BOQ Surveyed Omitted BOQ Amount

BOQ
Description Unit Quantity Quantity Quantity
No
(m) (m) (m) LOCAL (LKR) FOREIGN (Euro)

3.0 Raw Water Transmission System

Approximately 1.0km long DI/PE raw water transmission main from Iginimitiya
3.1 reservoir to treatment plant site with suitable surge arresting system (not less m 1000 700 300 215,896.00
than 500mm dia)

Approximately 1.0km long DI/PE raw water transmission main from Iginimitiya
3.2 reservoir to treatment plant site with suitable surge arresting system (not less m 1000 700 300 9,404,230.00
than 500mm dia)

5.0 Clear Water Transmission System

Approximately 24km long clear water transmission main from Anamaduwa to


5.6
Mahakubukkadawala tower site with suitable surge arresting system to dilever m 24000 18000 6000 2,302,416.00
4,650meter cube per day quantity of water
Approximately 24km long clear water transmission main from Anamaduwa to
5.12 Mahakubukkadawala tower site with suitable surge arresting system to dilever m 24000 18000 6000 201,307,619.00
4,650meter cube per day quantity of water
Varied Amount due to changes in the lengths of Transmission main

Omission Variation
Description
LOCAL (LKR) FOREIGN (Euro) LOCAL (LKR) FOREIGN (Euro)

Omission due to raw water and Anamaduwa- Mahakumbukkawala transmission 49,427,801.59 595,546.70
main

52,385,950.47 1,142,887.23
Variation due to Mullegama to Anamaduwa junction transmission main
Balance to be paid as Variation 2,958,148.88 547,340.53
in SLRs 117,899,659.34