Work is planned at Charkop Depot to install an overhead electric system by April 15, 2020. As of January 25, 2020, 130 of the 174 planned mast foundations have been erected, with the remaining 43 held up due to stacked rail panels. Material delivery was completed on January 31, 2020 and mast foundation work was already finished. Erection of cantilever fittings is planned for February 20, 2020 along with subsequent conductor stringing, testing and inspection, leading to overhead power line charging and commissioning by April 15.
Work is planned at Charkop Depot to install an overhead electric system by April 15, 2020. As of January 25, 2020, 130 of the 174 planned mast foundations have been erected, with the remaining 43 held up due to stacked rail panels. Material delivery was completed on January 31, 2020 and mast foundation work was already finished. Erection of cantilever fittings is planned for February 20, 2020 along with subsequent conductor stringing, testing and inspection, leading to overhead power line charging and commissioning by April 15.
Work is planned at Charkop Depot to install an overhead electric system by April 15, 2020. As of January 25, 2020, 130 of the 174 planned mast foundations have been erected, with the remaining 43 held up due to stacked rail panels. Material delivery was completed on January 31, 2020 and mast foundation work was already finished. Erection of cantilever fittings is planned for February 20, 2020 along with subsequent conductor stringing, testing and inspection, leading to overhead power line charging and commissioning by April 15.
Sl. Description Target Date Remarks/Current Status
No. 1 Material Delivery 31.01.2020 Masts, Contact Wire, Catenary Wire & Cantilever Tubes delivered at site. 2 Completion of OHE mast Already Completed. - foundations 3 Erection of masts (174 25.01.2020 130 nos. has been erected. nos. masts) Balance 43 nos. is held up due to stacking of rail panels