Earthquake Risk Buildings

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

57

CASE STUDIES: EARTHQUAKE RISK BUILDINGS


1. NEW P L Y M O U T H G I R L S ' HIGH SCHOOL
S T R U C T U R A L S T R E N G T H E N I N G A N D U P G R A D I N G OF
THE 1926 B L O C K

D.L. Hutchison* and W.D. Gill**


INTRODUCTION: corridor, reasonable symmetry would be
achieved in the north-south direction;
The building forms the apex of a two- symmetry is already adequate in the
storey L-shaped classroom block, the legs' 1
east-west direction.
of the L having been added later and
including walls of reinforced concrete. It was decided initially to consider
This section was built in 1926 and is of two levels of design seismic loadings
cavity brick construction with reinforced for the 1926 block, viz 'full code
concrete bands provided at first floor and (NZS 4203:1976) and 'two thirds code'.
1

eaves level. Floors and roof trusses are Design proceeded first of all using
of timber. full code in both directions -

The L-shaped block as a whole is not C = C I S M R


of great architectural importance and the a
=.125 x 1.3x2.4 xl.O x 1.0
suite of buildings in the school grounds
have no consistent architectural form. = 0.39 g
Consequently, thought had been given to
demolishing the 192 6 building of the for flexure.
classroom block and replacing its
facilities elsewhere in the grounds. An over-strength factor of about 50%
However, because toilets and main stairway was used for shear design.
servicing the L-shaped classroom block
are all located in the 1926 building, The solution adopted in the end for
it was decided it should be retained. protection of walls achieved this level
of strength for in-plane loading as
An initial feasibility study had well as satisfying face loading
considered the possibility of tying the requirements with generally the minimum
1926 building to the adjacent *legs . 1
percentage of reinforcement required
Unfortunately, the system of horizontal by NZS 3101:1982. Hence a redesign to
ties at first floor level would have been two-thirds of code was not considered
seriously interrupted by the stairwell. warranted, an observation noted by
Furthermore, such a solution relies on the Garrettd) in the case of strengthening
brickwork being able to withstand face of Hastings Boys High School. 1

loading by spanning without protection


between floors. Initially, diaphragm action at first
floor and eaves level was designed in
The 1926 block also^contains four steel bracing using channel sections.
classrooms of about 47 m each. The These bracing planes were to be tied
total area per floor^of the two-storey into the reinforced concrete bond
block is about 250 m . A lightweight beams at each level. However, after
decramastic roof has replaced the former costing, this system was rejected
concrete tile roof in recent times. and instead, an overlay of particle
board was used at first floor and
Inevitably, upgrading of other ceiling level. Neither solution was
aspects of an old building are considered sufficiently stiff to act as a diaphragm
once the decision to strengthen the in the normal sense of the term, i.e. f

structure is taken. Accordingly, both where 'infinite' stiffness ensures


plumbing and electrical services were that each element of wall receives
upgraded, and the building interior applied shear in proportion to its
finish was completely redone. stiffness. Thus, each section of wall
strengthening was designed to resist
The structural cost was about half load accruing from respective tributary
the total value of the strengthening/ areas of floor, plus loads resulting
refurbishing operation. from their own inertia as well as that
of tributary face loaded walls. The
This article concentrates on structural timber diaphragm therefore served
matters. primarily to tie face-loaded walls to
nearby orthogonal walls. Such an
LEVEL OF DESIGN LOADING AND STRENGTHENING approach is justified provided that
SOLUTION ADOPTED: the layout of walls is reasonably
symmetrical. Boardman
The layout of the 1926 block is shown (2)
in Fig 1 Structural' brick of up to 14
1
used a
in. (356 mm) is present. It is evident similar approach to design.
that, by bricking up some of the window In order to obtain relative costs,
openings in the interior wall to the a variety of solutions for strengthening
a typical piece of brickwork of the
* Ministry of Works and Development, 1926 block were designed. In order
Wellington of economy (cheapest first), the solutions
** Ministry of Works and Development, considered were as follows:
New Plymouth
B U L L E T I N OF T H E NEW Z E A L A N D S O C I E T Y F O R E A R T H Q U A K E E N G I N E E R I N G , V O L . 17, NO. 1, M A R C H 1984
58 FIGURE 1

1926 BLOCK Z PART 1940 BLOCK FROM E A S T SIDE.


59

1 GRC plaster coat to two faces and, in general, two layers of 665 HRC
mesh were used, staggered by 7 5 mm to
2 Steel braced frame minimise shadowing from the process of
applying sprayed concrete. Apart from
3 Post-tensioned brickwork trimmers around openings, additional bars
of deformed steel were used at ends of
4 Reinforced hollow masonry some panels to increase flexural strength.

5 150 mm reinforced sprayed concrete The ground level was approximately 1


metre below ground floor level, and
6 150 mm reinforced concrete the original wall construction in this
area consisted of mass concrete in
In spite of its relatively low excess of 300 mm thick and generally
place in the above ranking, 150 mm 600 mm thick. Hence no tying of walls
reinforced sprayed concrete was selected to a diaphragm at ground floor level was
for all walls. This was influenced made but the sprayed concrete continued
by the fact that more experience was to footing level. Transfer of seismic
locally available for using this method load into existing foundations was
than for the other solutions. Reasons achieved by epoxying bars into existing
for rejecting the other possibilities concrete. A similar means was used
were: to transmit shear into the new walls at
first floor and roof levels. Fig 3 gives
insufficient laboratory experience details. Performance and proof testing
with GRC plaster was available at was required of epoxied bars.
that stage, and, in any event, we
were not prepared to use a thin As mentioned earlier, tying of
structural plaster as a shear cum brick walls at first floor and roof
face load resisting system when only level was achieved by an overlay of
one face could realistically be particle-board to floor and ceiling.
plastered. This would apply in In the case of the first floor level, two
the case of external walls where 12 mm sheets were overlaid, staggered
the exterior brickwork appearance relative to each other, and glued
had to be retained; together with a gap-filling adhesive,
Expandite WB. Only one layer was used
the steel braced frame was only at roof level, and there, internal
seriously considered as a replacement joints were made by gluing and screwing
for the transverse (east-west) non- to blocking - Figure 4 gives details.
gravity load bearing walls. If used
alongside brickwork, there would The means of connection to ring beam/
have remained the problem of protecting brickwork at the perimeter of diaphragm
the adjacent wall against face sections was more difficult. In the
loading. In addition, the difference end, 20 m cuphead bolts at varying
in stiffness between frame and centres, but as close as 100 mm, were
brickwall could have reduced the designed to provide a load path via
threshold of damage under in-plane steel angles bolted into the ring beam
loading. The solution was not or sprayed concrete. Bearing strength
used because it was decided to retain of the structural particle-board is
the same strengthening method for critical and no published information
all walls; was available. An onsite modification
resulted in a third 12 mm layer being
in the case of the post-tensioning glued as an edge strip to allow
solution, although we understood countersinking of the bolt heads with
that vertical holes through several no loss of bearing strength. The
metres of brickwork could be drilled countersunk head was also surrounded
with precision, we were concerned by epoxy. Figure 5 shows typical
about loss of prestress due to details.
creep in the medium to long term.
More research is needed in this An area of particular uncertainty
area, but the concern seems justified during design was the question of protection
in the case of old brickwork; of veneer, against outwards collapse.
Examination on site during the design
reinforced hollow masonry was stage indicated that the cavity behind
considered for the same locations parts of the veneer had been mortared
(east-west walls) as the steel up and that there was effectively no
braced frame and as replacement for adhesion between structural brick
1 f

existing brickwork. It was not and veneer in such instances. In


used in the end in order to retain addition, although pointed with a cement
one strengthening method for all walls. mix, the mortar to veneer was generally
sand-lime only. Some butterfly ties
Figure 2 shows the floor layout and were present but their frequency was not
the extent of wall treatment for the known. It was decided that the expense
reinforced concrete/sprayed concrete of tying the veneer to structural brick
solution used. The tender documents through additional ties was not
did not rule out the possibility of warranted; this was in part influenced by
conventional reinforced concrete being the fact that the main walkway outside
offered. However , the successful the building (the eastern side - see Fig 1)
tenderer (Fletcher Construction) offered was separated from the building exterior
sprayed concrete. by a fairly extensive planted area. It
was also decided to give some protection
Analysis of the system of walls to the veneer by grouting the cavity
considered them as deep membered frames where it existed. The grout contained
1936 BLOCK

Legend
© WALL TO BE DEMOLISHED AND R E P L A C E D WITH 150mm R.C. WALL
(b) 150mm R.C. WALL A D D E D TO EXISTING WALLS. P L A S T E R TO BE REMOVED FROM EXISTING WALLS.
(R) A S FOR B EXCEPT 265mm R.C. WALL AT 1 s f
FLOOR
© EXISTING GR'D FLOOR W A L L S CUT BACK 150mm FROM B E A M FACE. FIRST FLOOR WALLS CUT BACK
115mm. REINSTATE WITH 150mm R.C. WALL.
(3) EXISTING GR'D FLOOR WALLS CUT B A C K 115mm FROM BEAM FACE. NO CUT B A C K AT FIRST FLOOR.
REINSTATE WITH 150mm R.C. WALL. PLASTER TO BE REMOVED AT FIRST FLOOR.
© WALLS TO BE DEMOLISHED AND REPLACED WITH TIMBER AT FIRST FLOOR ONLY.
61

an expansive admixture to enhance bond, into the ring beam, because the
the cavity was flooded beforehand to horizontal reinforcement in the beams
saturate brickwork and a careful watch behind which the vertical dowels would
kept for signs of movement or cracking have to pass could not be located.
in the veneer during the grouting
operation. In addition, we were worried As mentioned, grouting of the
about the possibility of efflorescence cavity did not give rise to the
but, encouraged by the experience problems feared, notwithstanding the
at Hastings Boys High S c h o o l ^ , we
1
weakness and brittleness evident in
decided to proceed. In the event, the bricks. However, the grout did
no movement of the veneer brickwork not fill all the cavity available, and
was observed and to date efflorescence in the end, the system of check ports
has only appeared as a fine dusting in specified in the documents was amended.
some areas. The bottom two courses was not effectively
filled due to the presence of mortar
CONSTRUCTION: droppings from the time of original
construction. During remedial work
Core tests of sprayed concrete showed in one area to these bottom courses,
its variability, not only in terms of it was apparent that excellent adhesion
strength (core strength of 20 MPa at of the grouted cavity to brick above
28 days was specified) but also in terms these courses had been achieved.
of evident lack of bond to the wire
reinforcing mesh on occasions. Cylinder The laying of the particle-board
strengths of core samples taken from diaphragms proceeded quite satisfactorily.
separate test panels consistently However, sheets tended to be cut in
exceeded the specified strength. However, order to abut the adjacent inner sheet,
strengths of a limited number of cores giving rise to a gap at the junction
taken from the permanent works were less with brickwork and loss of bolt edge
encouraging: here the 28 day strength distance. The lack of squareness
generally ranged from 15 - 28 MPa with of room spaces also often resulted in
most test results in the 20 - 25 MPa range. one edge losing significant edge
A value as low as 9 MPa was recorded. distance, particularly at ceiling level.
Figure 8 shows the edge detail.
Of particular concern was the
evident lack of compaction over the SUMMARY AND OBSERVATIONS;
depth of the 400 mm floor joist at first
floor level. It is in this region that 1 In a low-rise building of this type,
both new gravity support to joists and the achieving of a level of seismic
lateral support to faceloaded walls strength in accordance with the
exist. Considerable remedial work was current loadings code for new
necessary here. buildings (NZS 4203 :1976) is not
onerous.
Details of trimming reinforcement
were originally set the same as is norm- 2 Half of the total cost of the
ally used for reinforced concrete but contract was consumed in non-
were changed on site to reduce the structural areas. Consideration
possibility of shadowing effects. In needs to be given to reducing the
addition, the specified D10 ties epoxied non-structural component; alternatively,
to structural brickwork were changed to it should be recognised that complete
an equivalent area of R6 ties because of refurbishing is being achieved
the greater ease of drilling a smaller together with an increase in
hole in often brittle brickwork. Figure seismic strength to a level of
6 shows a typical area of wall. loading applicable to modern
buildings.
It was found that supervision of the
epoxying operation was critical: 3 Although the level of risk to
initial fixings produced without super- life is greatly reduced to approx-
vision had virtually no strength. However, imate that applying to new buildings
given proper supervision, results were following the addition of strengthen-
such that bar yield was achieved in ing measures such as that described
performance tests, and proof tests were above, it is unlikely that the
also satisfactory. Figure 7 shows the susceptibility of the strengthened
range of results. Unfortunately, due brickwork to damage has been
to a lack of readily available equipment, reduced to the level of that of a
continuous proof testing (a minimum of new building because of the
5% of fixings were required to be retention of brittle materials,
tested by the specification) was not carried particularly the exterior veneer.
out. It has been hoped that a simple However, the degree of damageability
fulcrum arrangement might have been compared to that of a new building
possible, but this was not feasible is simply not known.
and so a hydraulic jack with direct
pull was used, with the crew being 4 There is a need for development
brought in from outside the city. of methods of connection of timber
diaphragms to surrounding brickwork.
The contract drawings showed vertical While such diaphragms are economically
dowels passing right through the first much more attractive than steel,
floor ring beams and thereby connecting it is evident that the method of
adjacent levels of sprayed concrete. connection used in this project
However, this was changed on site to could be refined through laboratory
L-bars (Figure 3) epoxied horizontally testing.
62

Epoxy connections of reinforcing


bars is extremely workmanship and
supervision dependent and a situation
of no strength is all too easily
achieved. Site testing is essential.

Sprayed concrete is very quickly


applied but the quality of the
product deteriorates rapidly in
areas where the compactive effort
of the application is absorbed.
Conventional cast in situ reinforced
concrete must be used in such
locations.

REFERENCES:
I.J. Garrett: "Hastings Boys' High D10 D R I L L E D A N D
School Administration Buildings, EPOXIED 100mm
Hastings , Hawke s Bay, New Zealand:
1
C E N T R A L IN WALL.
Case Studies : Earthquake Risk
Buildings" Bulletin N.Z. National
Society for Earthquake Engineering,
Vol. 16, No. 1, March 1983.
h — 665 M
P.R. Boardman: "Restoration of Old M E S H E.F.
Auckland Customhouse : Case Studies :
Earthquake Risk Buildings": Bulletin
N.Z. National Society for Earthquake
Engineering, Vol. 16, No. 1, March
1983.

D10 D R I L L E D A N D
EPOXIED, ALTERNATING.

665 M
M E S H E.F.

665 M
M E S H E.F.

-D10 DOWEL D R I L L E D
AND E P O X I E D , A N G L E
AT 15° A P P R O X .

B-B

FIGURE 3
63

3-150 x 7 5 L'G N A I L S
1st FUR CORRIDOR
2 - 5 0 x 40 L'G. FOR 25 ,i,25
ROOF, CORRIDOR &
CLASSROOMS.*

OMIT AT
ROOF. 150 x 50 M16 BOLTS
150 x 50 AT 5 0 0 C R S .
JOISTS
BETWEEN JOISTS 100x50
EACH SIDE
A-A * 4 - 8 8 0 x 7 5 L'G
S C R E W S AT 100 C R S .
1st FL'R
1st F L R C L A S S R O O M S .
& ROOF
T Y P I C A L EDGE DETAILS

2 S H E E T S OF 12 mm THICK ' S T R U C T E X '


E X I S T I N G TONGUE & GROOVE FLOORING.

FIGURE U

R16 AT 900 CRS. 16mm CUP H E A D


T H R E A D E D 35mm COACH BOLTS
BOTH ENDS AT 300mm C R S .
100 x 1 0 0 x 1 0 L
CONTINUOUS.

400x50
JOIST 2 0 0 x 50
D16-900 % JOIST.
THREADED 35 m m -
100 x 1 0 0 x 1 0 L
CONTINUOUS.
8mm x 50 LG
COACH S C R E W
16mm T R U B O L T EACH JOIST.

FIGURE 5

FIGURE 7 TWO E P O X I E D B A R T E S T S P E C I M E N S
FIGURE 6 T Y P I C A L WALL JUNCTION
UPPER S P E C I M E N HAD ADEQUATE
REINFORCEMENT.
S T R E N G T H , THE LOWER HAD
INSUFFICIENT E P O X Y S T R E N G T H .
DIAPHRAGM VIEWED FROM BELOW.

You might also like