Nem Construction (PVT) LTD Monthly Costing Report - December 2019 Mahiyanganaya Plant Crushing Cost Summary
Nem Construction (PVT) LTD Monthly Costing Report - December 2019 Mahiyanganaya Plant Crushing Cost Summary
Nem Construction (PVT) LTD Monthly Costing Report - December 2019 Mahiyanganaya Plant Crushing Cost Summary
Cumulative Cost
Description Remarks
(Rs:)
Aug-19 Sep-19 Oct-19 Nov-19 Dec-19
Unit Cost Crushing Rs./Cube 908.62 799.92 784.51 780.33 791.16 799.61
Cumulative Cost
Description % of Total Cost
(Rs:)
Manpower 71.75 23.84 33.98 45.59 37.38 38.81 4.85%
Plant Diesel Cost 58.00 60.09 66.45 67.61 68.62 65.26 8.16%
Machinery 97.11 72.44 73.31 90.94 87.87 82.65 10.34%
Materials 550.00 550.00 550.00 550.00 550.00 550.00 68.78%
Overhead 131.76 93.54 60.77 26.20 47.28 62.89 7.87%
Total Cost 908.62 799.92 784.51 780.33 791.16 799.61 100.00%
Crushing Cost without materials 358.62 249.92 234.51 230.33 241.16 249.61