23rd June, 2020

Design Status (Rajasthan)


Official Activity Internal Activity
Item Unit Qty
Qty Rev Date Days Status Date Days Person Remarks
Plan & Profile Km 28.1
Pavement Design Km 28.1
Box Culverts (34+2) No 36
SVUP No 13
Package‐1

LVUP No 8
VUP No 1
InterChange No 1
Boundary Wall Km 28.1
Service Road (1 No) Km 0.55
RE Wall @ 26+400 Km 2.25
Toe Wall/High Emb. Km 6.76
Plan & Profile Km 30 30 6 17‐Jun‐20 6 Modified P&P Submitted (Rev‐6) (Site‐109) 23‐Jun‐20 0 Pranshu Final reply to be sent along with Proof & Safety recommendations
Pavement Design Km 30 30 7 6‐Jun‐20 17 Rev‐6 Approved (AE‐127). Approved PDR (Rev‐7) Site‐95
Box Culverts (40+2) No 42 39 6 22‐Jun‐20 1 Final submission for 39/42 Box Culverts (Rev‐6) (Site‐115) 22‐Jun‐20 1 Lalit (s) GFC awaited from TL (Approved from LASA HO)
SVUP No 5 5 6 9‐Jun‐20 14 Final submission for all 5 SVUPs (Rev‐6) (Site‐100) 9‐Jun‐20 14 Lalit (s) GFC awaited from TL (Approved from LASA HO)
Observations on LVUP (33+250 & 39+450) Rev‐1
LVUP No 8 8 1 6‐Jun‐20 17 6‐Jun‐20 17 Jain Sir Compliance from Jain Sir awaited
Revised Geotech submitted (Site‐96) 6‐6‐20
Package‐2

1. Namrata 1. Review of 3 VUPs (45° Skew) awaited
VUP No 5 2 3 5‐Jun‐20 18 Submission of VUP @ 38+630 (R3) & 50+050 (R2) vide Site‐92 5‐Jun‐20 18
2. Lalit (s) 2. GFC awaited (2 VUPs 0° Skew) from TL (Approved from LASA HO)
InterChange No 1 1 0 10‐Jun‐20 13 Compliance & submission of R1 (Site‐102) 10‐Jun‐20 13 Lalit (s) GFC awaited from TL (Approved from LASA HO)
Boundary Wall Km 30 30 5 22‐Jun‐20 1 Revised Design & Drawing submitted (Rev‐5) via Mail 23‐Jun‐20 0 Lalit (s) Approval received from LASA. (Official letter from TL awaited)
WaySide Amenities No 1 1 0 10‐Jun‐20 13 Compliance to observations submitted (Site‐103) 10‐Jun‐20 13 Lalit (s) Approval Awaited from AE (Follow up from Site required)
Service Road (5 No) Km 2.96 1.45 0 12‐Jun‐20 11 SR & CR P&P for VUP @ 38+630 (Rev‐0) submitted (Site‐108) 12‐Jun‐20 11 Lalit (s) Approval Awaited from TL
RE Wall @ 52+350 Km 2.45 23‐Jun‐20 0 Pranshu Checklist received from GeoSys India
1. Prasanna 1. Revised & Additional Geotech Reports awaited from Prasanna
Toe Wall/High Emb. Km 21.82 21.82 1 11‐Jun‐20 12 Further observations received from AE (Rev‐1) 19‐Jun‐20 4 2. Anuj Sir 2. Inputs from Anuj Sir awaited (Also minimum length issue)
3. Kunal Sir 3. Material Specification from Vendor (As per CA) required
Plan & Profile Km 30 28.21 1 28‐Apr‐20 56 28.21 Km approved (AE‐104) 28‐Apr‐20 56 Anuj Sir Get approval of remaining 2 Km
Pavement Design Km 30
Box Culverts (32) No 32
SVUP No 10 12‐Jun‐20 11 Nitin Cross‐Road P&P awaited
Package‐3

LVUP No 8 12‐Jun‐20 11 Prasanna Geotech Reports received


VUP No 3 12‐Jun‐20 11 Prasanna Geotech Reports awaited
InterChange No 1
Boundary Wall Km 30
WaySide Amenities No 1 1 0 5‐Jun‐20 18 WSA Concept Layout submitted 5‐Jun‐20 18 Lalit (s) Approval Awaited from AE (Follow up from Site required)
Service Road (3 No) Km 0.95 0.3 0 12‐Jun‐20 11 SR & CR P&P for VUP @ 68+592 (Rev‐0) submitted (Site‐61) 12‐Jun‐20 11 Lalit (s) Approval Awaited from TL
RE Wall @ 75+300 Km 2.25
Toe Wall/High Emb. Km 20.30
Plan & Profile Km 28 28 3 15‐Jun‐20 8 Final P&P requested by AE as per finalised box culverts 23‐Jun‐20 0 Lalit © Send 3 Sets of Rev‐4 To Site
Pavement Design Km 28 28 4 15‐Jun‐20 8 Approved Pavement Composition received (AE‐438) 15‐Jun‐20 8 Anuj Sir Soil Tests sent. Compliance awaited
Box Culverts (29) No 29 29 3 9‐May‐20 45 Rev‐3 Approved (AE‐282) 23‐Jun‐20 0 Santosh Sample confirmed. Final Drawings awaited
SVUP No 11 11 3 5‐Jun‐20 18 Compliance and submission of Rev‐3 5‐Jun‐20 18 TL Approval Awaited
LVUP No 7 7 2 26‐May‐20 28 Comments on LVUP (Rev‐2) (Retaining Wall Approved) 26‐May‐20 28 Jain Sir Compliance awaited from Jain Sir
Package‐5

VUP No 3 1 1 26‐May‐20 28 Compliance & Revised submission of VUP 137+901 (R1) 6‐Jun‐20 17 TL Approval/Observations Awaited (Remaining will be submitted after)


InterChange No 3 3 0 23‐May‐20 31 Observations on InterChange received (AE‐327) 19‐Jun‐20 4 Tushar Compliance/Revised Designs & Drawings awaited
1. AP Singh 1. Geotech Reports awaited
MNB No 1 1 0 16‐Jun‐20 7 COS details requested by AE to issue COS Notice 18‐Jun‐20 5
2. Tushar 2. Topo levels sent to Tushar
ROB No 1 1 1 3‐Jun‐20 20 Compliance & MNIT drawings submitted (Site‐95 & 96) 18‐Jun‐20 5 Sandeep P Signed & Stamped Checklist awaited
Boundary Wall Km 28 28 3 22‐Jun‐20 1 Observation on Boundary Wall Design (Rev‐3) (AE‐479) 22‐Jun‐20 1 Jain Sir Compliance & Revised Design required
RE Wall @ 122+000 Km 2.45
Toe Wall/High Emb. Km 12.12 12.12 0 21‐May‐20 33 Rev‐0 Submitted vide Site‐84 5‐Jun‐20 18 TL Observations/Approval Awaited
Plan & Profile Km 29.66 18‐Jun‐20 5 Nitin Revised FRL & GL awaited
Pavement Design Km 29.66
Box Culverts (35) No 35
SVUP No 12
LVUP No 4
Package‐6

VUP No 5
InterChange No 1
MNB No 1
WaySide Amenities No 1 1 0 5‐Jun‐20 18 Approval of Conceptual Layout Plan for WSA requested 5‐Jun‐20 18 TL Approval Awaited
Service Road (4 No) Km 2.16
Boundary Wall Km 29.66
RE Wall @ 150+900 Km 2.25
Toe Wall/High Emb. Km 23.02
Plan & Profile Km 24 24 0 19‐Jun‐20 4 Submitted Soft copy of complete P&P (Rev‐0) via mail (PM) 19‐Jun‐20 4 Lalit (s) Approval/Review awaited from TL
Pavement Design Km 24
Box Culverts (36+5) No 41 37 0 18‐Jun‐20 5 Lalit (s) Designs & Drawings (Rev‐0) sent to Site
SVUP No 11 20‐Jun‐20 3 Balaji Geotech Reports awaited
Package‐3/3

LVUP No 4 20‐Jun‐20 3 Balaji Geotech Reports awaited


VUP No 3 20‐Jun‐20 3 Balaji Geotech Reports awaited
Looney MJB No 1
MNB No 1
ROB No 1
WaySide Amenities No 1 1 0 5‐Jun‐20 18 Approval of Conceptual Layout Plan for WSA requested 5‐Jun‐20 18 TL Approval Awaited
Service Road (1 No) Km 0.8
Boundary Wall Km 24
Toe Wall/High Emb. Km 9.20

NHAI NKC Projects Pvt. Ltd.