Progress S-Curve

Engineering

99% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
100% 97% 98%
95%
92% 99% 99% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
97%
90% 93%

80% 88%
80% 83%

70%
62%
Percentage

60%
62%

50%
48%

40% 44%

% Montly Cum Plan (Baseline 0) 34%


30%
% Montly Cum Actual 24% 30%
% Montly Cum Plan (Mitigation Plan 2)
20% Plan 3)
% Montly Cum Plan (Mitigation
22%
Mitigation Plan 4

10%
15%
5%
0% 0% 0% 1% 8%
0% 0% 1% 2% 3%

Month No 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Monthly Cut-off Date 25-Jul 25-Aug 25-Sep 25-Oct 25-Nov 25-Dec 25-Jan 25-Feb 25-Mar 25-Apr 25-May 25-Jun 25-Jul 25-Aug 25-Sep 25-Oct 25-Nov 25-Dec 25-Jan 25-Feb 25-Mar 25-Apr 25-May 25-Jun 25-Jul 25-Aug 25-Sep 25-Oct

% Montly Cum Plan (Baseline 0) 0% 0% 0% 1% 5% 24% 48% 62% 80% 92% 95% 97% 98% 99% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

% Montly Cum Plan (Mitigation


99% 99% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Plan 2)
% Montly Cum Plan (Mitigation
100% 100% 100% 100% 100% 100% 100% 100% 100%
Plan 3)
% Montly Cum Plan (Mitigation
100% 100% 100% 100% 100% 100%
Plan 4
% Montly Cum Actual 0% 1% 2% 3% 8% 15% 22% 30% 34% 44% 62% 83% 88% 93% 97% 99% 99% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

VARIANCE (Mitigation VS ACTUAL) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%