CTI Engineering International Co., LTD.: Project Log Book (For Inspector)

You might also like

You are on page 1of 1

CTI Engineering International Co., Ltd.

THE CONSULTANCY SERVICES FOR THE CONSTRUCTION SUPERVISION OF THE FLOOD RISK
MANAGEMENT PROJECT (FRIMP) FOR THE CAGAYAN RIVER, TAGOLOAN RIVER AND IMUS RIVER
(JICA LOAN AGREEMENT NO. PH-P253)
PROJECT LOG BOOK (for INSPECTOR)
Current Date : April 30, 2020 WEATHER AT SITE:
Project Title : Flood Risk Management Project (FRIMP) AM PM
Imus River Basin Sub-Project
Fair Fair
Contract Period : August 20, 2016 – November 09, 2020
Contract Amount : PHP 1,470,379,161.66
INSPECTION ITEMS AT SITE:
RESULT
LOCATION (Sta.) ITEM DESCRIPTION Q'TY (OK/NG)
Bacoor Site 1) @BRB-A: Sloping activity at Separating Dike.
2) @BRB-A: Excavation at Connecting Sluice.

Imus Site 1) Concrete pouring Of Base Concrete (bottom section)


sta. 0+350 - sta. 0+400
AM

2) Concrete pouring of CBRW (BF/FC) sta. 0+612 - sta. 0+710.


(top setion).
3) Backfilling at Dranage Sluice 2x2m.
4) Backfilling of inlet sta. 2+360
Bacoor Site 1) @BRB-A: Concrete pouring of CBRW (BF/FC) sta. 0+060 -
sta. 0+725.
Noveleta Casting Yard 1) Concrete pouring of precast blocks (End Blocks)
PM

3004 pcs.
2) Concrete pouring of precast blocks (Concrete Blocks) 7779 pcs.
Note: Concrete pouring of precast blocks c/o CAVDEAL ME II; Night-time hauling c/o DPWH checker.
POINT(S) TO BE NOTED AT SITE:

QUALITY TEST(S) AT LABORATORY:


MATERIALS LOCATION TO BE USED RESULT

AVAILABLE MANPOWER & EQUIPMENT: EQPT ON SITE EQPT ON SITE


WORKFORCE Q'TY OS WORKFORCE Q'TY OS EQUIPMENT SCHEDULE Q'TY O S B EQUIPMENT SCHEDULE Q'TY O S B
Project Manager 1 1 Project Nurse 1 1 Bulldozer with Ripper 4 3 Flatbed Truck/Highbed 3 1
Const. Manager 1 HR Officer 1 1 Crawler Backhoe w/ Breaker 4 Bar Cutter 6
Project Engineer AutoCAD operator 4 2 Crawler Backhoe w/ Vibro Hammer Bar Bender 6 1
Earthworks 2 1 Technical Staff 3 Crawler Backhoe 4 7 7 Concrete Vibrator 2 2 1
Drainage 2 1 Lab. Technician 6 3 Wheel type Backhoe 1 Concrete Cutter 1
Slope 2 2 Lab. Aide 6 1 Loader, Wheel type 8 1 Concrete Screeder
Roadway 2 Survey Aide 12 3 Dumptruck 20 6 26 Bagger Concrete Mixer 4 1
QE/Surveyor 2 2 Clerk 3 1 Road Grader 1 Generator Set w/ set of Lightings 6 2
Materials Engr. 2 1 Operator 23 9 Road Roller, Vibratory 1 1 Concrete Batching Plant 1 1
Materials Engr. 1 1 Driver 42 10 Water Truck 2 1 Electric Welding Machine 3 3
Highway Engineer 1 Mechanic 6 3 Transit Mixer 9 3 Cutting/Burning Machine 3 3
Surveyor 4 2 Electrician 2 1 Pumpcrete 1 1 Plate Compactor** - 2 1
Equipment Engr. 2 1 Security Guard 10 5 Mobile Crane 2 Tamping Rammer** - 1 1
Safety Officer 1 1 Skilled Laborer 52 33 BoomTruck 2
Envi. Engineer 1 Unskilled Lab. 116 17 Elf w/ Basket Lift
Field Engineer 6 2 Checker* - Elf/Pick-up Service 4 4
Warehouseman* - 1
Total 316 103 Total 95 25 57 1
X: Absent / not on Site , OS: On Site O: Operating/in use, S: Standby/not utilized, B: Breakdown
*Checker & Warehouseman are not included in the manpower schedule. **Plate compactor and Tamping Rammer are not included in the equipment schedule.
Note: Recorded are the total quantities of manpower and equipment mobilized at Bacoor and Imus RB, at Temporary Stock Yards & at Noveleta Casting Yard.

Submitted by: Checked by:

____LEMUEL JAKE T. TAPEC____ ___ARJINE I. RAMIREZ___


INSPECTOR STRUCTURAL ENGINEER

Noted by:

______SHUJI KAKU________
PROJECT MANAGER