.00
0.300 Ltr Minyak Bekisting 11,550.00 3,465.00 3,465.00
0.350 Lbr Plywood tebal 9 mm 66,605.00 23,311.75 23,311.75
0.660 OH Pekerja 90,000.00 59,400.00 59,400.00
0.330 OH Tukang kayu 105,000.00 34,650.00 34,650.00
0.033 OH Kepala Tukang 120,000.00 3,960.00 3,960.00
0.033 OH Mandor 128,000.00 4,224.00 4,224.00
Total 262,297.75

PASANG KAWAT BERDURI GALVANIS 1 m2


1.000 btg dolken kayu galam 7,700.00 7,700.00 7,700.00
15.000 m' kawat duri 3,000.00 45,000.00 45,000.00
0.060 kg paku biasa 15,400.00 924.00 924.00
0.200 OH Pekerja 90,000.00 18,000.00 18,000.00
0.300 OH Tukang kayu 105,000.00 31,500.00 31,500.00
0.020 OH Kepala Tukang 120,000.00 2,400.00 2,400.00
0.020 OH Mandor 128,000.00 2,560.00 2,560.00
Total 108,084.00