Professional Documents
Culture Documents
Arbitration - Set 3
Arbitration - Set 3
211504 construction contracts entered into by parties, and whether such disputes arise before or after the
completion of the contracts. Accordingly, the execution of the contracts and the effect of the agreement
FEDERAL BUILDERS, INC., Petitioner vs POWER FACTORS, INC., Respondent to submit to arbitration are different matters, and the signing or non-signing of one does not necessarily
affect the other. In other words, the formalities of the contract have nothing to do with the jurisdiction
Construction Industry Arbitration Commission; Jurisdiction; Under the Construction Industry of the CIAC.
Arbitration Commission Revised Rules of Procedure Governing Construction
Arbitration (CIAC Revised Rules), all that is required for the CIAC to acquire jurisdiction is for the Civil Law; Contracts; A contract does not need to be in writing in order to be obligatory and
parties of any construction contract to agree to submit their dispute to arbitration.—The need to effective unless the law specifically requires so.—Under Article 1318 of the Civil Code, a valid
establish a proper arbitral machinery to settle disputes expeditiously was recognized by the contract should have the following essential elements, namely: (a) consent of the contracting parties;
Government in order to promote and maintain the development of the country’s construction industry. (b) object certain that is the subject matter of the contract; and (c) cause or consideration. Moreover, a
With such recognition came the creation of the CIAC through Executive Order No. 1008 (E.O. No. contract does not need to be in writing in order to be obligatory and effective unless the law
1008), also known as The Construction Industry Arbitration Law. Section 4 of E.O. No. 1008 specifically requires so. Pursuant to Article 1356 and Article 1357 of the Civil Code, contracts shall be
provides: Sec. 4. Jurisdiction.—The CIAC shall have original and exclusive jurisdiction over disputes obligatory in whatever form they may have been entered into, provided that all the essential requisites
arising from, or connected with, contracts entered into by parties involved in construction in the for their validity are present. Indeed, there was a contract between Federal and Power even if the
Philippines, whether the dispute arises before or after the completion of the contract, or after the Contract of Service was unsigned. Such contract was obligatory and binding between them by virtue of
abandonment or breach thereof. These disputes may involve government or private contracts. For the all the essential elements for a valid contract being present.
Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary
arbitration. x x x Under the CIAC Revised Rules of Procedure Governing Construction Construction Industry Arbitration Commission; Jurisdiction; Although the agreement to submit
Arbitration (CIAC Revised Rules), all that is required for the CIAC to acquire jurisdiction is for the to arbitration has been expressly required to be in writing and signed by the parties therein by Section
parties of any construction contract to agree to submit their dispute to arbitration. Also, Section 2.3 of 4 of Republic Act (RA) No. 876 (Arbitration Law), the requirement is conspicuously absent from the
the CIAC Revised Rules states that the agreement may be reflected in an arbitration clause in their Construction Industry Arbitration Commission (CIAC) Revised Rules, which even expressly allows
contract or by subsequently agreeing to submit their dispute to voluntary arbitration. The such agreement not to be signed by the parties therein.—The agreement contemplated in the
CIAC Revised Rules clarifies, however, that the agreement of the parties to submit their dispute to CIAC Revised Rules to vest jurisdiction of the CIAC over the parties’ dispute is not necessarily an
arbitration need not be signed or be formally agreed upon in the contract because it can also be in the arbitration clause to be contained only in a signed and finalized construction contract. The agreement
form of other modes of communication in writing. could also be in a separate agreement, or any other form of written communication, as long as their
intent to submit their dispute to arbitration is clear. The fact that a contract was signed by both parties
Same; Same; Executive Order (EO) No. 1008 emphasizes that the modes of voluntary dispute has nothing to do with the jurisdiction of the CIAC, and this is the explanation why the CIAC Revised
resolution like arbitration are always preferred because they settle disputes in a speedy and amicable Rules itself expressly provides that the written communication or agreement need not be signed by the
manner.—The liberal application of procedural rules as to the form by which the agreement is parties. Although the agreement to submit to arbitration has been expressly required to be in writing
embodied is the objective of the CIAC Revised Rules. Such liberality conforms to the letter and spirit and signed by the parties therein by Section 4 of Republic Act No. 876 (Arbitration Law), the
of E.O. No. 1008 itself which emphasizes that the modes of voluntary dispute resolution like requirement is conspicuously absent from the CIAC Revised Rules, which even expressly allows such
arbitration are always preferred because they settle disputes in a speedy and amicable manner. They agreement not to be signed by the parties therein. Brushing aside the obvious contractual agreement in
likewise help in alleviating or unclogging the judicial dockets. Verily, E.O. No. 1008 recognizes that this case warranting the submission to arbitration is surely a step backward. Consistent with the policy
the expeditious resolution of construction disputes will promote a healthy partnership between the of encouraging alternative dispute resolution methods, therefore, any doubt should be resolved in favor
Government and the private sector as well as aid in the continuous growth of the country considering of arbitration. In this connection, the CA correctly observed that the act of Atty. Albano in manifesting
that the construction industry provides employment to a large segment of the national labor force aside that Federal had agreed to the form of arbitration was unnecessary and inconsequential considering the
from its being a leading contributor to the gross national product. recognition of the value of the Contract of Service despite its being an unsigned draft.
Same; Same; Construction Disputes; Section 2.1, Rule 2 of the Construction Industry Arbitration DECISION
Commission (CIAC) Revised Rules particularly specifies that the CIAC has original and exclusive
jurisdiction over construction disputes, whether such disputes arise from or are merely connected BERSAMIN, J.:
with the construction contracts entered into by parties, and whether such disputes
arise before or after the completion of the contracts.—Worthy to note is that the jurisdiction of the An agreement to submit to voluntary arbitration for purposes of vesting jurisdiction over a
CIAC is over the dispute, not over the contract between the parties. Section 2.1, Rule 2 of the construction dispute in the Construction Industry Arbitration Commission (CIAC) need not be
CIAC Revised Rules particularly specifies that the CIAC has original and exclusive jurisdiction contained in the construction contract, or be signed by the parties. It is enough that the
over construction disputes, whether such disputes arise from or are merely connected with the agreement be in writing.
On November 20, 2009, Atty. Vivencio Albano, the counsel of Federal, submitted a letter to WHEREFORE, the CIAC Final Award dated 12 May 20l0 in CIAC Case No. 31-2009 is
the CIAC manifesting that Federal agreed to arbitration and sought an extension of 15 days hereby AFFIRMED with MODIFICATION. As modified, FEDERAL BUILDERS, INC. is
to file its answer, which request the CIAC granted. ordered to pay POWER FACTORS, INC. the following:
On December 16, 2009, Atty. Albano filed his withdrawal of appearance stating that Federal 1. Unpaid balance on the original contract ₱4,276,614.75;
had meanwhile engaged another counsel.6
2. Unpaid balance on change orders 2,864,113.32;
Federal, represented by new counsel (Domingo, Dizon, Leonardo and Rodillas Law Office), 3. Attorney's Fees 250,000.00;
moved to dismiss the case on the ground that CIAC had no jurisdiction over the case
inasmuch as the Contract of Service between Federal and Power had been a mere draft that 4. Cost of Arbitration 149,503.86;
was never finalized or signed by the parties. Federal contended that in the absence of the
agreement for arbitration, the CIAC had no jurisdiction to hear and decide the case. 7
The interest to be imposed on the net award (unpaid balance on the original contract and
change order) amounting to P.7, 140,728.07 awarded to POWER FACTORS INC. shall be
On February 8, 2010, the CIAC issued an order setting the case for hearing, and directing six (6%) per annum, reckoned from 4 July 2006 until this Decision becomes final and
that Federal's motion to dismiss be resolved after the reception of evidence of the parties. 8 executory. Further, the total award due to POWER FACTORS INC. shall be subjected to an
15. ARBITRATION COMMITTEE -All disputes, controversies or differences, which may arise 2. Amounts as modified by the CA are correct
between the Parties herein, out of or in relation to or in connection with this Agreement, or for
breach thereof shall be settled by the Construction Industry Arbitration Commission (CIAC)
We find no reversible error regarding the amounts as modified by the CA. Power did not
which shall have original and exclusive jurisdiction over the aforementioned disputes. 20
sufficiently establish that the change or increase of the cost of materials and labor was to be
separately determined and approved by both parties as provided under Article 1724 of
With the parties having no issues on the provisions or parts of the Contract of Service other the Civil Code. As such, Federal should not be held liable for the labor cost escalation.
than that pertaining to the downpayment that Federal was supposed to pay, Federal could not
validly insist on the lack of a contract in order to defeat the jurisdiction of the CIAC. As earlier
WHEREFORE, the Court AFFIRMS the decision promulgated on August 12, 2013;
pointed out, the CIAC Revised Rules specifically allows any written mode of communication
and ORDERS the petitioner to pay the costs of suit.
to show the parties' intent or agreement to submit to arbitration their present or future
disputes arising from or connected with their contract.
SO ORDERED.
The CIAC and the CA both found that the parties had disagreed on the amount of the
downpayment.1âwphi1 On its part, Power indicated after receiving and reviewing the draft of
NATIONAL TRANSMISSION CORPORATION, Petitioner, vs. ALPHAOMEGA Assailed in this petition for review on certiorari 1 are the Decision2 dated April 8, 2008 and the
INTEGRATED CORPORATION, Respondent. Resolution3 dated August 27, 2008 of the Court of Appeals (CA) in CA-G.R. SP No. 99454
affirming with modification the Final Award4 of the Construction Industry Arbitration
Remedial Law; Civil Procedure; Section 1, Rule 45 of the Rules of Court provides that a petition Commission (CIAC) Arbitral Tribunal in favor of respondent Alphaomega Integrated
for review on certiorari under the said rule, as in this case, “shall raise only questions of law which Corporation (AIC) by increasing petitioner National· Transmission Corporation's (TRANSCO)
must be distinctly set forth.”—TRANSCO seeks through this petition a recalibration of the liability from Pl 7,495,117.44 to Pl 8,896,673.31.
evidence presented before the CIAC Arbitral Tribunal, insisting that AIC is not entitled to any
damages not only because it had previously waived all claims for standby fees in case of project delays The Facts
but had eventually failed to perform the workable portions of the projects. This is evidently a factual
question which cannot be the proper subject of the present petition. Section 1, Rule 45 of the Rules of AIC, a duly licensed transmission line contractor, participated in the public biddings
Court provides that a petition for review on certiorari under the said rule, as in this case, “shall raise conducted by TRANSCO and was awarded six ( 6) government construction projects,
only questions of law which must be distinctly set forth.” Thus, absent any of the existing exceptions namely: (a) Contract .for the Construction & Erection of Batangas Transmission
impelling the contrary, the Court is, as general rule, precluded from delving on factual determinations, Reinforcement Project Schedule III (BTRP Schedule III Project); (b) Contract for the
as what TRANSCO essentially seeks in this case. Construction & Erection of Batangas Transmission Reinforcement Project Schedule I (BTRP
Schedule I Project); (c) Contract for the Construction,Erection & Installation of 230 KV and 69
Same; Same; It is well-settled that findings of fact of quasi-judicial bodies, which have acquired KV S/S Equipment and Various Facilities for Makban Substation under the Batangas
expertise because their jurisdiction is confined to specific matters, are generally accorded not only Transmission Reinforcement Project (Schedule II) (Makban Substation Project); (d) Contract
respect, but also finality, especially when affirmed by the Court of Appeals (CA).—The Court finds no for the Construction, Erection & Installation of 138 & 69 KV S/S Equipment for Bacolod
reason to disturb the factual findings of the CIAC Arbitral Tribunal on the matter of AIC’s entitlement Substation under the Negros III-Panay III Substation Projects (Schedule II) (Bacolod
to damages which the CA affirmed as being well supported by evidence and properly referred to in the Substation Project); (e) Contract for the Construction, Erection & Installation of 138 & 69 KV
record. It is well-settled that findings of fact of quasi-judicial bodies, which have acquired expertise Substation Equipment for the New Bunawan Switching Station Project (Bunawan Substation
because their jurisdiction is confined to specific matters, are generally accorded not only respect, but Project); and (f) Contract for the Construction, Erection & Installation of 138 and 69 KV
also finality, especially when affirmed by the CA. The CIAC possesses that required expertise in the Substation Equipment for Quiot Substation Project (Quiot Substation Project). 5
field of construction arbitration and the factual findings of its construction arbitrators are final and
conclusive, not reviewable by this Court on appeal. In the course of the performance ofthe contracts, AIC encountered difficulties and incurred
losses allegedly due to TRANSCO’s breach of their contracts, prompting it to surrender the
Same; Same; It is well-settled that no relief can be granted a party who does not appeal and that projects to TRANSCO under protest. In accordance with an express stipulation in the
a party who did not appeal the decision may not obtain any affirmative relief from the appellate court contracts that disagreements shall be settled by the parties through arbitration before the
other than what he had obtained from the lower court, if any, whose decision is brought up on appeal. CIAC, AIC submitted a request for arbitration before the CIAC on August 28, 2006, and,
—It must be emphasized that the petition for review before the CA was filed by TRANSCO. AIC thereafter, filed an Amended Complaint against TRANSCO alleging that the latter breached
never elevated before the courts the matter concerning the discrepancy between the amount of the the contracts by its failure to: (a) furnish the required Detailed Engineering; (b) arrange a well-
award stated in the body of the Final Award and the total award shown in its dispositive portion. The established right-of-way to the project areas; (c) secure the necessary permits and
issue was touched upon by the CA only after AIC raised the same through its Comment (With Motion clearances from the concerned local government units (LGUs); (d) ensure a continuous
to Acknowledge Actual Amount of Award) to TRANSCO’s petition for review. The CA should not supply of construction materials; and (e) carry out AIC’s requests for power shut down. The
have modified the amount of the award to favor AIC because it is well-settled that no relief can be aforementioned transgressions resultedin protracted delays and contract suspensions for
granted a party who does not appeal and that a party who did not appeal the decision may not obtain each project,6 as follows:
any affirmative relief from the appellate court other than what he had obtained from the lower court, if
any, whose decision is brought up on appeal. The disposition, as stated in the fallo of the CIAC
Arbitral Tribunal’s Final Award, should therefore stand. Contract Original Duration of Transco- Percentage (%) of Original
Contract Approved Suspension Contract Duration
DECISION Duration and/or Extensions
1) BTRP Schedule III 560 days 711 days 127%
xxxx
Failure to file said motion would consequentlyrender the award final and executory under
Section 18. 1 of the same rules, viz.:
Section 18.1 Execution of Award – A final arbitral award shall become executory upon the
lapse of fifteen (15) days from receipt thereof by the parties.1âwphi1
AIC admitted that it had ample time to file a motion for correction of the Final Award but
claimed to have purposely sat on its right to seek correction supposedly as a strategic move
against TRANSCO34 and, instead, filed with the CIAC Arbitral Tribunal on June 13, 2007 a
"Motion for Issuance of Writ of Execution for the Total Amount of 18,967,318.49 as Embodied
in the Final Award."35 The Arbitral Tribunal eventually denied AIC’s aforesaid motion for
execution because, despite its merit, the Arbitral Tribunal could not disregard the time-
Volume II: Technical Specifications for the Architectural, Structural, Mechanical, Plumbing, CECON offered the lowest tender amount. However, ACI did not award the project to any
Fire Protection and Electrical Works; and bidder, even as the validity of CECON's proposal lapsed on November 29, 2002. ACI only
subsequently informed CECON that the contract was being awarded to it. ACI elected to
Addenda Nos. 1, 2, 3, and 4 relating to modifications to portions of the Tender Documents. inform CECON verbally and not in writing.
[11]
In a phone call on December 7, 2002, ACI instructed CECON to proceed with excavation
The Tender Documents described the project's contract sum to be a "lump sum" or "lump works on the project. ACI, however, was unable to deliver to CECON the entire project site.
sum fixed price" and restricted cost adjustments, as follows: Only half, identified as the Malvar-to-Roxas portion, was immediately available. The other
half, identified as the Roxas to-Coliseum portion, was delivered only about five (5) months
6 TYPE OF CONTRACT later.
6.1 This is a Lump Sum Contract and the price is a fixed price not subject to measurement or As the details of the project had yet to be finalized, ACI and CECON pursued further
recalculation should the actual quantities of work and materials differ from any estimate negotiations. ACI and CECON subsequently agreed to include in the project the construction
available at the time of contracting, except in regard to Cost-Bearing Changes which may be of an office tower atop the portion identified as Part A of the project. This escalated CECON's
ordered by the Owner which shall be valued under the terms of the Contract in accordance project cost to P1,582,810,525.00.
with the Schedule of Rates, and with regard to the Value Engineering Proposals under
Clause 27. The Contract Sum shall not be adjusted for changes in the cost of labour, After further negotiations, the project cost was again adjusted to P1,613,615,244.00. Still
materials or other matters.[12] later, CECON extended to ACI a P73,615,244.00 discount, thereby"reducing its offered
project cost to P1,540,000.00.
TENDER AND CONTRACT
Despite these developments, ACI still failed to formally award the project to CECON. The
Fixed Price Contract parties had yet to execute a formal contract. This prompted CECON to write a letter to ACI,
dated December 27, 2002,[20] emphasizing that the project cost quoted to ACI was "based
The Contract Sum payable to the Contactor is a Lump Sum Fixed Price and will not be upon the prices prevailing at December 26, 2002" price levels.
subject to adjustment, save only where expressly provided for within the Contract Documents
and the Form of Agreement. By January 2003 and with the project yet to be formally awarded, the prices of steel products
had increased by 5% and of cement by P5.00 per bag. On January 8, 2003, CECON again
The Contract Sum shall not be subject to any adjustment "in respect of rise and fall in the cost wrote ACI notifying it of these increasing costs and specifically stating that further delays may
of materials[,] labor, plant, equipment, exchange rates or any other matters affecting the cost affect the contract sum.
of execution of Contract, save only where expressly provided for within the Contract
Documents or the Form of Agreement. Still without a formal award, CECON again wrote to ACI on January 21, 2003[23] indicating
cost and time adjustments to its original proposal. Specifically, it referred to an 11.52%
The Contract Sum shall further not be subject to any change in subsequent legislation, which increase for the cost of steel products, totalling P24,921,418.00 for the project; a P5.00
causes additional or reduced costs to the Contractor.[13] increase per bag of cement, totalling P3,698,540.00 for the project; and costs incurred
because of changes to the project's structural framing, totalling P26,011,460.00. The contract
The bidders' proposals for the project were submitted on August 30, 2002. These were based sum, therefore, needed to be increased to P1,594,631,418.00. CECON also specifically
on "design and construct" bidding.[14] stated that its tender relating to these adjusted prices were valid only until January 31, 2003,
as further price changes may be forthcoming. CECON emphasized that its steel supplier had
CECON submitted its bid, indicating a tender amount of P1,449,089,174.00. This amount was actually already advised it of a forthcoming 10% increase in steel prices by the first week of
inclusive of "both the act of designing the building and executing its construction." Its bid and February 2003. CECON further impressed upon ACI the need to adjust the 400 days allotted
tender were based on schematic drawings, i.e., conceptual designs and suppositions culled for the completion of the project.
from ACI's Tender Documents. CECON's proposal "specifically stated that its bid was valid
On June 2, 2003, ACI finally wrote a letter[27] to CECON indicating its acceptance of Second, instead of leaving it to CECON, ACI opted to purchase on its own certain pieces of
CECON's August 30, 2002 tender for an adjusted contract sum of P1,540,000.00 only: equipment-elevators, escalators, chillers, generator sets, indoor substations, cooling towers,
pumps, and tanks-which were to be installed in the project. This entailed "take-out costs"; that
Araneta Center, Inc. (ACI) hereby accepts the C-E Construction Corporation (CEC) tender is, the value of these pieces of equipment needed to be removed from the total amount due
dated August 30, 2002, submitted to ACI in the adjusted sum of One Billion Five Hundred to CECON. ACI considered a sum totalling P251,443,749.00 to have been removed from the
Forty Million Pesos Only (P1,540,000,000.00), which sum includes all additionally quoted and contract sum due to CECON. This amount of P251,443,749.00 was broken down, as follows:
accepted items within this acceptance letter and attachments, Appendix A, consisting of one
(1) page, and Appendix B, consisting of seven (7) pages plus attachments, which sum of One (a) For elevators/escalators, PhP106,000,000;
Billion Five Hundred Forty Million Pesos Only (P1,540,000,000.00) is inclusive of any
Government Customs Duty and Taxes including Value Added Tax (VAT) and Expanded (b) For Chillers, PhP41,152,900;
Value Added Tax (EVAD, and which sum is hereinafter referred to as the Contract Sum.[28]
(c) For Generator Sets, PhP53,040,000;
Item 4, Appendix B of this acceptance letter explicitly recognized that "all design except
support to excavation sites, is now by ACI."[29] It thereby confirmed that the parties were not (d) For Indoor Substation, PhP23,024,150;
bound by a design-and-construct agreement, as initially contemplated in ACI's June 2002
invitation, but by a construct-only agreement. The letter stated that "[CECON] acknowledge[s] (e) For Cooling Towers, PhP5,472,809; and
that a binding contract is now existing."[30] However, consistent with ACI's admitted changes,
it also expressed ACI's corresponding undertaking: "This notwithstanding, formal contract (f) For Pumps and Tanks, PhP22,753,890.[39]
documents embodying these positions will shortly be prepared and forwarded to you for
execution. CECON avers that in removing the sum of P251,443,749.00, ACI "simply deleted the amount
in the cost breakdown corresponding to each of the items taken out in the contract
Despite ACI's undertaking, no formal contract documents were delivered to CECON or documents."[40] ACI thereby disregarded that the corresponding stipulated costs pertained
otherwise executed between ACI and CECON. not only to the acquisition cost of these pieces of equipment but also to so-called "builder's
works" and other costs relating to their preparation for and installation in the project. Finding it
As it assumed the design aspect of the project, ACI issued to CECON the construction unjust to be performing auxiliary services practically for free, CECON proposed a reduction in
drawings for the project. Unlike schematics, these drawings specified "the kind of work to be the take-out costs claimed by ACI. It instead claimed P26,892,019.00 by way of
done and the kind of material to be used."[33] CECON laments, however, that "ACI issued compensation for the work that it rendered.
the construction drawings in piece-meal fashion at times of its own choosing."[34] From the
commencement of CECON's engagement until its turnover of the project to ACI, ACI issued With many changes to the project and ACI's delays in delivering drawings and specifications,
some 1,675 construction drawings. CECON emphasized that many of these drawings were CECON increasingly found itself unable to complete the project on January 10, 2004. It noted
partial and frequently pertained to revisions of prior items of work.[35] Of these drawings, that it had to file a total of 15 Requests for Time Extension from June 10, 2003 to December
more than 600 were issued by ACI well after the intended completion date of January 10, 15, 2003, all of which ACI failed to timely act on.
2004: Drawing No. 1040 was issued on January 12, 2004, and the latest, Drawing No. 1675,
was issued on November 26, 2004. Exasperated, CECON served notice upon ACI that it would avail of arbitration. On January
29, 2004, it filed with the CIAC its Request for Adjudication.[43] It prayed that a total sum of
Apart from shifting its arrangement with CECON from design-and-construct to construct only, P183,910,176.92 representing adjusted project costs be awarded in its favor.[44]
ACI introduced other changes to its arrangements with CECON. CECON underscored two (2)
of the most notable of these changes which impelled it to seek legal relief. On March 31, 2004, CECON and ACI filed before the CIAC a Joint Manifestation[45]
indicating that some issues between them had already been settled. Proceedings before the
In the meantime, CECON completed the project and turned over Gateway Mall to ACI.[48] It The CIAC Arbitral Tribunal noted that while ACI's initial invitation to bidders was for a lump-
had its blessing on November 26, 2004. sum design-and-construct arrangement, the way that events actually unfolded clearly
indicated a shift to an arrangement where the designs were contingent upon ACI itself.
As negotiations seemed futile, on December 29, 2004, CECON filed with the CIAC a Motion Considering that the premise for CECON's August 30, 2002 lump-sum offer of P1,540,000.00
to Proceed with arbitration proceedings. ACI filed an Opposition. was no longer availing, CECON was no longer bound by its representations in respect of that
lump-sum amount. It may then claim cost adjustments totalling P16,429,630.74, as well as
After its Opposition was denied, ACI filed its Answer dated January 26, 2005.[51] It attributed values accruing to the various change orders issued by ACI, totalling P159,827,046.94.
liability for delays to CECON and sought to recover counterclaims totalling P180,752 297.84.
This amount covered liquidated damages for CECON's supposed delays, the cost of The CIAC Arbitral Tribunal found ACI liable for the delays. This entitled CECON to extended
defective works which had to be rectified, the cost of procuring permits and licenses, and overhead costs and the ensuing extension cost of its Contractor's All Risk Insurance. For
ACI's other advances. these costs, the CIAC Arbitral Tribunal awarded CECON the total amount of P16,289,623.08.
As it was ACI that was liable for the delays, the CIAC Arbitral Tribunal ruled that ACI was not
On February 8, 2005, ACI filed a Manifestation and Motion seeking the CIAC's clearance for entitled to liquidated damages.
the parties to enter into mediation. Mediation was then instituted with Atty. Sedfrey Ordonez
acting as mediator. The CIAC Arbitral Tribunal ruled that CECON was entitled to a differential in take out costs
representing builder's works and related costs with respect to the equipment purchased by
After mediation failed, an arbitral tribunal was constituted through a March 16, 2005 Order of ACI. This differential cost was in the amount of P15,332,091.47.[63] The CIAC Arbitral
the CIAC. It was to be composed of Dr. Ernesto S. De Castro, who acted as Chairperson with Tribunal further noted that while ACI initially opted to purchase by itself pumps, tanks, and
Engr. Reynaldo T. Viray and Atty. James S. Villafranca as members. cooling towers and removed these from CECON's scope of work, it subsequently elected to
still obtain these through CECON. Considering that the corresponding amount deducted as
ACI filed a Motion for Reconsideration of the CIAC March 16, 2005 Order. This was denied in take-out costs did not encompass the overhead costs and profits under day work, which
the Order dated March 30, 2005. should have accrued to CECON because of these equipment, the CIAC Arbitral Tribunal
ruled that CECON was entitled to 18% day work rate or a total of P21,267,908.00.
In the Order dated April 1, 2005, the CIAC Arbitral Tribunal set the preliminary conference on
April 13, 2005. The CIAC Arbitral Tribunal also found that, apart from adjusted costs incurred on account of
ACI's own activities, it also became necessary for CECON, as main contractor, to continue
At the preliminary conference, CECON indicated that, the total sum it was entitled to recover extending auxiliary services to the project's subcontractors because of the delays. Thus, the
from ACI needed to be adjusted to P324,113,410.08. The CIAC Arbitral Tribunal, thus, CIAC Arbitral Tribunal awarded CECON attendance fees-the main contractor's mark-up for
directed CECON to file an Amended Request for Adjudication/Amended Complaint. auxiliary services extended to subcontractors - totalling P14,335,674.88. This amount was
lower than the original amount prayed for by CECON (i.e., P19,544,667.81)[65] as the CIAC
Following the filing of CECON's Amended Request for Adjudication/Amended Complaint and Arbitral Tribunal ruled that CECON may not claim attendance fees pertaining to
the ensuing responsive pleadings, another preliminary conference was set on May 13, 2005. subcontractors which directly dealt with ACI.
The initial hearing of the case was then set on June 10, 2005.
Considering that CECON's predicament was borne by ACI's fault, the CIAC Arbitral Tribunal
At the initial hearing, the CIAC Arbitral Tribunal resolved to exclude the amount of saw it fit to award to CECON the costs of arbitration totalling P1,083,802.58.
P20,483,505.12 from CECON's claims as these pertained to unpaid accomplishments that
did not relate to the issue of cost adjustments attributed to ACI, as originally pleaded by While mainly ruling in CECON's favor, the CIAC Arbitral Tribunal found CECON liable for
CECON. discolored and mismatched tiles. It noted that CECON had engaged the services of a
subcontractor for the installation of tiles, for which it claimed attendance fees. Thus, it
Following the conduct of hearings, the submission of the parties' memoranda and offers of awarded P7,980,000.00 to ACI.[68] In addition, it found CECON liable to ACI for amounts
exhibits, the CIAC Arbitral Tribunal rendered its Decision on October 25, 2006. It awarded a
On December 4, 2006, ACI filed before the Court of Appeals a Petition for Review[71] under Regarding attendance fees, the Court of Appeals proffered that the work attributed to
Rule 43 of the 1997 Rules of Civil Procedure. subcontractors was merely work done by CECON itself, thereby negating the need for
attendance fees.
In the meantime, on December 28, 2006, the CIAC Arbitral Tribunal issued an Order[72]
acknowledging arithmetical errors in its October 25, 2006 Decision, Thus, it modified its Concerning take-out costs, the Court of Appeals stated that CECON was in no position to
October 25, 2006 Decision, indicating that the net amount due to CECON was propose its own take-out costs as the tender documents issued along with ACI's invitation to
P231,357,136.72, rather than P217,428,155.75. bidders stated that take-out costs must be based exclusively on the rates provided in the
Contract Cost Breakdown. Nevertheless, as ACI had previously undertaken to pay the
In its assailed April28, 2008 Decision,[74] the Court of Appeals reduced the award in favor of variance in takeout costs amounting to P3,811,289.70, the Court of Appeals concluded that
CECON to P114,324,605.00 and increased the award to ACI to P31,566,246.20. an award for take-out costs in that amount was proper.
The Court of Appeals held as inviolable the lump-sum fixed price arrangement between ACI On the CIAC Arbitral Tribunal's award for overhead costs and profits under day work, the
and CECON. It faulted the CIAC Arbitral Tribunal for acting in excess of jurisdiction as it Court of Appeals held that it was improper to grant this award based on stipulations on day
supposedly took it upon itself to unilaterally modify the arrangement between ACI and works pertaining "only to 'materials' and not to equipment."
CECON.
Finally, the Court of Appeals held that CECON was not entitled to costs of litigation
Thus, the Court of Appeals deleted the CIAC Arbitral Tribunal's award representing cost considering that "no premium is to be placed on the right to litigate"[88] and since ACI could
adjustments. However, the Court of Appeals also noted that in ACI's and CECON's March 30, not be faulted for delays.
2004 Joint Ma11ifestation before CIAC, ACI conceded that P10,266,628.00 worth of cost
adjustments was due to CECON and undertook to pay CECON that amount. The Court of The dispositive portion of the assailed Court of Appeals April 28, 2008 Decision read:
Appeals, hence, maintained a P10,266,628.00 award of cost adjustment in favor of CECON.
WHEREFORE, based on all the foregoing, the Decision of the Arbitral Tribunal is modified as
On the cost increases borne by Change Order No. 11-the shift from reinforced concrete to follows:
structural steel framing-and by transitions from schematic diagrams to construction drawings,
the Court of Appeals dismissed the CIAC Arbitral Tribunals award to CECON as arising from a. AWARD TO CECON
"pity" and unwarranted by the lump-sum, fixed-price arrangement.
NO.
The Court of Appeals held ACI liable to CECON for the sum of P12,672,488.36 for
miscellaneous change orders, which it construed to be "separate contracts that have been ISSUE
entered into at the time [ACI] required them."[79] It likewise held ACI liable for P1,132,946.17
representing the balance of 12 other partially paid change orders. Pesos (PHP)
In addition, CECON is directed to submit all required. close-out documents within thirty (30) 3. Bookmarking Granite Tiles- 6,980,000.00
days from receipt of this Decision.
4. Permits, Licenses and other Advances- 6,186,246.23
The parties shall bear their own costs of arbitration and litigation.
TOTAL- 36,166,246.23
SO ORDERED.
II - COMPUTATION:
Acting on CECON's Motion for Reconsideration, the Court of Appeals issued its Amended
Decision on July 1, 2010.[90] This Amended Decision increased the award for miscellaneous AWARD TO CE CONSTRUCTION, INC- 130,062,581.94
change orders to P27,601,469.32; reinstated awards for undervalued works in supplying and
installing G.I. sheets worth P1,209,782.50[91] and for the drilling of holes and application of LESS
epoxy worth P4,543,456.00;[92] and deleted the award for takeout costs.
ACI insists on the inviolability of its supposed agreement with CECON, as embodied in the I. This Court begins by demarcating the jurisdictional and technical competence of the CIAC
contract documents delivered to contractors alongside the original offer to bid. It cites specific and of its arbitral tribunals.
provisions of these documents such as valuation rules and required notices for extensions
and changes, reckoning of losses and expenses, the ensuing liquidated damages for defects, I.A. The Construction Industry Arbitration Commission was a creation of Executive Order No.
cost-bearing changes and provisional sums,[98] which define parameters for permissible 1008, otherwise known as the Construction Industry Arbitration Law.[105] At inception, it was
changes and for reckoning corresponding costs and liabilities. However, it did not attach any under the administrative supervision of the Philippine Domestic Construction Board[106]
of these documents to its Comment or Memorandum. It also cites statutory provisions-Articles which, in turn, was an implementing agency of the Construction Industry Authority of the
1715[99] and 1724[100] of the Civil Code-on CECON's liabilities and the primacy of stipulated Philippines (CIAP).[107] The CIAP is presently attached to the Department of Trade and
contract prices. Industry.
By the inviolability their agreement, ACI insists on the supposed immutability of the stipulated The CIAC was created with the specific purpose of an "early and expeditious settlement of
contract sum and on the impropriety of the CIAC Arbitral Tribunal in writing its own terms for disputes"[109] cognizant of the exceptional role of construction to "the furtherance of national
ACI and CECON to follow.It faults the CIAC Arbitral Tribunal for erroneously reckoning the development goals."
sums due to CECON, particularly in relying on factual considerations that run afoul of
contractual stipulations and on bases such as industry practices and standards, which Section 4 of the Construction Industry Arbitration Law spells out the jurisdiction of the CIAC:
supposedly should not have even been considered as the parties have already adduced their
respective evidence. It insists upon CECON's fault for delays and defects, making it liable for Section 4. Jurisdiction. - The CIAC shall have original and exclusive jurisdiction over disputes
liquidated damages. arising from, or connected with, contracts entered into by parties involved in construction in
the Philippines, whether the dispute arises before or after the completion of the contract, or
Though nominally modifying the CIAC Arbitral Tribunal October 25, 2006 Decision, the Court after the abandonment or breach thereof. These disputes may involve government or private
of Appeals actually reversed it on the pivotal matter of the characterization of the contract contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit
between CECON and ACI. Upon its characterization of the contract as one for a lump-sum the same to voluntary arbitration.
fixed price, the Court of Appeals deleted much of the CIAC Arbitral Tribunal's monetary
awards to CECON and awarded liquidated damages to ACI. The jurisdiction of the CIAC may include but is not limited to violation of specifications for
materials and workmanship; violation of the terms of agreement; interpretation and/or
On initial impression, what demands resolution is the issue of whether or not the Court of application of contractual time and delays; maintenance and defects; payment, default of
Appeals erred in characterizing the contractual arrangement between petitioner CE employer or contractor and changes in contract cost.
Construction Corporation and respondent Araneta Center, Inc. as immutably one for a lump-
sum fixed price. Excluded from the coverage of this law are disputes arising from employer-employee
relationships which shall continue to be covered by the Labor Code of the Philippines.
Section 35. Coverage of the Law. - Construction disputes which fall within the original and Voluntary Arbitrators resolve labor disputes and grievances arising from the interpretation of
exclusive jurisdiction of the Construction Industry Arbitration Commission (the "Commission") Collective Bargaining Agreements. These disputes were specifically excluded from the
shall include those between or among parties to, or who are otherwise bound by, an coverage of both the Arbitration Law and the ADR Law.
arbitration agreement, directly or by reference whether such parties are project owner,
contractor, subcontractor, fabricator, project manager, design professional, consultant, Unlike purely commercial relationships, the relationship between capital and labor are heavily
quantity surveyor, bondsman or issuer of an insurance policy in a construction project. impressed with public interest. Because of this. Voluntary Arbitrators authorized to resolve
labor disputes have been clothed with quasi-judicial authority.
The Commission shall continue to exercise original and exclusive jurisdiction over
construction disputes although the arbitration is "commercial" pursuant to Section 21 of this On the other hand, commercial relationships covered by our commercial arbitratjon laws are
Act. purely private and contractual in nature. Unlike labor relationships, they do not possess the
same compelling state interest that would justify state interference into the autonomy of
I.B. The CIAC does not only serve the interest of speedy dispute resolution, it also facilitates contracts. Hence, commercial arbitration is a purely private system of adjudication facilitated
authoritative dispute resolution. Its authority proceeds not only from juridical legitimacy but by private citizens instead of government instrumentalities wielding quasi-judicial powers.
equally from technical expertise. The creation of a special adjudicatory body for construction
disputes presupposes distinctive and nuanced competence on matters that are conceded to
be outside the innate expertise of regular courts and adjudicatory bodies concerned with
Section 15. Appointment of Experts. - The services of technical or legal experts may be
utilized in the settlement of disputes if requested by any of the parties or by the Arbitral
Tribunal. If the request for an expert is done by either or by both of the parties, it is necessary
that the appointment of the expert be confirmed by the Arbitral Tribunal.
Whenever the parties request for the services of an expert, they shall equally shoulder the
expert's fees and expenses, half of which shall be deposited with the Secretariat before the
expert renders service. When only one party makes the request, it shall deposit the whole
amount required.
Consistent with this restrictive approach, this Court is duty-bound to be extremely watchful Guided by the primacy of CIAC's technical competence, in exercising this Court's limited
and to ensure that an appeal does not become an ingenious means for und rmining the power of judicial review, this Court proceeds to rule on whether or not the Court of Appeals
integrity of arbitration or for conveniently setting aside the conclusions arbitral processes erred in its assailed decisions.
make. An appeal is not an artifice for the parties to undermine the process they voluntarily
elected to engage in. To prevent this Court from being a party to such perversion, this Court's III. Properly discerning the issues in this case reveals that what is involved is not a mere
primordial inclination must be to uphold the factual finqings of arbitral tribunals: matter of contractual interpretation but a question of the CIAC Arbitral Tribunal's exercise of
its powers.
Aware of the objective of voluntary arbitration in the labor field, in the construction industry,
and in any other area for that matter, the Court will not assist one or the other or even both III.A
parties in any effort to subvert or defeat that objective tbr their private purposes. The Court
will not review the factual findings of an arbitral tribunal upon the artful allegation that such F.F. Cruz v. HR Construction[127] distinguished questions of law, properly cognizable in
body had "misapprehended the facts" and will not pass upon issues which are, at bottom, appeals from CIAC arbitral awards, from questions of fact:
issues of fact, no matter how cleverly disguised they might be as "legal questions." The
parties here had recourse to arbitration and chose the arbitrators themselves; they must have A question of law arises when there is doubt as to what the law is on a certain state of facts,
had confidence in such arbitrators. The Court will not, therefore, permit the parties to relitigate while there is a question of fact when the doubt arises as to the truth or falsity of the alleged
before it the issues of facts previously presented and argued before the Arbitral Tribunal, facts. For a question to be one of law, the same must not involve an examination of the
save only where a very clear showing is made that, in reaching its factual conclusions, the probative value of the evidence presented by the litigants or any of them. The resolution of
Arbitral Tribunal committed an error so egregious and hurtful to one party as to constitute a tbe issue must rest solely on what the law provides on the given set of circumstances. Once it
grave abuse of discretion resulting in lack or loss of jurisdiction. Prototypical examples would is clear that the issue invites a review of the evidence presented, the question posed is one of
be factual conclusions of the Tribunal which resulted in deprivation of one or the other party fact.[128]
of a fair opportunity to present its position before the Arbitral Tribunal, and an award obtained
through fraud or the corruption of arbitrators. Any other, more relaxed, rule would result in It further explained that an inquiry into the true intention of the contracting parties is a legal,
setting at naught the basic objective of a voluntary arbitration and would reduce arbitration to rather than a factual, issue:
a largely inutile institution.
On the surface, the instant petition appears to merely raise factual questions as it mainly puts
Thus, even as exceptions to the highly restrictive nature of appeals may be contemplated, in issue the appropriate amount that is due to HRCC. However, a more thorough analysis of
these exceptions are only on the nanowest of grounds. Factual findings of CIAC arbitral the issues raised by FFCCl would show that it actually asserts questions of law.
tribunals may be revisited not merely because arbitral tribunals may have erred, not even on
the already exceptional grounds traditionally available in Rule 45 Petitions.[124] Rather, FFCCI primarily seeks from this Court a determination of whether [the] amount claimed by
factual findings may be reviewed only in cases where the CIAC arbitral tribunals conducted HRCC in its progress billing may be enforced against it in the absence of a joint
their affairs in a haphazard, immodest manner that the most basic integrity of the arbitral measurement of the former's completed works. Otherwise stated, the main question
process was imperiled. In Spouses David v. Construction Industry and Arbitration advanced by FFCCI is this: in the absence of the joint measurement agreed upon in the
Commission: Subcontract Agreement, how will the completed works of HRCC be verified and the amolfnt
due thereon be computed?
Though similarly concerned with "an interpretation of the true agreement between the To rule that the CIAC Arbitral Tribunal modified the parties' agreement because it was
parties,"[130] this case is not entirely congruent with F.F. Cruz. indisputably one for a lump-sum, fixed price of P1,540,000,000.00 is begging the question.
The Court of Appeals used a conclusion as a premise to support itself. It erroneously jumped
In F.F. Cruz, the parties' agreement had been clearly set out in writing. There was a definitive to a conclusion only to plead this conclusion in support of points that should have made up its
instrument which needed only to be consulted to ascertain the parties' intent: anterior framework, points that would have been the ones to lead to a conclusion. It then
used this abortive conclusion to injudiciously dispose of the case.
In resolving the dispute as to the proper valuation of the works accomplished by HRCC, the
primordial consideration should be the terms of the Subcontract Agreement. It is basic that if The Court of Appeals took the parties' contractual relation as a revealed and preordained
the tem1s of a contract are clear and leave no doubt upon the intention of the contracting starting point. Then, it dismissed every prior or subsequent detail that contradicted this
parties, the literal meaning of its stipulations shall control.[131] assumption. It thereby conveniently terminated the discussion before it even began.
Thus, this Court concluded: III.C. There was never a meeting of minds on the price of P1,540,000,000.00. Thus, that
stipulation could not have been the basis of any obligation.
Pursuant to the terms of payment agreed upon by the parties, FFCCI obliged itself to pay the
monthly progress billings of HRCC within 30 days from receipt of the same. Additionally, the The only thing that ACI has in its favor is its initial delivery of tender documents to prospective
monthly progress billings of HRCC should indicate the extent of the works completed by it, bidders. Everything that transpired after this delivery militates against ACI's position.
the same beinff essential to the valuation of the amount that FFCCI would pay to HRCC.[132]
Before proceeding to a consideration of the circumstances that negate a meeting of minds,
III.B. In this case, there is no established contract that simply required interpretation and this Court emphasizes that ACI would have this Court sustain claims premised on supposed
application. inviolable documents. Yet, it did not annex copies of these documents either to its Comment
or to its Memorandum.
The assailed Court of Appeals April 28, 2008 Decision implies that all that had to be done to
resolve the present controversy was to apply the supposedly clear and unmistakable terms of ACI leaves this Court compelled to rely purely on their packaged presentation and in a bind,
the contract between ACI and CECON. It even echoes the words of F.F. Cruz: unable to verify even the accuracy of the syntax of its citations. This Court cannot approve of
this predicament. To cursorily acquiesce to ACI's overtures without due diligence and
It is a legal principle of long standing that when the language of the contract is explicit, substantiation is being overly solicitous, even manifestly partisan.
leaving no doubt as to the intention of the parties, the courts may not read into it any other
intention that would contradict its plain import. The clear terms of the contract should never ACI and its counsel must have fully known the importance of equipping this Court with a
be the subject matter of interpretation. Neither abstract justice nor the rule of liberal reliable means of confirmation, especially in a case so steeped in the sway of circumstances.
interpretation justifies the creation of a contract for the parties which they did not make ACI's omission can only work against its cause.
themselves or the imposition upon one party to a contract or obligation not assumed simply or
merely to avoid seeming hardships. Their true meaning must be enforced, as it is to be By delivering tender documents to bidders, ACI made an offer. By these documents, it
presumed that the contracting parties know their scope and effects. specitled its terms and defined the parameters within which bidders could operate. These
tender documents, therefore, guided the bidders in formulating their own offers to ACI, or,
The Contract Documents expressly characterize the construction contract between [ACI] and even more fundamentally, helped them make up their minds if they were even willing to
CECON as "lump-sum" and "fixed price" in nature. As a consequence, the Contract consider undertaking the proposed project. In responding and submitting their bids,
The mere occurrence of these exchanges of offers fails to satisfy the Civil Code's requirement It is ACI's contention that the offered project cost of P1,540,000,000.00 is what binds the
of absolute and unqualified acceptance: parties because its June 2, 2003 letter indicated acceptance of this offered amount.
Article 1319. Consent is manifested by the meeting of the offer and the acceptance upon the This is plain error.
thing and the cause which are to constitute the contract. The offer must be certain and the
acceptance absolute. A qualified acceptance constitutes a counter-offer. CECON was never remiss in impressing upon ACI that the P1,540,000,000.00 offer was not
perpetually availing. WithoutACI's timely acceptance, on December 27, 2002, CECON wrote
Acceptance made by letter or telegram does not bind the offerer except from the time it came to ACI emphasizing that the quoted sum of P1,540,000,000.00 was "based [only] upon the
to his knowledge. The contract, in such a case, is presumed to have been entered into in the prices prevailing at December 26, 2002" levels.[139] On January 8, 2003, CECON notified
place where the offer was made. (Emphasis supplied) ACI of further increases in costs and specifically stated that "[f]urther delay in the acceptance
of the revised offer and release of the down payment may affect the revised lump sum
Subsequent events do not only show that there was no meeting of minds on CECON's initial amount."[140] Finally, on January 21, 2003, CECON wrote again to ACI,[141] stating that the
offered contract sum of P1,449,089,174.00 as stated in its August 30, 2002 bid. They also contract sum had to be increased to P1,594,631,418.00. CECON also specifically stated,
show that there was never any meeting of minds on the contract sum at all. consistent with Article 1321 of the Civil Code, that its tender of this adjusted price was valid
only until January 31, 2003, as further price changes may be forthcoming. CECON also
In accordance with Article 1321 of the Civil Code,[135] an offeror may fix the time of impressed upon ACI that the 400 days allotted for the completion of the project had to be
acceptance. Thus, CECON's August 30, 2002 offer of P1,449,089,174.00 "specifically stated adjusted.
that its bid was valid for only ninety (90) days, or only until 29 November 2002."[136]
November 29, 2002 lapsed and ACI failed to manifest its acceptance of CECON's offered When ACI indicated acceptance, CECON's P1,540,000,000.00 offer had been superseded.
contract sum. Even CECON's subsequent offer of P1,594,631,418.00 had, by then, lapsed by more than
four (4) months. Apparently totally misinformed, ACI's acceptance letter did not even realize
It was only sometime after November 29, 2002 that ACI verbally informed CECON that the or remotely reference CECON's most recent P1,594,631,418.00 stipulation but insisted on
contract was being awarded to it. Through a telephone call on December 7, 2002, ACI the passe offer of P1,540,000,000.00 from the past year.
informed CECON that it may commence excavation works. However, there is no indication
that an agreement was reached on the contract sum in any of these conversations. ACI, ACI's supposed acceptance was not an effective, unqualified acceptance, as contemplated
CECON, the CIAC Arbitral Tribunal, and the Court of Appeals all concede that negotiations by Article 1319 of the Civil Code. At most, it was a counter-offer to revert to
persisted. P1,540,000,000.00.
Still without settling on a contract sum, even the object of the contract was subjected to ACI's June 2, 2003 letter stated an undertaking: "This notwithstanding, formal contract
multiple modifications. Absent a concurrence of consent and object, no contract was documents embodying these positions will shortly be prepared and forwarded to you for
perfected. execution."[143] Through this letter, ACI not only undertook to deliver documents, it also
admitted that the final, definitive terms between the parties had yet to be articulated in writing.
An office tower atop Part A was included in CECON's scope of works and the contract sum
increased to P1,582,810,525.00. Price fluctuations were conceded after this and the project ACI's delivery CECON's review, and both parties' final act of formalizing their respective
cost was again adjusted to P1,613,615,244.00. Thereafter, CECON agreed to extend a consent and affixing their respective signatures would have established a clear point in which
discount and reduced its offered project cost to P1,540,000,000.00.[138] the contract between ACI and CECON has been perfected. These points, i.e. ACI's delivery,
III.D. Without properly executed contract documents, what would have been a straightforward SECTION 21.3 Extent of power of arbitrator - The Arbitral Tribunal shall decide only such
exercise, akin to the experience in F.F. Cruz, became a drawn-out fact-finding affair. The issues and related matters as are submitted to them for adjudication. They have no power to
situation that ACI engendered made it necessary for the CIAC Arbitral Tribunal to unravel the add, to subtract from, modify, or amend any of the terms of the contract or any supplementary
terms binding ACI to CECON from sources other than definitive documents. agreement thereto, or any rule, regulation or policy promulgated by the CIAC.
It is these actions of the CIAC Arbitral Tribunal that raise an issue, purely as a matter of law, To otherwise be puritanical about cognizable issues would be to cripple CIAC arbitral
now the subject of this Court's review; that is, faced with the lacunae confronting it, whether tribunals. It would potentially be to condone the parties' efforts at tying the hands of tribunals
or not the CIAC Arbitral Tribunal acted within its jurisdiction. through circuitous, trivial recitals that fail to address the complete extent of their claims and
which are ultimately ineffectual in dispensing an exhaustive and dependable resolution.
IV. The CIAC Arbitral Tribunal did not act in excess of its jurisdiction. Contrary to the Court of Construction arbitration is not a game of guile which may be left to ingenious textual or
Appeals' and ACI's assertions, it did not draw up its own tenns and force these terms upon technical acrobatics, but an endeavor to ascertain the tluth and to dispense justice "by every
ACI and CECON. and all reasonable means without regard to technicalities of law or proc.edure."
IV.A. The CIAC Arbitral Tribunal was not confronted with a barefaced controversy for which a IV.B. Two (2) guiding principles steered the CIAC Arbitral Tribunal in going about its task.
fom1ulaic resolution sufficed. More pressingly, it was confronted with a state of affairs where First was the basic matter of fairness. Second was effective dispute resolution or the
CECON rendered services to ACI, with neither definitive governing instrwnents nor a overarching principle of arbitration as a mechanism relieved of the encumbrances of litigation.
confirmed, fixed remuneration for its services. Thus, did the CIAC Arbitral Tribunal go about In Section 1.1 of the CIAC Rules of Procedure:
the task of asce1taining the sum properly due to CECON.
SECTION 1.1 Statement of policy and objectives - It is the policy and objective of these Rules
This task was well within its jurisdiction. This determination entailed the full range of subjects to provide a fair and expeditious resolution of construction disputes as an altemative to
expressly stipulated by Section 4 of the Construction Industry Arbitration Law to be within the judicial proceedings, which may restore the disrupted harmonious and friendly relationships
CIAC's subject matter jurisdiction. between or among the parties. (Emphasis supplied)
Section 4. Jurisdiction. - The jurisdiction of the CIAC may include but is not limited to violation CECON's predicament demanded compensation. The precise extent may yet to have been
of specifications for materials and workmanship; violation of the terms of agreement; settled; yet, as the exigencies that prompted CECON to request for arbitration unraveled, it
interpretation and/or application of contractual time and delays; maintenance and defects; became clear that it was not for the CIAC Arbitral Tribunal to turn a blind eye to CECON's just
payment, default of employer or contractor and changes in contract cost. entitlement to compensation.
CECON raised the principal issue of the payment due to it on account, not only of fluctuating Jurisprudence has settled that even in cases where parties enter into contracts which do not
project costs but more so because of ACI's inability to timely act on many contingencies, strictly confmm to standard formalities or to the typifying provisions of nominate contracts,
despite proper notice and communication from and by CECON. Theretbre, at the heart of the when one renders services to another, the latter must compensate the fonner for the
controversy was the "interpretation and/or application of contractual time and delays." ACI's reasonable value of the services rendered. This amount shall be fixed by a court. This is a
counter-arguments, too, directly appealed to CIAC's subject matter jurisdiction. ACI countered matter so basic, this Court has once characterized it as one that "springs from the fountain of
by asserting that sanctioning CECON's claims was tantamount to violating the tem1s of their good conscience":
agreement. It further claimed liability on CECON's part for "maintenance and defects," and for
"violation of specifications for materials and workmanship." As early as 1903, in Perez v. Pomar, this Court mled that where one has rendered services to
another, and these services are accepted by the latter, in the absence of proof that the
ACI and CECON voluntarily submitted themselves to the CIAC Arbitral Tribunal's jurisdiction. service was rendered gratuitously, it is but just that he should pay a reasonable remuneration
The contending parties' own volition is at the inception of every construction arbitration therefore because "it is a well known principle of law, that no one should be permitted to
proceeding.[144] Common sense dictates that by the parties' voluntary submission, they enrich himself to the damage of another." Similary in 1914, this Court declared that in this
acknowledge that an arbitral tribunal constituted under the CIAC has full competence to rule jurisdiction, even in the absence of statute, ". . . under the general principle that one person
IV.C. The reality of a vacuum where there were no definite contractual terms, coupled with V.A. The tender documents may have characterized the contract sum as fixed and lump-sum,
the demands of a "fair and expeditious resolution" of a dispute centered on contractual but the premises for this arrangement have undoubtedly been repudiated by intervening
interpretation, called into operation Article 1371 of the Civil Code: circumstances.
Article 1371. In order to judge the intention of the contracting parties, their contemporaneous When CECON made its offer of P1,540,000,000.00, it proceeded from several premises.
and subsequent acts shall be principally considered. (Emphasis supplled) First, ACI would timely respond to the representations made in its bid. Second, CECON could
act on the basis of prices prevailing then. Third, the subject matter of the contract was the
Article 1379 of the Civil Code invokes principles from the Revised Rules on Evidence. By entire expanse of design and construction covering all elements disclosed in the tender
invoking these principles, Article 1379 makes them properly applicable in every instance of documents, nothing more and nothing less. Fourth, the basic specifications for designing and
contractual interpretation, even those where the need for interpretation arises outside of court building the Gateway Mall, as stated in the tender documents, would remain consistent.
proceedings: Lastly, ACI would timely deliver on its concomitant obligations.
Article 1379. The principles of interpretation stated in Rule 123 of the Rules of Court shall Contrary to CECON's reasonable expectations, ACI failed to timely act either on CECON's
likewise be observed in the construction of contracts. bid or on those of its competitors. Negotiations persisted for the better part of two (2) calendar
years, during which the quoted contract sum had to be revised at least five (5) times. The
As with Article 1371, therefore, the following principles from the Revised Rules on Evidence object of the contract and CECON's scope of work widely varied. There were radical changes
equally governed the CIAC Arbitral Tribunal's affairs: like the addition of an entire office tower to the project and the change in the project's
structural framing. There was also the undoing of CECON's freedom to design, thereby
4. Interpretation of Documents rendering it entirely dependent on configurations that ACI was to unilaterally resolve, It turned
out that ACI took its time in delivering construction drawings to CECON, with almost 38% of
Section 12. Interpretation according to intention; general and particular provisions. - In the construction drawings being delivered after the intended completion date. There were many
construction of an instrument, the intention of the parties is to be pursued; and when a other less expansive changes to the project, such as ACI's fickleness on which equipment it
general and a particular provision are inconsistent, the latter is paramount to the former. So a would acquire by itself. ACI even failed to immediately deliver the project site to CECON so
particular intent will control a general one that is inconsistent with it. that CECON may commence excavation, the most basic task in setting up a structure's
foundation. ACI also failed to produce definite instruments articulating its agreement with
Section 13. Interpretation according to circumstances. - For the proper construction of an CECON, the final contract documents.
instrument, the circumstances under which it was made, including the situation of the subject
thereof and of the parties to it, may be shown, so that the judge may be placed in the position With the withering of the premises upon which a lump-sum, fixed price arrangement would
of those whose language he is to interpret. have been founded, such an arrangement must have certainly been negated:
Within its competence and in keeping with basic principles on contractual interpretation, the [T]he contract is fixed and lump sum when it was tendered and contracted as a design and
CIAC Arbitral Tribunal ascertained the trqe and just terms governing ACI and CECON. Thus, constmct package. The contract scope and character significantly changed when the design
the CIAC Arbitral Tribunal did not conjure its own contractual creature out of nothing. In was taken over by the Respondent. At the time of the negotiation and agreement of the
keeping with this, the CIAC Arbitral Tribtmal found it proper to sustain CECON's position. amount of Php1.54 billion, there were no final plans for the change to structural steel, and all
There having been no meeting of minds on the contract sum, the amount due to CECON the [mechanical, electrical and plumbing] drawings were all schematics.
It has been established that the original tender, request for proposal and award is for a design Respondent has agreed to the price increase in structural steel and after some negotiation
and construct contract. The contract documents are therefore associated for said system of paid the agreed amount. Respondent also agreed to the price increase in the reinforcing bars
construction. When Respondent decided to change and take over the design, such as the and instructed the Claimant to bill it accordingly. To the Tribunal, such action is an
change from concrete to structural steel framing, "take-out" equipment from the contract and acknowledgment of the price increase. Respondent can make the case that said agreement
modify the [mechanical, electrical and plumbing w]orks, the original scope of work had been is conditional, i.e., the Complaint must be withdrawn. To the Tribunal, the conditionality falls
drastically changed. To tie down the Claimant to the tmit prices for the proposal for a different both ways. The Claimant has as much interest to agree to a negotiated price increase so that
scope of work would be grossly unfair. This Tribunal will hold that unit price adjustment could it can collect payments for the claims. The conditionalities do not change the basis for the
be allowed but only for change orders that were not in the original scope of work, such as the quantity and the amotmt. The process of the negotiation has arrived at the price difference
change order from concrete to structural framing, the [mechanical, electrical and plumbing and quantities. The Tribunal finds the process in arriving at the Joint Manifestation, a fair
w]orks, [schematic drawings to construction drawings] and the Miscellaneous Change Order determination of the unit price increase. This holding will render the discussions on Exhibit
Works. JJJJ, and the demand of the burden of proof of the Respondent superfluous.[154]
V.B. Contrary to ACI's oft-repeated argument,[152] the CIAC Arbitral Tribunal correctly found This absurdity is so patent that the Court of Appeals was still compelled to uphold awards
that ACI had gained no solace in statutory provisions on the immutability of prices stipulated premised on ACI's admissions, even as it reversed the CIAC Arbitral Tribunal decision on the
between a contractor and a landowner. Article 1724 of the Civil Code reads: primordial issue of the characterization of the contractual arrangement between CECON and
ACI:
Article 1724. The contractor who undertakes to build a structure or any other work for a
stipulated price, in conformity with plans and specifications agreed upon with the land-owner, As stated, the contract between [ACI] and CECON has not been amended or revised. The
can neither withdraw from the contract nor demand an increase in the price on account of the Arbitral Tribunal had no power to amend the contract to provide that there be allowed price
higher cost of labor or materials, save when there has been a change in the plans and and/or cost adjustment removing the express stipulation that the Project is for a lump sum or
specifications, provided: fixed price consideration. Accordingly, this Court removes the award for additional costs
spent by CECON on cement and formworks due to price increases or removing the award for
(1) Such change has been authorized by the proprietor in writing; and these items in the total amount of PhP5,598,338.20. Since CECON is not entitled to its claim
for price increase, it is likewise not entitled to the award of the interest rate of 6% per annum.
(2) The additional price to be paid to the contractor has been determined in writing by both
parties. With regard however to the additional costs for the rebars due to price increases. this Court
finds that CECON is entitled to the amount of PhP10,266,628.00 representing the additional
Article 1724 demands two (2) requisites in order that a price may become immutable: first, costs spent by CECON for rebars due to price increases, notwithstanding the Arbitral
there must be an actual, stipulated price; and second, plans and specifications must have Tribunal's excess of jurisdiction in amending the contract between the parties because [ACI]
definitely been agreed upon. and CECON had in fact agreed that CECON was entitled to such an amount and that [ACI]
VI.A. With the undoing of the foundation for the Court of Appeal's fallacious, circular Section 14. Peculiar signification of terms. - The terms of a writing are presumed to have
reasoning, its monetary awards must also necessarily give way to the reinstatement of the been used in their primary and general acceptation, but evidence is admissible to show that
CIAC Arbitral Tribunal's awards. they have a local, technical, or otherwise peculiar signification, and were so used and
understood in the particular instance, in which case the agreement must be construed
The inevitable changes borne by ACI's own trifling actions justify, as a consequence, accordingly.
compensation for cost adjustments and the ensuing change orders, additional overhead costs
for the period of extension, extended coverage for contractor's all-risk insurance, and Section 19. Interpretation according to usage. - An instrument may be construed according to
attendance fees for auxiliary services to subcontractors whose functions were also usage, in order to determine its true character.[157] (Emphasis supplied)
necessarily prolonged. ACI's frivolity on the acquisition of elevators, escalators, chillers,
generator sets, indoor substations, cooling towers, pumps, and tanlcs also vindicates Equally availing is the following principle. This is especially tlue of the remuneration due to
compensation for the works that remained under CECON's account. ACI's authorship of the CECON, considering that stipulations for remuneration are devised for the benefit of the
causes of delay supports time extensions favoring CECON and, conversely, discredits person rendering the service:
liquidated damages benefitting ACI.
Section 17. Of two constn.1ctions, which preferred. - When the terms of an agreement have
This Court upholds the Arbitral Tribunal's awards on each of the items due to CECON, as well been intended in a different sense by the different parties to it, that sense is to prevail against
as on its findings relating to CECON's countervailing liabilities. either party in which he supposed the other understood it, and when different constructions of
a provision are otherwise equally proper, that is to be taken which is the most favorable to the
In fulfilling its task, the CIAC Arbitral Tribunal was equipped with its technical competence, party in whose favor the provision was made.[158]
adhered to the rigors demanded by the CIAC Rules of Procedure, and was endowed with the
experience of exclusively presiding over 19 months of arbitral proceedings, examining object VI.C. In appraising the CIAC Arbitral Tribunal's awards, it is not the province of the present
and documentary evidence, and probing witnesses. Rule 45 Petition to supplant this Court's wisdom for the inherent technical competence of and
the insights drawn by the CIAC Arbitral Tribunal throughout the protracted proceedings before
VI.B. Within the CIAC Arbitral Tribunal's technical competence was its reference to prevailing it. The CIAC Arbitral Tribunal perused each of the parties' voluminous pieces of evidence.
industry practices, a much-bewailed point by ACI.[156] This reference was made not only [159] Its members personally heard, observed, tested, and propounded questions to each of
desirable but even necessary by the absence of definitive governing instruments. Moreover, the witnesses. Having been constituted solely and precisely for the purpose of resolving the
this reference was made feasible by the CIAC Arbitral Tribunars inherent expertise in the dispute between ACI and CECON for 19 months, the CIAC Arbitral Tribunal devoted itself to
construction industry. no other task than resolving that controversy. This Court has the benefit neither of the CIAC
Arbitral Tribunal's technical competence nor of its irreplaceable experience of hearing the
This reference was not only borne by practical contingencies and buttressed by recognized case, scrutinizing every piece of evidence, and probing the witnesses.
proficiency, it was also sanctioned by the statutory framework of contractual interpretation
within which the CIAC Arbitral Tribunal operated. Thus, the following principles governed the
Inventive, hair-splitting recitals of the supposed imperfections in the CIAC Arbitral Tribunal's In this Court alone, ACI sought extensions to file its Comment no less than five (5) times.[162]
execution of its tasks will not compel this Court to supplant itself as a fact-finding, technical It sought several other extensions in the filing of its Memorandum.[163]
expert.
It also does not escape this Court's attention that while ACI's arguments have perennially
ACI's refutations on each of the specific items claimed by CECON and its counterclaims of pleaded the supposed primacy and itnmutability of stipulations originally articulated in the
sums call for the point by point appraisal of work, progress, defects and rectifications, and tender documents, it never bothered to annex any of these documents either to its Comment
delays and their causes. They are, in truth, invitations for this Court to engage in its own audit or to its Memorandum. Without these and other supporting materials, this Court is left in the
of works and corresponding financial consequences. In the alternative, its refutations insist on uneasy predicament of merely relying on ACI's self-stated assertions and without means of
the application of rates, schedules, and other stipulations in the same tender documents, verifying even the syntax of its citations.
copies of which ACI never adduced and the efficacy of which this Court has previously
discussed to be, at best, doubtful. While presumptions of good faith may be indulged, the repercussions of ACI's vacillation
cannot be denied.
This Court now rectifies the error made by the Court of Appeals. By this rectification, this
Court does not open the doors to an inordinate and overzealous display of this Court's Even if this Court were to ignore the delays borne by ACI's procedural posturing, this Court is
authority as a final arbiter. compelled to hearken to ACI's original faults. These are, after all, what begot these
proceedings. These are the same original faults which so exasperated CECON; it was left
Without a showing of any of the exceptional circumstances justifying factual review, it is with no recourse but to seek the intervention of CIAC.
neither this Court's business nor in this Court's competence to pontificate on technical
matters. These include things such as fluctuations in prices of materials from 2002 to 2004, These faults began as soon as bidders responded to ACI's invitation. In CECON's case, its
the architectural and engineering consequences - with their ensuing financial effects - of communicated time for the validity of its offer lapsed without confinnation from ACI. ACI only
shifting from reinforced concrete to structural steel, the feasibility of rectification works for verbally responded and only after CECON's communicated timeframe. It told CECON to
defective installations and fixtures, the viability of a given schedule of rates as against commence excavation works but failed to completely deliver the project site until five (5)
another, the audit of changes for every schematic drawing as revised by construction months later. It engaged in protracted negotiations, never confirming acceptance until the
drawings, the proper mechanism for examining discolored and mismatched tiles, the minutiae tenth month, after bidders had submitted their offers. By then, ACI's supposed acceptance
of installing G.I. sheets and sealing cracks with epoxy sealants, or even unpaid sums for could not even identify CECON's most recent quoted price. It undertook to process and
garbage collection. deliver formal documents, yet this controversy already reached this Court and not a single
page of those documents has seen the light of day. It has repeatedly added and taken from
The CIAC Arbitral Tribunal acted in keeping with the law, its competence, and the adduced CECONs scope of works but vigorously opposed adjustments that should have at least been
evidence; thus, this Court upholds and reinstates the CIAC Arbitral Tribunal's monetary given reasonable consideration, only to admit and partially stipulate on thern. In taking upon
awards. itself the task of designing, it took its time in delivering as many as 1,675 construction
This Court commenced its discussion by underscoring that arbitration primarily serves the
need of expeditious dispute resolution. This interest takes on an even greater urgency in the
context of construction projects and the national interest so intimately tied with them. ACI's
actions have so bogged down its contractor. Nearing 13 years after the Gateway Mall's
completion, its contractor has yet to be fully and properly compensated. Not only have ACI's
actions begotten this dispute, they have hyper-extended arbitration proceedings and dragged
courts into the controversy. The delays have virtually bastardized the hopes at expeditious
and effective dispute resolution which are supposedly the hallmarks of arbitration
proceedings.
For these, in addition to sustaining each of the awards due to CECON arising from the facets
of the project, this Court also sustains the CIAC Arbitral Tribunal's award to CECON of
arbitration costs. Further, this Court imposes upon respondent Araneta Corporation, Inc. the
burden of bearing the costs of what have mutated into a full-fledged litigation before this
Court and the Court of Appeals.
WHEREFORE, the Petition is GRANTED. The assailed April 28, 2008 Decision and July 1,
2010 Amended Decision of the Court of Appeals in CA-G.R. SP No. 96834 are REVERSED
and SET ASIDE. The Construction Industry Arbitration Commission Arbitral Tribunal October
25, 2006 Decision in CIAC Case No. 01-2004 is REINSTATED.
Legal interest at the rate of six percent (6%) per annum is imposed on the award from the
finality of this Decision until its full satisfaction.
SO ORDERED.
Furnish all scaffoldings as required to support the system at no ,cost to Form-Eze; Assist BFC in setting the deck forms to the proper grade and locations provided that BFC has
laid out the grid lines as needed for placing the scaffoldings under the deck forms and
Furnish all plywood and lumber as required in the formwork operation as no cost to Form- provided the scaffoldings is readily available for placement under the deck forms.
Eze;
Obligations of BFC
Purchase materials for the formwork as requested by Form-Eze. The direct cost of materials
shall be deducted from the contract and the balance paid to Form-Eze; and Furnish additional hoisting; and
Responsible for the freight of the equipment to and fro the Marikina jobsite and the Form-Eze Provide all labor requested by Form-Eze and deducted from the contract at P60.00 per
warehouse in Cainta, Rizal. carpenter man-hour.
The amount of hardware to be furnished is sufficient to provide 7,000 contact square meters Total contract amount for moving equipment: 126,000 x P50.00/contact square meter (cost
of formwork. for stripping and movement of the equipment, excluding cost of resetting to grade, cleaning
plywood surfaces and applying release agent) P6,300,000.00.
Contract Price
Terms of Payment
Total contract amount for the equipment: 126,000 contact square meters (equipment to be
used) x P225.00/contact square meter (cost per use of the hardware for forming the elevated 15% down payment or P945,000.00 paid to Form-Eze on or before pick up of equipment; and
beam and slab)= P28,350,000.00.
Monthly progress billing will coincide with the contact square meters formed with the Form-
Terms of Payment Eze equipment.
15% down payment or P4,252,500.00 paid to Form-Eze on or before pick up of equipment; CONTRACT NO. 3: Contract for Column Formwork on the SM Marikina Mall Project dated 20
December 20066
When concrete is placed on the slab forms, the equipment rental per contact square meter is
due and payable to Form-Eze and shall be paid on the first day of the following month; Obligations of Form-Eze
Furnish labor as required by Form-Eze for forming columns and will deduct fro Form-Eze Agreement is contingent upon parties entering into an exclusive licensing agreement with
P60.00 per man-hour for each carpenters for the column framework; and BFC for the manufacture of Form-Eze equipment.
Responsible for all column grid lay-out and establishing elevations on the columns CONTRACT NO. 5: Contract for the Purchase and Lease of the Heavy Duty Galvanized X-
Bracing on SM Marikina Mall Project dated 29 January 20078
Terms of Payment
Obligations of BFC
Total Contract Amount: 9,100 contact square meters of formwork x P355.00/contact square
meter= P3,230,500.00; Manufacture heavy duty galvanized x-bracing.
BFC agrees to purchase all materials for the formwork as required by Form-Eze and the Credit BFC with P400.00 per x-brace. If the x-bracing is not manufactured exactly as
direct cost of those materials will be deducted from this contract and the balance paid to specified by Form-Eze, credit is P300.00 per x-brace.
Form-Eze; and
Agreement is contingent upon parties entering into an exclusive licensing agreement for the
When columns are poured and stripped, P355.00 per contact square meter is due and manufacturing of Form-Eze equipment.
payable at that time. Progress payments will be made for the work completed in a particular
month and paid on the first day of the following month. Any materials or equipment purchased MEMORANDUM OF AGREEMENT dated 5 January 20079
by BFC at the request of Form-Eze shall be deducted from this contract and prorated equally
over a 4-month period. BFC will manufacture Form-Eze equipment and will sell exclusively to Form-Eze.
CONTRACT NO. 4: Contract for the Lease of the Heavy Duty Galvanized Scaffold Frames LETTER-AGREEMENT dated 5 January 200710
and Related Accessories on SM Marikina Mall Project dated 29 January 20077
Changes to Contract No.4
Obligations of BFC
The threading of the heavy duty screw will be accomplished in segments and then machined. The existence of five contracts, a memorandum of agreement and a supplemental contract.
Form-Eze will send to the jobsite all 18-inch and 24-inch adjustable u-heads available in its BFC renegotiated Contract #1 but it did not result in a separate written contract.
current stock in order to start forming the project while BFC is fabricating the 14-innch
adjustable u-heads. When the 3.000 pieces 14-inch u-heads are completed and are on the Under Contract #1, BFC is willing and ready to pay Form-Eze the amount of P3,515,003.59,
jobsite, Form-Eze will take back the 18-inch and 24-inch adjustable u-heads that were which amount shall be deducted from the amount of the latter's claim.
temporarily in use at the jobsite.
Under Contract BFC is willing and ready to pay Form-Eze the amount of P675,788.97, which
The creditable amount for the purchase of the 6-foot heavy duty galvanized scaffolding and amount shall be deducted from the amount of the latter's claim.
related accessories is changed to P4,235.00 per 6-foot heavy duty galvanized frames,
adjustable u-heads and heavy duty base plate. BFC admits that it has the obligation to return to Form-Eze equipment furnished them under
Contracts #1, 2, and 3, and all heavy duty galvanized scaffold frames and related
On 30 March 2007, Form-Eze filed a Request for Arbitration11 before the CIAC. In its accessories, heavy duty galvanized x-bracing and adjustable U-heads and base plates
Complaint, Form-Eze alleged that BFC has an unpaid obligation amounting to P9,189,024.58; fabricated and manufactured by BFC under Contracts #4, 5 and letters dated 5 January
that BFC wanted to re-negotiate the equipment leases; and that it was not complying with the 2007.14
contractual and supplemental agreements in effect. Form-Eze prayed for the following relief:
The claims15 of the parties are summarized, as follow:
[For BFC] to pay the current monthly equipment rentals;
FORM-EZE'S CLAIMS As of 7/19/2007 From 7/20/2007 to end of contract based on agreed
Provisions made to guarantee the earned monthly equipment leased amounts are paid minimum contact sq.m. of 126,000
timely;
Arrears on Contract No.1
To legislate provisions to ensure the lease contracts are not breached during the construction
of the SM Marikina Mall; P26,310,476.29
Provisions made to guarantee the performance of [BFC] for the manufacturing of the shoring - 3,515,003.59
equipment purchased by Form-Eze from BFC;
22,795,472.70
Provisions made to guarantee the return of all Form-Eze equipment when the concrete
structure is completed and all lost and damaged equipment has been paid for by [BFC]; and P11,489,523.71
In its Amended Answer with Counterclaim, BFC sought for reformation of Contract #1 to 4,771,723.63
incorporate a provision that BFC shall deduct from said billing the cost of labor supplied by it
for the fabrication and assembly of the forming system and for the stripping, cleaning, -675,788.97
resetting thereof at the rate of P60.00 per man-hour. BFC also demanded the refund of
P5,773,440.00 as expenses for the manufacture of additional hardware to complete the 7,000 4,095,934.66
square meters of formwork required in Contract #1. BFC explained that Form-Eze had only
furnished 4,682.4 square meters of formwork.13 1,528,276. 37
The CIAC appointed a 3-member Arbitral Tribunal (CIAC Arbitral Tribunal), composed of Atty. Arrears on Contract No.3 2,099,825.00 1,130,675.00
Custodio O. Parlade, Atty. Alfredo F. Tadiar and Engineer Romeo C. David, to adjudicate
Form-Eze's claims. Arrears on Letter dated 1/5/07 740,600.00 483,000.00
BFC's COUNTERCLAIM Contract #1 - Provision in the Contract to include the P75 per contact sq.m. for labor
guarantee.
Cost of labor, helmet & expenses for x-bracing for the assembly of the form
Is [BFC] #1 entitled to the reformation of Contract #1 to include a provision that [BFC] #1 shall
system under Contract #1 P 812,791.09 deduct from [Form-Eze's] billing the cost of labor, helmet and expenses for x-bracing supplied
by it for the assembly of the form system amounting to P812,791.09 , to deduct from the
Cost of stripping, petroleum, oil, & helmet under Contract #2 1,391,086.02 billing under Contract #2 the cost of labor for the stripping thereof, the costs of petroleum, oil
and lubricant and helmet of the said laborers up to the end of the contract in the sum of
Attorney's Fees 300,000.00 P1,391,086.02 and from the billing under Contract #3, the cost of labor for the installation and
forming of the built up column forms from June 19, 2007 up to the end of the project in the
Total Counterclaims P2,503,877.11 sum of P273,240.00?16]
TOTAL SUM IN DISPUTE P46,867,184.55 Is it proper to include Mr. Honorio Pineda as Respondent No. 2?
The total arbitration fees amounted to P616,393.73. Does the Arbitral Tribunal have the jurisdiction to award claims that accrued after the filing of
the Request for Arbitration or does the Claimant have a cause of action for claims that
CIAC Arbitral Tribunal was tasked to resolve the following issues, to wit: accrued during the same period?
Is Claimant entitled to its total claim of P34,284,996.41 representing the alleged arrear on Who between the parties is entitled to attorney's fees?
equipment rental under Contract #1?
Who between the parties should bear the arbitration costs?17
Is Claimant entitled to its claim of P5,624,211.03 representing the alleged arrears under
Contract #2? FINAL AWARD BY CIAC
Is Claimant entitled to its claim of P3,230,500.00 representing the alleged arrears under On 7 December 2007, the CIAC Arbitral Tribunal rendered a Final Award in favor of Form-
Contract #3? Eze. The dispositive portion reads:
Is Claimant entitled to its claim of P1,374,408.00 representing the rental fees under Letter WHEREFORE, award is hereby made in favor of Claimant and against [BFC], ordering the
dated 5 January 2007? latter to pay the former the following amounts:
Is Claimant entitled to its claim for the reformation of the subject Contracts to include the a) On Contracts No. 1
following:
P28,350,000.00
Contract #1 - Provisions to guarantee the earned monthly equipment leased amounts are
paid timely; Less: Payments already made
Contract #1 - Provision to ensure that the lease contracts are not breached during the 7,700,000.00
construction of the SM Marikina Mall;
_____________
990,000.00 ____________
60,000.00 P28,517,251.67
____________ The Tribunal further awards in favor of [Form-Eze] and against [BFC] and [Pineda] who are
ordered, jointly and severally to pay [Form Eze] P300,00.00 as attorney's fees, and to
TOTAL indemnify [Form-Eze's] cost of arbitration paid to CIAC.
c) On Contract No.3 a) The claims under Issues No. 5 and 6 for reformation of Contracts No 1, 2, 3, 4 and 5
are denied for lack of merit.
P 2,153,166.67 b) The inclusion of Mr. Honorio Pineda in the Complaint as additional respondent is
proper.
Less: cost of labor
c) The Tribunal has jurisdiction over the claims of [Form-Eze] and finds that the
Complaint states a cause of action as to claims that accrued after the filing of the
96,915.00
Complaint.
____________ d) All other claims and counterclaims submitted pursuant to the definition of issues in
the Terms of Reference, not otherwise disposed of or resolved above, are dismissed
P2,056,751.67 for lack of merit. All claims and counterclaims peripherally discussed in these
proceedings which are outside the scope of the definition of issues in the Terms of
On Letter Agreement of January 5, 2008 to December 8, 2007 Reference are likewise outside the scope of this Final Award.
e) The net award in favor of [Form-Eze] amounting to P28,517,251.67 shall earn
P560,000.00
interest at the rate of 6% per annum fro the date of this Final Award, and 12% from
IN SUM THE FOLLOWING AWARDS ARE MADE: the date the Final Award becomes final and executory until the same is fully paid.18
Contract No. 1 BFC filed a Motion for Correction of the Final Award. Form-Eze asserted that the calculations
made on the total quantity of deckforms supplied to be used under Contract No. 1 is
P 20,650,000.00 erroneous because the quantity of the accessories that were delivered together with the loose
truss chords and assembled trusses that were backloaded were ignored in the computation.
Contract No. 2 BFC explained that the hardware supplied must be assembled first into deckforms since what
is actually rented under Contract No. 1 are the deckforms, and not the hardware, thus:
Therefore, to form 87 completely assembled deckforms of 44 ft. in length out of/from the BFC filed a motion for reconsideration but it was denied by the Court of Appeals in a
delivered chords and trusses, it will require 2,958 pieces of joist and 5,916 pieces of beam Resolution dated 13 July 2010. Hence, the present petition. BFC, in its Memorandum, raised
hangers. the following issues for our resolution:
However, as show in Exhibits "C-9(5)", "C-9(11)", "C-9(15)", "C-9(18)", "C-9(21)", "C-9(25)", I. Whether or not the Court of Appeals committed a reversible error in affirming the
"C-9(27)", "C-9(30)", and "C-9(31)", only 2,512 pieces of joists and in Exhibits "C-9(8)", "C- CIAC's ruling that BFC is liable to pay rent to the [Form Eze] under Contract Nos. 1, 2,
9(15)", "C-9(16)", "C- 9(18)", "C-9(21)", "C-9(27)", "C-9(32)", "C-9(34)", "C-9(35)", "C-9(37)", and 3 even for portions where the latter's supplied formwork system were not used.
"C-9(38)", "C-9(41)", "C-9(35)", "C-9(38)", "C-9(40)", and "C-9(41)", only 3,626 pieces of
II. Whether or not the Court of Appeals committed a reversible error in affirming the
beam hangers, the very documents on which this Commission/Tribunal anchored its finding
now sought to be corrected, were actually delivered by the Claimant. CIAC's conclusion that [Form-Eze] was able to supply BFC with such quantity of
deckforms sufficient to provide the stipulated 7,000 contact square meter of formworks
Accordingly, 87 deckforms of 44 ft. in length can not be completely assembled from the as to entitle said [Form-Eze] to the stipulated minimum contract rental price of
delivered chords and trusses because the quantity of the delivered accessories is insufficient Php28,350,000.00 under Contract No. 1 and consequently to Php6,300,000.00 under
for the purpose. To be precise, only 53 deckforms of 44ft. in length can be completely Contract No. 2, when, based on the quantity of the delivered accessories, which are
assembled out of the total length of the chords and trusses with the use of 1,802 pieces of component pm1s of deck form system, but which the CIAC totally ignored, [Form-Eze]
joists and 3,604 pieces of beam hangers (with an excess of 22 pieces of beam hangers, 710
can only provide 4,441.73 contact square meters of formworks that will entitle it to only
pieces of joist and 2,720 ft of chords and trusses) which are sufficient to provide only
4,441.73 contact sq.m. of formworks. Php17,989,006.05 and Php3,997,557.00, respectively thereunder.
III. Whether or not the Court of Appeals committed reversible error in affirming the CIAC's
To therefore conclude that 87 deckforms of 44 ft. in length can be completely assembled with ruling that [Form-Eze] is entitled to twoOthirds of the stipulated minimum contract
the use of/out of 2,512 pieces of joists and 3,626 pieces of beam hangers, is an evident amount of Php3,230,500.00 or Php2,153,666.67 under Contract No. 3, considering
miscalculation. that CIAC did not state the factual and legal basis of said ruling and despite its
contrary factual finding that [Form-Eze] failed to supply the minimum required
In as much as only 3,626 pieces of beam hangers were actually delivered, which, when used
columnforms.
with the delivered quantity of joists and length of the delivered chords and trusses in
completely assembling 53 deckforms of 44 ft. in length, is sufficient to provide only 4,441.73 IV. Whether or not the Court of Appeals committed a reversible error in affirming the
contact sq.m. of formworks, the minimum rental amount stipulated under Contract No. l CIAC's ruling against the reformation of Contract No. 1 to include a provision that BFC
should correspondingly be reduced to only Php17,989,006.50, less payment of Php shall furnish the labor needed by [Form-Eze] in assembling the deckforms and that it shall
7,700,000.00=Php 10,829,006.50 as the net amout of rent due the Claimant thereunder, as deduct therefrom the agreed cost of labor at Php60.00 per man hour, since it has been
shown in the herewith attached Annex "B" hereof. the true intention and real agreement of the parties thereto.
V. Whether or not the Court of Appeals committed a reversible error in affirming the
On the same ground, the minimum contact amount stipulated under Contract No. 2 should
CIAC when it did not deduct the following costs incurred by BFC from the minimum
also be proportionately reduced to Php 3,997,557.00, less payment of Php 990,000.00 + cost
of labor of Php60,000.00 = Php 2,947,557.00 as the net amount due the Claimant contract amounts due:
thereunder.
(2) under Contract No. 2 for the cost of labor in the stripping of said deckforms, the cost of Cost of labor in assembling Deckforms, expenses for xBracings and cost of helmet
petroleum, oil and lubricant and helmet up to the end of the contract in the sum total of
Php1,391,086.02; and 812,791.90
(3) under Contract No. 3 for the cost of labor in installing and forming the built up 9,000,619.95
columnforms from 25 June 2007 up to the end of the contract in the sum total of
Php273,240.00, when BFC is legally entitled thereto. SUBTOTAL
VI. Whether or not the Court of Appeals committed a reversible error in affirming the Php 8,988,386.55
CIAC in ordering BFC to pay rental fees under letter dated 5 January 2007, covering the
period from 25 June 2007 to 17 December 2007 in the sum total of Php560,000.00 at b. On Contract No. 2- Php 3,997,557.50
Php96,000.00 a month, when the acquisition cost of the pieces of u-heads and plates
referred to therein is allegedly only Php96,000.00, and there is evidence presented to Less: Payments already made- Php 990,000.00
show that these items were purchased at Php96,000.00 and there is on evidence to
show the prevailing rate of rent for the same items. Costs of labor in stripping And moving of the same Deckforms, petroleum, oil And lubricant
and helmet- 1,304,036.82
VI. Whether or not the Court of Appeals committed a reversible error in affirming the
CIAC in ruling that Respondent Pineda can be held as co-respondent (in the arbitration Php 2,294,036.82
case) when he is not a party to the contracts and agreements involved in this case, as
well as the arbitration agreement, and he did not voluntarily submit himself to arbitration SUBTOTAL
in this case.
VII. Whether or not the Court of Appeals committed a reversible error when it Php 1,702,520.68
ruled that the attorney's fees and cost of arbitration shall be for the account of
c. On Contract No. 3 Php 538,417.87
Petitioners, considering that [Form-Eze] failed to supply the minimum required
equipment under the contracts and when the root cause of the dispute is the imprecision Less:
of the language and the incompleteness of the contracts and agreements, which were
prepared by the Respondents.20 Cost of labor in the installation and removal of the Columnforms - 96,915.00
To begin, Executive Order No. (EO) 1008, which vests upon the CIAC original and exclusive The CIAC Arbitral Tribunal conducted its own study and came up with the following findings:
jurisdiction over disputes arising from, or connected with, contracts entered into by parties
involved in construction in the Philippines, plainly states that the arbitral award "shall be final The receipted hardware deliveries made by [Form-Eze] show that the total length of loose
and inappealable except on questions of law which shall be appealable to the Court." Later, truss chords delivered was 11,912 lineal feet and the length of the truss chords from the
however, the Court, in Revised Administrative Circular (RAC) No. 1-95, modified this rule, assembled trusses delivered was 2,052 lineal feet or a total available length of trusses of
directing that the appeals from the arbitral award of the CIAC be first brought to the CA on 13,964 lineal feet. By an iterative process of selection and elimination, 175 units of 44' long
"questions of fact, law or mixed questions of fact and law." This amendment was eventually trusses could be assembled, equivalent to 87 deckforms of 44 feet in length. The assembled
transposed into the present CIAC Revised Rules which direct that "a petition for review from a 87- 44' deckforms can provide 7,268.58 square meters of contact area, broken down as
final award may be taken by any of the parties within fifteen (15) days from receipt thereof in follows:
accordance with the provisions of Rule 43 of the Rules of Court." Notably, the current
provision is in harmony with the Court's pronouncement that ''despite statutory provisions Contact Area (%)
making the decisions of certain administrative agencies 'final,' the Court still takes cognizance
of petitions showing want of jurisdiction, grave abuse of discretion, violation of due process, Interior & Near Column Slabs = 4,156.89 sq.m. (57.19%)
denial of substantial justice or erroneous interpretation of the law" and that, in particular,
"voluntary arbitrators, by the nature of their functions, act in a quasi-judicial capacity, such Grid Beams (B-1) = 740.37 sq.m. (10.19%)
that their decisions are within the scope of judicial review."23
Interior Beams (B-2) = 1,663.20 sq.m. (22.88%)
Factual findings of construction arbitrators may be reviewed by the Court in cases where: 1)
the award was procured by corruption, fraud or other undue means; (2) there was evident Grid Girders (G-2) = 708.12 sq.m. (9.74%)
partiality or corruption of the arbitrators or any of them; (3) the arbitrators were guilty of
misconduct in refusing to hear evidence pertinent and material to the controversy; (4) one or Total = 7,268.58 sq.m. (100%)
more of the arbitrators were disqualified to act as such under Section nine of Republic Act
(R.A.) No. 876 and willfully refrained from disclosing such disqualifications or of any other The resulting contact area of 7,628.58 sq.m. is 3.84% over the 7,000 sq.m. requirement of
misbehavior by which the rights of any party have been materially prejudiced; (5) the the contract. But the former figure includes the contact area of girders which according to
arbitrators exceeded their powers, or so imperfectly executed them, that a mutual, final and [petitioners] should not be included. As shown in ANNEX "A", sheets 5 & 6 of 6, the contact
definite award upon the subject matter submitted to them was not made; (6) when there is a area contributed by the girders is only 708.12 sq.m., and if this is deducted from the
very clear showing of grave abuse of discretion resulting in lack or loss of jurisdiction as when computed total contact area, the remaining available contact area would be 6,560.46 sq.m. or
a party was deprived of a fair opportunity to present its position before the Arbitral Tribunal or 93.72%. The fact, however, is that the non inclusion of the contact area provided by the
when an award is obtained through fraud or the corruption of arbitrators; (7) when the findings girders would be a violation of the letter-contract dated 8 February 2007, paragraph 9 of
of the Court of Appeals are contrary to those of the CIAC, and (8) when a party is deprived of which provides that: "[Form-Eze] offered to install beam hangers and ledger angles in order to
administrative due process. support the moment beam from from column to column and thereby save BFC considerable
labor and eliminate the use of BFC's light duty scaffolding underneath and beam. By doing
While this rule, which limits the scope of the review of CIAC findings, applies only to the that it will also speed up the forming operation and save BFC labor. The only light duty
Supreme Court, the Court of Appeals nonetheless is not precluded from reviewing findings of scaffolding that BFC will be installing is that under the girder which supports tremendous
facts, it being a reviewer of facts. By conveniently adopting the CIAC's decision as its own loading during the stressing of the beams prior to it being stressed. By forming the girder in
and refusing to delve into its factual findings, the Court of Appeals had effectively turned a this manner, [Form-Eze] is not involved in the tripping or resetting of the girder formwork.
As agreed upon by the parties, the 708.12 sq. m. contact area covered by the grid girders In order that an action for reformation of instrument may prosper, the following requisites
should be included in the billing. Taking into account this contact area corresponding the grid must concur: (1) there must have been a meeting of the minds of the parties to the contract;
girders and the 4,441.73 contact square meter assembled deckforms, the total contact area is (2) the instrument does not express the true intention of the parties; and (3) the failure of the
only 5,149.85, which still falls short of the 7,000 contact area requirement. instrument to express the true intention of the parties is due to mistake, fraud, inequitable
conduct or accident.30
To award the full contract price to Form-Eze in Contract No. 1 is tantamount to unjust
enrichment. There is unjust enrichment under Article 22 of the Civil Code when (1) a person In the instant case, the question to be resolved is whether the contract expressed their true
is unjustly benefited, and (2) such benefit is derived at the expense of or with damages to intention; and, if not, whether it was due to mistake, fraud, inequitable conduct or accident.
another. The principle of unjust enrichment essentially contemplates payment when there is While intentions involve a state of mind which may sometimes be difficult to decipher,
no duty to pay, and the person who receives the payment has no right to receive it.28 By subsequent and contemporaneous acts of the parties as well as the evidentiary facts as
requiring BFC to pay the full contract price when it only supplied deckforms which covered proved and admitted can be reflective of one's intention.31
only 5,149.85 contact square meters of formworks, the CIAC Arbitral Tribunal is essentially
unjustly giving unwarranted benefit to Form-Eze by allowing it to earn more than it legally and BFC relies on the Form-Eze Proposed SM Marikina Mall Project Elevated Beam and Slab
contractually deserved. It is also worth mentioning that Form-Eze had in fact only been Formwork dated 7 December 200632 to support its contention that Contract No. 1 should
claiming for the contact area where its equipment was used. have a provision on the cost of labor. Indeed, in the aforementioned proposal, BFC has
agreed "to furnish the labor required for fabrication and assembly of the forming equipment"
Therefore, using the computation of BFC, the amount of contact square meters that the and that "BFC will deduct from the total contract amount 50.00 per man-hour each carpenter
delivered hardware and deckforms can handle is: or laborer supplied to Form-Eze." Notably, Contracts No. 2 and 3 contain labor-guarantee
provisions considering that BFC has committed to provide the necessary labor for both
126,000 sq. m. x contracts.
ATTY. D. MORGA, JR. (COUNSEL-RESPONDENT): You mean no former workers of the The cost for x-bracing amounts to P358,250.00 as evidenced by the receipt issued by
Claimant were employed for the purpose. Comer.35
MR. R.V. CLEMENTE (CLAIMANT): No.33 The costs of labor are as follow:
Obviously, BFC would want to be compensated for the labor it provided to Form-Eze as Contract No. 1 = P453,294.50
shown in Contracts No. 2 and 3.
Contract No. 2 = P1,373,634.60
As a matter of fact, Mr. James Franklin, the President of Form-Eze conceded that Contract
No. 1 should be modified to include a labor-guarantee provision, to wit: Contract No. 3 = P273,240.00
Q: Mr. Witness, respondent [BFC], in their counterlcaims, would like this Commission to Obligation of BFC under Contract No. 1:
reform Contract No. 1 to include a provision that it should deduct from your billing the cost of
92,696.40 contact square meters x P225.00 = P20,856,690.00
P11,857,317.45 The CIAC had correctly noted the ambiguity in Contract No. 3, particularly the "sufficient
number of column forms as required to complete six (6) poured in place columns per day."
The Memorandum of Agreement dated 5 January 2007 is an exclusive licensing agreement. For BFC, the sufficient number of column forms is 12 sets a day while Form-Eze considered
its supply of six (6) full height built up column forms as sufficient. The CIAC found that Form-
BFC avers that CIAC erred when it stated the BFC was given the exclusive license to Eze failed to comply with the requirements under Contract No. 3, hence it merely awarded
manufacture Form-Eze's equipment consisting of scaffoldings and accessories and they Form-Eze 2/3 of the minimum contract amount at P2,153,666.67.
became part of that provided by Form Eze to BFC.
We find that the CIAC's award lacked bases. It gave credence to the methodology used by
At the outset, we agree that the subsequent Memorandum of Agreement executed by the Form-Eze and noted that the latter had supplied six (6) full height built-up columforms, albeit
parties on 5 January 2007 is an exclusive licensing agreement. It was signed by both parties insufficient. We hold the contrary. The methodology used by BFC, which involves
wherein BFC has agreed to sell the scaffolding frames and accessories it manufactured to "columnforms with window openings and that from its installation, alignment, bracing,
Form-Eze at the end of the project. This Agreement was incorporated in Contract No. 4 inspection, approval of alignment, verticality and rigidity of the erected columnforms, pouring,
wherein BFC will be allowed to deduct P6,352,500.00 from the equipment lease contract, drying and removal of the forms, it will require twelve (12) column forms a day, should have
which is presumably Contract No. 1. At this point, Contract No. 4 is deemed to have novated been considered. The CIAC itself had already ruled that the ambiguity in Contract No. 3
the obligation of BFC with respect to furnishing all scaffoldings. Contract No. 1 states that should not favor Form-Eze, the party who prepared the contract. Thus, it is only logical that
BFC shall furnish the scaffoldings at no cost to Form-Eze. On the other hand, Contract No. 4 the methodology employed by BFC should be credited.
requires BFC to sell the scaffoldings to Form-Eze at the end of the project and deduct the
cost of the same from the contract price of Contract No. 1. This setup cannot in any way be Using 12 column forms as the minimum requisite and Form-Eze having supplied only four (4)
interpreted as part of the deckform supplied by Form-Eze. As pointed out by BFC, the usable column forms, it can be established that the delivered column forms can only be used
scaffoldings and accessories were the responsibility of BFC under Contract No. 1. Thus, the for 1/3 portion of the 9,100 contact square meters or 3,033.33 contact square meters. It was
manufactured hardware under Contract No. 4 could not have added to the deckform system further proven by BFC that about 50% of the column form requirements of the project were
because they are not the equipment of Form-Eze had obligated itself to supply under already completed with the use of their own equipment. Thus, it is but equitable that the
Contract No. 1. 3,033.33 contact square meters be further reduced by 50% or 1,516.67 contact square
meters. BFC is then liable to pay P441,502.87 broken down as follows:
Obligation of BFC under Contract No.2
1,516.67 X P355.00 = P 538,417.85
BFC maintains that since Form-Eze failed to meet the minimum conditions under Contract
No. 1 where the minimum 126,000 contact square meters were not reached, then the forklifts Less: Cost of Labor 96,915.00
under Contract No. 2 were also not used for a minimum of 126,000 contact square meters.
__________
We agree. BFC is liable only to pay the amount proportionate to 92,696.40 contact square
meters at P50.00 per contact square meter, the rental rate for the forklifts. Thus: SUBTOTAL:
Less: Payments made- 990,000.00 BFC is obliged to pay rental for u-heads under Letter-Agreement dated 5 January 2007.
BFC President should not be included as party to this case? Under Letter-Agreement dated 7 January 2007: 560,000.00
Section 4 of Executive Order No. 1008 vests jurisdiction on CIAC over disputes disputes _____________
arising from, or connected with, contracts entered into by parties involved in construction in
the Philippines, whether the dispute arises before or after the completion of the contract, or GRAND TOTAL: P15,217,262.82 and 50% of the Cost of Arbitration.
after the abandonment or breach thereof. Moreover, the party involved must agree to submit
to voluntary arbitration. In other words, anyone who is not a party to the contract in his SO ORDERED.
personal capacity is not subject to the jurisdiction of the CIAC. In this case, Pineda signed the
challenged contracts in his capacity as President of BFC. There is no indication that he
voluntarily submitted himself as a party to the arbitration case. In fact, he has been
consistently contesting his inclusion as a respondent in the CIAC proceedings. CIAC however
considered Pineda as a joint tortfeasor, thus justifying his joinder as a co-defendant.
We do not consider the imputed acts of Pineda as an indicia of bad faith to classify him as a
joint tortfeasor. First, it was proven that Form-Eze is not entitled to all its monetary claims
under the contract. Second, we have also subscribed to BFC's position that Contract No. 1
should have included a labor guarantee provision and that it was by mistake that said clause
was excluded. Third, BFC's alleged refusal to return the u-head assemblies and heavy duty
bases was meted with a heavy penalty in the form of a huge rental fee. BFC had, as a matter
of fact, admitted to owing Form-Eze rental payment. Fourth, the claim of threat against Form-
Eze's President is unsubstantiated and uncorroborated.
The controversy essentially boils down to the interpretation and factual application of the
existing contracts. Neither party was able to prove bad faith in their dealing with each other.
Under Article 2208 of the Civil Code, attorney's fees may, among others, be recovered where
defendant acted in gross and evident bad faith in refusing to satisfy the plaintiff’s plainly valid,