Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

NOTES

1. EACH BANK IS TO HAVE ALL NEUTRALS,ARRESTORS


& CAPACITOR RACK CONNECTED TO THE POLE GROUND.

2. CAPACITOR NEUTRAL CONNECTION MUST


BE GROUNDED.

3. GROUND CONTROL BOX TO POLE


GROUND (SEE GROUNDING
INSTRUCTIONS ON PAGE 1230).

4. SECONDARY POWER FOR THE


CONTROL MUST ORIGINATE FROM
THE SAME CIRCUIT TO WHICH THE
CAPACITOR IS CONNECTED (
i.e.
NO SWITCHES BETWEEN TRANSFORMER
AND CAPACITOR BANK).

3’-0"
5. DIMENSION VARIES WITH MANU-
FACTURER. MEASURE RACK BEFORE
BORING BOTTOM HOLE.

6. 20 FOOT CONTROL CABLE INCLUDED


IN COMPATIBLE UNIT. 5’-10"

7. LOCATE CONTROLS ON OPPOSITE


SEE NOTE 5
SIDE OF POLE FROM BANK.

8. CUSTOMER OWNED/SRP MAINTAINED


CAPACITOR SHALL BE MARKED WITH
THE CB NUMBER FOLLOWED BY AN
"F" (i.e. CB 123F)

CAP. TRANSFORMER
C.U. BANK SIZE
UNITS INCLUDED

CA132 1350 KVAR 10 NO

CB
007
SEE NOTE 3
9’-0" MAX.
8’-6" MIN.

FINAL GRADE

REV.FORMAT 8512E48.DGN
OVERHEAD DISTRIBUTION
CONSTRUCTION STANDARDS 22kV CAPACITORS ISSUE DATE: 09/15/88

R
REV. DATE: 08/01/99
1350 KVAR
SWITCHED BANK APPROVAL:

PROPRIETARY MATERIAL CA132 1301


PRIMARY FUSES FOR DISTRIBUTION CAPACITOR BANKS

3 Phase Capacitor 12.47 / 21.6 kV Wye


Bank Size with Primary Neutral

KS 40 Fitall
1350 kVAR
(60-2950)

1302
DATE: 3-23-94 Overhead Distribution
REV. NO.: 1
CAPACITORS Construction Standards
REV. DATE: 1-30-94
PROTECTIVE EQUIPMENT AND FUSING
APPROVAL:
21.6kV CAPACITOR FUSES
1302 PROPRIETARY MATERIAL
TEST ALL NEWLY CONSTRUCTED CAPACITOR BANKS BEFORE PLACING IN SERVICE
TEST ALL CAPACITOR BANKS AFTER REPLACING FAILED TANKS

1. DE-ENERGIZE CAPACITOR BANK WITH AUTOMATIC CONTROL OR BY OPERATING


LINK BREAK CUTOUTS.

2. DISCONNECT PRIMARY STINGERS AND WAIT 5 MINUTES FOR CAPACITOR TO DISCHARGE.

3. USING HOT STICK AND TEMPORARY JUMPERS, SHORT ACROSS AND GROUND EACH OF
THE THREE GROUPS OF CAPACITORS.

4. REMOVE THE JUMPERS AFTER A PERIOD OF 5 MINUTES HAS ELAPSED.

5. MAKE A VISUAL INSPECTION OF ALL CAPACITORS. CHECK FOR BROKEN BUSHINGS,


BULGING TANKS, AND OBVIOUS OIL LEAKS.

6. REMOVE THE LINE SIDE CONNECTION OF EACH CAPACITOR. IT IS NOT NECESSARY


TO REMOVE THE NEUTRAL CONNECTION.

7. USING A CAPACITANCE METER*, MEASURE THE CAPACITANCE BETWEEN THE PHASE


AND THE NEUTRAL TERMINALS OF EACH CAPACITOR. A READING FROM EACH TANK IS
REQUIRED. IF THE MEASURED VALUE OF THE CAPACITANCE IS NOT IN THE ACCEPTABLE
RANGE, AS SHOWN BELOW, THE CAPACITOR IS BAD ORDER AND MUST BE RPLACED.

ACCEPTABLE CAPACITANCE VALUES (MICROFARADS)

CAPACITOR MINIMUM NOMINAL MAXIMUM


SIZE (kVAR)
150 2.30 2.56 3.07

8. WHEN SHIPPING CAPACITOR TANKS, A PIECE OF CONDUCTOR SHALL BE INSTALLED


FROM THE BUSHING TO THE TANK GROUND (OR BETWEEN THE BUSHINGS ON TWO
BUSHING TANKS).

9. LOW VOLTAGE FUSES IN THE CONTROL UNIT ARE:

SANGAMO - 10 AMP SLOW - BLOW FNM10 - BUSSMAN (0601408)

FISHER PIERCE - 5 AMP SLOW - BLOW FNM10 - BUSSMAN (0601407)

FISHER PIERCE RADIO CONTROLLED - 10 AMP SLOW - BLOW - BUSSMAN


FNM10 - (0601408)

HD ELECTRIC PAGER CONTROLLED - 15 AMP SLOW - BLOW - BUSSMAN,


MDA-15 OR LITTLE FUSE 326015P
(0601409)

10. INSTALL ALL NEW PRIMARY FUSES AFTER REPLACING ANY OF THE TANKS. A FAULT
THAT BLOWS ONRE FUSE GENERALLY WEAKENS THE OTHER TWO.

NOTE: THE FIRST FOUR STEPS OF THE ABOVE PROCEDURE MAY BE OMITTED FOR NEW
INSTALLATIONS THAT HAVE NEVER BEEN ENERGIZED.

*CAPACITANCE METER REPLACES THE PREVIOUSLY USED SIMPSON METER FOR CHECKING
CAPACITORS.

REV. RENUMBER AND PUT ON CAD 8512E435.DGN


Overhead Distribution
Construction Standards CAPACITORS ISSUE DATE: 08/02/93

R PROCEDURE FOR TESTING


REV. DATE: 07/30/08
DISTRIBUTION CAPACITOR BANKS
RATED 12.47kV FOR 22kV SYSTEM APPROVAL:

1303

You might also like