PHARMA GENERAL MODIFICATION

1. mixing to holding tanks shall have a bleed or recirculation this will be need so as to maintain the
homoginity of the mixture.

2. holding to filling tanks shall have a bleed/ recirculation this will be need so as to maintain the
homoginity of the mixture.

3. Sprayball to be design as a jet nozzle and to have a recirculated line to be tapped into the its
corresponding main pump.

4. All of the existing pumps shall be reevaluated(new design na) and to be changed in to hygienic design
for easy access in cleaning,

5. Due to the different bleed point in CIP and for recirculation concerning the homogeneity pumps will
br reevaluated

6. holding tanks concerning the homogeneity shall be tapped with sampling connections 3 levels

7. METSAL material to be used, TANK FARM HOLDING TO DAY TANK (pump is to be pvdf dual diaphragm
pump , piping material is PVDF) DAY TANKS TO MIXING TANKS (same) MIXING TANKS TO NEXT
DESTINATION (ss pump and pipe)

8.AIR BLOWER SYSTEM kami na bahala sa pagcalculate nito basta lahat ng may steaming

9. Additonal eucalyptus oil day tanks (confirm the capacity)

10. hydraulic crusher to be designed for the camphor

11. parallel filters for the essence tanks.

12. no existing pump is available for the hot water system (is this still applicable)

13. camphor minimal exposure to air

14. check cip specially for the viscous fluids

15. salicylic material compatibilty checking

Mga utang ko sila maam cristel and maam elena.


mga pinangako ko na bibigay namin

1. nitrogen lines na gagawin na nating nitrogen talaga lalo na sa purging

2. kay stew papaproceed na namin na gumamit nalang ng stainless na material sa mga tanks.

3. ung mga list ng idadagdag per line na equipment

4. emv pa finalize narin ng mga kailangan natin na mga files lalo na sa mga filter.
5. hbg to finalize ng mga list ng mga pumps na to be evaluated once finalized na then within up to 16
makapagsend ng revised na datasheet kasama ng answers sa lahat ng concerns para sa tq narin natin
para sa mga positive displacement na pumps.

6. PID update with regards to the changes in every line.

7. review the methyl salicylate raw mats and then give them feedback about the materials that are
acceptable to be used a parent material for the mixing tanks.

8. siemps ung additional tanks kailangan natin iclarify kila maam cristel para mas maging ok na rin lahat
per line to. so bukas ng gabi finalize ko lahat for line 1 and 2. with PID na dapat un para sa alignment
natin sa prod. kailangan nantin mafinalize to para hindi narin maging sobrang hirap para sa lahat ang
mga mangyayari naito hahaha

9. review the pressure tanks that was discussed in the soapoery DI water. if this is also applicalbe in the
pharma.

10. electric tracing for Soapery, Pharma

11. Design ng hydraulic press.

12. design ng pharma ointment tanks without incorporated na pumps in between. review any possible
effects.

13. Alcohol tanks clarifiy the max cap.

14. review the controls for each and everything line per line.