Professional Documents
Culture Documents
Earthquake Risk Buildings
Earthquake Risk Buildings
Earthquake Risk Buildings
eaves level. Floors and roof trusses are Design proceeded first of all using
of timber. full code in both directions -
1 GRC plaster coat to two faces and, in general, two layers of 665 HRC
mesh were used, staggered by 7 5 mm to
2 Steel braced frame minimise shadowing from the process of
applying sprayed concrete. Apart from
3 Post-tensioned brickwork trimmers around openings, additional bars
of deformed steel were used at ends of
4 Reinforced hollow masonry some panels to increase flexural strength.
Legend
© WALL TO BE DEMOLISHED AND R E P L A C E D WITH 150mm R.C. WALL
(b) 150mm R.C. WALL A D D E D TO EXISTING WALLS. P L A S T E R TO BE REMOVED FROM EXISTING WALLS.
(R) A S FOR B EXCEPT 265mm R.C. WALL AT 1 s f
FLOOR
© EXISTING GR'D FLOOR W A L L S CUT BACK 150mm FROM B E A M FACE. FIRST FLOOR WALLS CUT BACK
115mm. REINSTATE WITH 150mm R.C. WALL.
(3) EXISTING GR'D FLOOR WALLS CUT B A C K 115mm FROM BEAM FACE. NO CUT B A C K AT FIRST FLOOR.
REINSTATE WITH 150mm R.C. WALL. PLASTER TO BE REMOVED AT FIRST FLOOR.
© WALLS TO BE DEMOLISHED AND REPLACED WITH TIMBER AT FIRST FLOOR ONLY.
61
an expansive admixture to enhance bond, into the ring beam, because the
the cavity was flooded beforehand to horizontal reinforcement in the beams
saturate brickwork and a careful watch behind which the vertical dowels would
kept for signs of movement or cracking have to pass could not be located.
in the veneer during the grouting
operation. In addition, we were worried As mentioned, grouting of the
about the possibility of efflorescence cavity did not give rise to the
but, encouraged by the experience problems feared, notwithstanding the
at Hastings Boys High S c h o o l ^ , we
1
weakness and brittleness evident in
decided to proceed. In the event, the bricks. However, the grout did
no movement of the veneer brickwork not fill all the cavity available, and
was observed and to date efflorescence in the end, the system of check ports
has only appeared as a fine dusting in specified in the documents was amended.
some areas. The bottom two courses was not effectively
filled due to the presence of mortar
CONSTRUCTION: droppings from the time of original
construction. During remedial work
Core tests of sprayed concrete showed in one area to these bottom courses,
its variability, not only in terms of it was apparent that excellent adhesion
strength (core strength of 20 MPa at of the grouted cavity to brick above
28 days was specified) but also in terms these courses had been achieved.
of evident lack of bond to the wire
reinforcing mesh on occasions. Cylinder The laying of the particle-board
strengths of core samples taken from diaphragms proceeded quite satisfactorily.
separate test panels consistently However, sheets tended to be cut in
exceeded the specified strength. However, order to abut the adjacent inner sheet,
strengths of a limited number of cores giving rise to a gap at the junction
taken from the permanent works were less with brickwork and loss of bolt edge
encouraging: here the 28 day strength distance. The lack of squareness
generally ranged from 15 - 28 MPa with of room spaces also often resulted in
most test results in the 20 - 25 MPa range. one edge losing significant edge
A value as low as 9 MPa was recorded. distance, particularly at ceiling level.
Figure 8 shows the edge detail.
Of particular concern was the
evident lack of compaction over the SUMMARY AND OBSERVATIONS;
depth of the 400 mm floor joist at first
floor level. It is in this region that 1 In a low-rise building of this type,
both new gravity support to joists and the achieving of a level of seismic
lateral support to faceloaded walls strength in accordance with the
exist. Considerable remedial work was current loadings code for new
necessary here. buildings (NZS 4203 :1976) is not
onerous.
Details of trimming reinforcement
were originally set the same as is norm- 2 Half of the total cost of the
ally used for reinforced concrete but contract was consumed in non-
were changed on site to reduce the structural areas. Consideration
possibility of shadowing effects. In needs to be given to reducing the
addition, the specified D10 ties epoxied non-structural component; alternatively,
to structural brickwork were changed to it should be recognised that complete
an equivalent area of R6 ties because of refurbishing is being achieved
the greater ease of drilling a smaller together with an increase in
hole in often brittle brickwork. Figure seismic strength to a level of
6 shows a typical area of wall. loading applicable to modern
buildings.
It was found that supervision of the
epoxying operation was critical: 3 Although the level of risk to
initial fixings produced without super- life is greatly reduced to approx-
vision had virtually no strength. However, imate that applying to new buildings
given proper supervision, results were following the addition of strengthen-
such that bar yield was achieved in ing measures such as that described
performance tests, and proof tests were above, it is unlikely that the
also satisfactory. Figure 7 shows the susceptibility of the strengthened
range of results. Unfortunately, due brickwork to damage has been
to a lack of readily available equipment, reduced to the level of that of a
continuous proof testing (a minimum of new building because of the
5% of fixings were required to be retention of brittle materials,
tested by the specification) was not carried particularly the exterior veneer.
out. It has been hoped that a simple However, the degree of damageability
fulcrum arrangement might have been compared to that of a new building
possible, but this was not feasible is simply not known.
and so a hydraulic jack with direct
pull was used, with the crew being 4 There is a need for development
brought in from outside the city. of methods of connection of timber
diaphragms to surrounding brickwork.
The contract drawings showed vertical While such diaphragms are economically
dowels passing right through the first much more attractive than steel,
floor ring beams and thereby connecting it is evident that the method of
adjacent levels of sprayed concrete. connection used in this project
However, this was changed on site to could be refined through laboratory
L-bars (Figure 3) epoxied horizontally testing.
62
REFERENCES:
I.J. Garrett: "Hastings Boys' High D10 D R I L L E D A N D
School Administration Buildings, EPOXIED 100mm
Hastings , Hawke s Bay, New Zealand:
1
C E N T R A L IN WALL.
Case Studies : Earthquake Risk
Buildings" Bulletin N.Z. National
Society for Earthquake Engineering,
Vol. 16, No. 1, March 1983.
h — 665 M
P.R. Boardman: "Restoration of Old M E S H E.F.
Auckland Customhouse : Case Studies :
Earthquake Risk Buildings": Bulletin
N.Z. National Society for Earthquake
Engineering, Vol. 16, No. 1, March
1983.
D10 D R I L L E D A N D
EPOXIED, ALTERNATING.
665 M
M E S H E.F.
665 M
M E S H E.F.
-D10 DOWEL D R I L L E D
AND E P O X I E D , A N G L E
AT 15° A P P R O X .
B-B
FIGURE 3
63
3-150 x 7 5 L'G N A I L S
1st FUR CORRIDOR
2 - 5 0 x 40 L'G. FOR 25 ,i,25
ROOF, CORRIDOR &
CLASSROOMS.*
OMIT AT
ROOF. 150 x 50 M16 BOLTS
150 x 50 AT 5 0 0 C R S .
JOISTS
BETWEEN JOISTS 100x50
EACH SIDE
A-A * 4 - 8 8 0 x 7 5 L'G
S C R E W S AT 100 C R S .
1st FL'R
1st F L R C L A S S R O O M S .
& ROOF
T Y P I C A L EDGE DETAILS
FIGURE U
400x50
JOIST 2 0 0 x 50
D16-900 % JOIST.
THREADED 35 m m -
100 x 1 0 0 x 1 0 L
CONTINUOUS.
8mm x 50 LG
COACH S C R E W
16mm T R U B O L T EACH JOIST.
FIGURE 5
FIGURE 7 TWO E P O X I E D B A R T E S T S P E C I M E N S
FIGURE 6 T Y P I C A L WALL JUNCTION
UPPER S P E C I M E N HAD ADEQUATE
REINFORCEMENT.
S T R E N G T H , THE LOWER HAD
INSUFFICIENT E P O X Y S T R E N G T H .
DIAPHRAGM VIEWED FROM BELOW.