Floating Aerators Covering Aquafen: Technical Specifications Installation, Maintenance, Starting Up, and Warranties

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

EUROPELEC

FLOATING AERATORS COVERING

AQUAFEN

TECHNICAL SPECIFICATIONS INSTALLATION,


MAINTENANCE, STARTING UP, AND WARRANTIES

IMPORTANT

DO NOT CLIMB ON THE FLOAT.

FLOATING AERATORS COVERING


Page 1 -
EUROPELEC 15, rue de la Banque – 75002 Paris – France – Tel. +33 (0)1 44 82 39 50 – Fax +33 (0)1 44 82 39 51
– e-mail : info@europelec.com - www.europelec.com
MAINTENANCE MUST BE CARRIED OUT FROM THE BANK OR A BOAT

1 COVERING FOR FLOATING AERATORS AQUAFEN

COVERING COMPOSITION:
The covering is made of:
The square central funnel
The 4 central sections
The 4 small sections
The four links between Aquafen float and covering and covering between the bank and
4 slings with 8 shackles
The 8 lifting plates for covering with diameter of 8 m
The 8 lifting counter plates for covering with diameter of 8 m
8 slings for the lifting with the crane for covering with diameter of 8 m

1.1 INSTRUCTIONS FOR ASSEMBLY AND HANDLING


1.1.1 COVERING HANDLING:
Each segment is handled manually by using two people.
When the covering is fully assembled, handling will be imperative made by 8 points for
covering with diameter of 8 m and by 4 points for smaller diameters.
Do not handle otherwise.

1.1.2 COVERING ASSEMBLY :


First you should choose a location where the soil is regular.
Put in place that will be the center of the covering a box or trestles of following heights:
Height of around 1.3 m for covering with diameter of 8 m
Height of around 1.2 m for covering with diameter of 7 m
Height of around 1.1 m for covering with diameter of 6 m
The box or the trestles will be used to facilitate the assembly of the covering.
Put the top of one of the four central sections (the straight part) on the box and screw
over the square central part. The bolt will be as follows: a large-large washer on each
side of the screw and for tightening some nuts Nylstop.
Then put in turn the other central sections and bolted together and also on the square
central part.
ATTENTION: you have to raise the box or trestles for coupling the sections together
(do not bring closer with the screws because the final parts will be difficult to assembly
in this case).
When the 4 central sections are completely assembled then you can put the 4 small
sections. Bolt to the central sections.
FLOATING AERATORS COVERING
Page 2 -
EUROPELEC 15, rue de la Banque – 75002 Paris – France – Tel. +33 (0)1 44 82 39 50 – Fax +33 (0)1 44 82 39 51
– e-mail : info@europelec.com - www.europelec.com
1.1.3 ASSEMBLY OF COVERING WITH A DIAMETER OF 8 M:
Attention, do not forget to put the 8 lifting plates and the 8 lifting counter plates on the
3rd and 4th holes of the steep part (for covering of 6 or 7 m diameter, the sling will be only
made by only 4 points. Lifting rings are provided at the center of the 4 central sections,
and so there are no lifting plates).
Do not climb on the covering. Install on those plates the 8 lifting slings provided.
Put the 4 slings at 90 ° on the Aquafen thanks to 4 shackles.
Fit the 4 linking plates on the slings thanks to 4 other shackles. Plates must absolutely
be equidistant from the float on the four slings. Then secure the machine Aquafen to the
bank. Attach the motor cable to one of the four slings but being careful to make a loop
that plunge into the water at the point of connection plates.
The plates will be the guide point of the deposing of the covering with the crane.

Be careful to center the covering on the top of the Aquafen otherwise you will split the
covering with the Aquafen motor.

With the help of rigging plates, center the covering to 1 meter above the water level
then when the visual center is correct (the 4 linking plates are equidistant from the
covering), put the covering on the water.
With the help of a boat, fix on the covering the 4 linking plates with two screws per
plate. Remove the 8 handling slings.

Lifting plates + counter plates

FLOATING AERATORS COVERING


Page 3 -
EUROPELEC 15, rue de la Banque – 75002 Paris – France – Tel. +33 (0)1 44 82 39 50 – Fax +33 (0)1 44 82 39 51
– e-mail : info@europelec.com - www.europelec.com
Linking plates

1.1.4 ASSEMBLY OF COVERING WITH A DIAMETER OF 7 M OR


LESS:
For covering with a diameter of 7 m or less, the sling will be only made by only 4
points; lifting rings are provided at the center of the 4 central sections.

Do not climb on the covering. Install on the lifting rings at the center of central sections
the 4 lifting slings that the crane operator has (in general they have chains).
Put the 4 slings at 90 ° on the Aquafen thanks to 4 shackles.
Fit the 4 linking plates on the slings thanks to 4 other shackles. Plates must absolutely
be equidistant from the float on the four slings. Then secure the machine Aquafen to the
bank. Attach the motor cable to one of the four slings but being careful to make a loop
that plunge into the water at the point of connection plates.
The plates will be the guide point of the deposing of the covering with the crane.

Be careful to center the covering on the top of the Aquafen otherwise you will split the
covering with the Aquafen motor.

With the help of rigging plates, center the covering to 1 meter above the water level
then when the visual center is correct (the 4 linking plates are equidistant from the
covering), put the covering on the water.
With the help of a boat, fix on the covering the 4 linking plates with two screws per
plate. Remove the 4 handling slings.

2 INSTRUCTIONS FOR STORAGE AND HANDLING

2.1 STORAGE
Store the elements in a place where they cannot receive shocks.

FLOATING AERATORS COVERING


Page 4 -
EUROPELEC 15, rue de la Banque – 75002 Paris – France – Tel. +33 (0)1 44 82 39 50 – Fax +33 (0)1 44 82 39 51
– e-mail : info@europelec.com - www.europelec.com
2.2 HANDLING
It goes without saying that the bodies handling equipping the covering are designed for
its own weight and should not be used to lift the entire machine, only the covering must
be handled with plates or lifting rings.

FLOATING AERATORS COVERING


Page 5 -
EUROPELEC 15, rue de la Banque – 75002 Paris – France – Tel. +33 (0)1 44 82 39 50 – Fax +33 (0)1 44 82 39 51
– e-mail : info@europelec.com - www.europelec.com
WARRANTY

The one year warranty is restricted to repair free of charge or replacement free of charge (as decided by
the manufacturer or his representative) of parts recognized as defective, without any other service or
compensation. Supply free of charge of spare parts is "ex-factory" from the manufacturer's plant, the
manufacturer being entitled to request the return FOB to his plants of the parts replaced or to be replaced.

1- START OF THE WARRANTY

The warranty starts on the date of the delivery voucher or, in the event of extended storage, the date of the
availability voucher.
The terms of the warranty may have been negotiated when the order was placed. In this case, only the
written clauses of the order explicitly accepted by our services are applicable.

2- WARRANTY CONDITIONS

In order for the warranty to be effective on the equipment, certain conditions must mandatorily be complied
with, i.e.:
- The installation of the aerators must comply with the drawings contained in this booklet.
- Their maintenance must be performed in compliance with the instructions of this booklet.
- The motor protection must be provided in compliance with prevailing standards to prevent overheating
and overload of the motor.
- The thermal micro switch probe wired in the motor must be connected to a relay allowing trip of the
motor: shutdown.
- In an installation including several aerators, separate protection for each motor is mandatory.
- The electrical connection cables must be normally sized.
- Maintenance and in particular lubrication must be carried out according to our instructions (see the
section "Maintenance")
-In all cases, we do not act, except in response to a written request (mail, telex, fax )

3- RESTRICTIVE CLAUSES

Repair, modification or replacement of parts during the warranty does not extend the warranty period on
the equipment.

- The warranty is rendered null and void if the buyer undertakes repair or modification on his own initiative.

- In all cases, when handling of the aerators requires hoisting gear, this gear must always be supplied to
our crews by the customer. In the event we have to rent the hoisting gear ourselves, the cost will be
refunded to us by the customer.

4- VARIOUS CLAUSES

No claims are receivable more than ten days after the reception of the equipment by the customer.

- The drawings or preliminary projects communicated to our customers remain our property and must be
considered as confidential.
- The transfer of property of the goods sold will not become effective until the full agreed price has been
paid (law n° 80335 dated May 12,1980)
- No works can be performed under warranty before the transfer of property.

FLOATING AERATORS COVERING


Page 6 -
EUROPELEC 15, rue de la Banque – 75002 Paris – France – Tel. +33 (0)1 44 82 39 50 – Fax +33 (0)1 44 82 39 51
– e-mail : info@europelec.com - www.europelec.com