Work planned for Charkop Depot

Sl. Description Target Date Remarks/Current Status


No.
1 Material Delivery 31.01.2020 Masts, Contact Wire, Catenary
Wire & Cantilever Tubes
delivered at site.
2 Completion of OHE mast Already Completed. -
foundations
3 Erection of masts (174 25.01.2020 130 nos. has been erected.
nos. masts) Balance 43 nos. is held up
due to stacking of rail panels

4 Erection of Cantilevers 20.02.2020 -


Fittings
5 Conductor Stringing 10.03.2020 -

6 SED Checking 20.03.2020 -

`7 EIG Inspection 25.03.2020 -

8 OHE Charging & 15.04.2020 -


Commissioning Date