ITB Lecture
2011
Reference:
1. Das, Braja M., Principles of Geotechnical Engineering, Brooks/Cole, USA, 2002.
CHAPTER 12
2. The Canadian Foundation Engineering Manual, 2006
’h = K ’v
1
9/28/2013
Lp >> La
At Rest, Ko
• Jaky, 1944 (good for loose sand)
Ko = 1 –sin ’
• Sherif, Fang, 1984 (dense sand)
Ko = 1 –sin ’ + 5.5 [ (d/d min) ‐ 1]
• Massarsch, 1979 (NC clays)
Ko = 0.44 + 0.42 [PI(%)/100]
• OC Clays: Ko, OC = Ko NC OCR
2
9/28/2013
Practice on Partially Submerged Wall
• Practice on board!!
• See example 12.1 in text book.
3
9/28/2013
4
9/28/2013
5
9/28/2013
X
6
9/28/2013
The Pole Method
(q,q) a
POLE
a
b
a b = a
a
b
b
(p,p)
Watch for the sign
convention
Switch to 35 mm screen
Rankine Ka – The Pole Method
v
A
h
A ff
h h h v
POLE ff
A
7
9/28/2013
Rankine Kp – The Pole Method
v
A
h
A
h v h h
ff
A POLE
ff
Rankine Ka
45o + ’/2
c’/tan ’ (’v + ’h)/2 ’’
v
h
ff
c’
’ (90o+’)/2
’h ’v
(90o‐’)
ff
’ POLE (’v ‐
( ’h)/2
)/2
sin ’ =
c’/tan ’ + (’v + ’h)/2
8
9/28/2013
Rankine Kp
45o ‐ ’/2
c’/tan ’ (’v + ’h)/2 ’
v
h
ff
c’ (90o‐)
’
’v ’h
’ff
POLE (’h ‐
( ’v)/2
)/2
sin ’ =
c’/tan ’ + (’v + ’h)/2
Why Effective Stress??
• ’ = t – u
• utot = uhydro static + uexcess
• h’ = K x v ’ h = K x v’ + utot
K < or > 1:
h = K x v
h = K x v’ + K x utot
9
9/28/2013
Practice in Class with p.384
q [F/L2]
‐ +
Rankine Active with Sloping Backfill
’v = ’ h
10
9/28/2013
Do the passive exercise!!
’v = ’ h
Coulomb’s Active Pressure
11
9/28/2013
12
9/28/2013
Culmann’s solution of Coulomb
13
9/28/2013
14
9/28/2013
15
9/28/2013
16
9/28/2013
17
9/28/2013
18
9/28/2013
19
9/28/2013
20
9/28/2013
Coulomb’s Passive Pressure
21
9/28/2013
Coulomb’s Passive + EQ
0 5 ’ H2 ( 1 – kv) Kp’
Ppe = 0.5
22
9/28/2013
Log Spiral Failure Plane
23
9/28/2013
24
9/28/2013
25
9/28/2013
26
9/28/2013
27
9/28/2013
Caquot & Kerisel
Active and Pasive Coefficients
28
9/28/2013
Morrison & Ebeling 1995
29
9/28/2013
Braced Cuts
From Canadian Foundation Engineering Manual, 4th Ed, 2006
30
9/28/2013
31
9/28/2013
32
9/28/2013
Peck et al.
Teng
Wayne Teng
33
9/28/2013
Catatan FXT:
Hanya betul
kalau
Ka = 1;
dan
conservative
kalau negative
pp
Catatan FXT:
Cideng:
( H + q) / cb =
(90 + 40)/ (0.25 x 6
x 5) = 17!!
SF Base heave:
5 x 7.5 ~ 15
/(
/(90+40) )
= 0.3 to 0.6
34
9/28/2013
British Practice (Tomlinson, Foundation Design and
Construction, 7th Ed, page 421)
35
9/28/2013
36
9/28/2013
37
9/28/2013
38
9/28/2013
39
9/28/2013
40
9/28/2013
41
9/28/2013
42
9/28/2013
43
9/28/2013
T. Priok Basin 1
+ Built 1877‐1883
+ Quay L= 1100 m, D = 7.5 m
+ 1910 Dredged to 8.5 m
spoil dumped on East side,
helping reduce the malaria
inhabited swamps. In 1908,
out of 139 servicemen, 14 died
of malaria.
44
9/28/2013
45
9/28/2013
46
9/28/2013
Dubai Infinity Tower 2007
..and one day the workers heard a loud crack and felt the
movement, and saw sand coming in, and then water…
47
9/28/2013
…2 minutes later ..
…. 4 minutes later
48
9/28/2013
…at the end …
49