1 Chipped out set mortar along the line of masonry work
2 Layout of 1st layer completed & certified. 3 Hacking to RCC columns & beam bottom where masonry is butting. 4 Openings for door, windows, AC units & other cutout etc. 5 Erection of doors, windows with necessary hold fasts. 6 Racking of joints and surface cleaning. 7 Verticality of walls & corners. 8 Thickness of joints as per specification. 9 Patli's in SMC-M15 10 Proportion of mix as per specification. 11 Wetting of Bricks before use. 12 Availability of measurement box [Farmas] for mortar to mix.