ANEJA CONSTRUCTIONS INDIA LIMITED

COMPANY PROFILE

Committed to Excellence

www.acil.co.in
FROM MANAGING DIRECTOR DESK

We have Incorporated Our Company 20 years ago when we Had mission for

“Committed to Excellence”

We knew that with every Project we Complete, we would be building a name.

With every new project we would be building something that we hold very dear

to ourselves: Our reputation.

And to build that, we knew we would have to build with values. This is why with

over 120 Site Completed over 20 years we have had but one blueprint, one

mantra for success.

Build not with bricks, mortar, steel or glass but with values that add worth. Build

with uncompromising quality that keeps the worth of your investment high as

time goes by. Keep promises and deliver on time .

It is because of this that we have partnered with some of the leading names in

Construction and Power Plant Industry . It’s why we have endeavoured to bring

you not just the highest standards but new benchmarks..


CONTENTS
1. Company Profile
❖About Us
❖ISO 9001-2008 Certification
❖Certificate of Incorporation
❖ HSE Policy

2. Experience
❖Our Clientele
❖Project Completion Certificates
❖Projects Undertaken
❖Current Projects
❖ Projects Completed
❖Snapshots of Prestigious Projects

3.Financial
❖Details of Turnover : 2013 – 2017
❖Balance Sheet 2013 – 2017

4. Plant & Equipments

5. Other Information
❖Our Specialties
❖Recognition
❖Quality Control at Project Site
❖Safety Control
❖Safety Appreciation from Clients
❖ About ACIL

❖ ISO 9001:2008 Certification

❖ Certificate of Incorporation

❖ Class I : Certificate

❖H.S.E. Policy
ABOUT ACIL

ACIL has carried out various construction jobs under his own direct supervision
and personal control. The works include earth work for Fiat Ltd, canal lining
works, river and canal protection works with self‐owned machinery. Important
works of Hydel Projects, intricate concrete structures, Thermal Power Plant etc
.were executed gaining rich experience in canal construction works, Coal
handling plants aqueducts, bridges, industrial & residential buildings.
Several works with huge quantity have been executed under this name and
style i.e. M/s. Aneja Constructions India Limited . We expanded our field from
irrigation works to construction of road works by obtaining our own Plant ,
Paver finisher and other relevant machinery block of years, required for Road
works and Civil Works.
We have the capacity to mobilize manpower and equipments for all kinds of civil
works of any magnitude. We have our own fleet of heavy earth moving
equipments which includes TATA Hitachi, Hyundai , Caterpillar, excavators,
Dozers, Vibrator / Road rollers, Dumpers, Batching Plants , Transit Mixer ,Hot
mix Plant for road works, Paver Finisher and other construction as well as heavy
earth moving equipments.
We are assisted by a team of qualified and experienced engineers who are well‐
versed in execution of all kinds of civil engineering projects, with a stubborn
commitment to quality and project schedule to the entire satisfaction of all our
esteemed clients/consultants both national and international.
ISO 9001:2008 Certification
ISO 14001:2015 Certification
ISO 18001:2007 Certification
CERTIFICATE OF INCORPORATION
Class I Registration with PWD Karnataka
Class I Registration with PWD Karnataka
ACIL HSE Policy

Our HSE Policy is project oriented. We strive to achieve and meet


HSE requirements of our clients in both Public as well as Private
sectors during project implementation.

In recognition of our safe construction practices, and 3.63 Million


Man Hours of Lost Time Accident Free (LTA free) Site Management
during past15 years, we enjoy a preferential treatment from our
clients through repeat orders.

We are conscious of our responsibility towards mother earth and


environment. We work in an e-environment while encouraging our
employees and other associates to minimize use of paper and
optimize carbon emission through sensible use of fuel and power in
our operations.

We strictly adhere to HSE compliance enforced by Statutory


Authorities under Central as well as State Governments from time
to time.
2.EXPERIENCE

❖Our Clientele

❖Project Completion Certificates.

❖Projects Undertaken

❖Current Projects

❖Projects Completed

❖ Snapshot of Prestigious Projects


Major clientele
Our Clientele
ABAN CONSTRUCTIONS PVT LTD
BHARAT HEAVY ELECTRICALS LTD
BGR ENERGY LTD.
BRIDGE & ROOF CO. (I) LTD
DODSAL LTD
DOOSAN POWER SYSTEM INDIA LIMITED
ENERGO INDIA

ELECON EPC

GAMMON INDIA LTD

GANNON DUNKERLEY CO. LTD

GE POWER INDIA PVT LIMITED


GUJARAT TORRENT ENERGY
CORPORATION LTD
HINDUSTAN OIL EXPLORATION CO LTD
INDO GULF CORPORATION LTD. (BIRLA COPPER)
JAIPRAKASH ASSOCIATES
JMC PROJECTS (I) LTD
JUBILANT GROUP
KAEVENER CEMENTATION INDIA LTD
LARSEN & TOUBRO LTD
Our Clientele
NATIONAL THERMAL POWER CORPORATION LTD.
NORTH WESTERN RAILWAYS
ORIENTAL CIVIL ENGINEERING CO. LTD
PREMIER OIL CACHAR BV
PMGSY, MADHYA PRADESH & KARNATAKA
PREMIER OIL CACHAR BV

PUNJ LLOYD LTD

RAJASHREE POLYFIL LTD


RELIANCE PETROLEUM LTD
RITES LIMITED

SANGHI MOVERS LTD

SAURASHTRA CEMENT LTD


SIMPLEX INFRASTRUCTURE LTD.
SUZLON INFRASTRUCTURE LTD
THE INDURE LTD.
TECPRO SYSTEMS LIMITED
TRF LIMITED (TATA ENTERPRISE)
THYSSENKRUPP INDUSTRIES INDIA PVT LTD
VEDANTA
WELSPUN GROUP
COMPLETION CERTIFICATE
OF WORK DONE
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES
COMPLETION CERTIFICATES

23 of 60
COMPLETION CERTIFICATES

24 of 60
COMPLETION CERTIFICATES

25 of 60
COMPLETION
COMPLETIONCERIFICATES
CERTIFICATES

25 of 60
PROJECTS UNDERTAKEN (1 of 2 )

ROAD & HIGHWAY WORK

I) Industrial Road
WBM Road.
RCC Pavement & Bituminous Concrete Road.

II) Highway / State Road


Heavy Earth work, Embankment.
GSB and WMM Layers.

III) Pipeline
Trenching in Hard and Soft Road with Blasting and
Chiselling.
Civil works of Pump House for Pipeline projects.
PROJECTS UNDERTAKEN (2 of 2 )

INDUSTRIAL CIVIL & CONSTRUCTION


I) Power Plant
Foundations.
Railway Bridge, Culvert for Thermal power Plants.
Ash Pond.
II) General Civil Work
Foundations, Industrial Sheds, Rig Pads
Administrative and Utilities
Boundary Wall
III) Earth Work
Mass Earth work in Soft and Hard Rock .
Embankment Filling, Area Grading, Under Water.
Projects in Progress
Amount Completion
Work Details Clients Start Date Status
(Lakh) Date

Main Civil work for WFGD , 2*800


MW Telangana Thermal Power Work in
GE Power 1874.00 May 18 Jan 20
Plant Project , Ramagundam progress
,Telangana

Temporary Structure Work for


Track hopper Area and Wagon Work in
Doosan 2100.00 Mar 18 Mar 19
Tippler with SDA , Soldier Pile and progress
Ground Anchoring Method

Civil Work for CHS , 2*660MW ,


Work in
Obra C Thermal power Plant , Doosan 1960.00 Mar 18 Mar 20
progress
Obra Dam , Uttar Pradesh

Construction of Slime Dam at Tata Work In


Tata Steel 1040.00 Feb 2018 Mar 19
Steel , Joda – Orissa Progress

Construction of Water Reservior – Work in


Tata Steel 1851.00 Feb 2018 Dec 19
Tata Steel , joda –orissa Progress

Exectuion of Balance Civil Works


of Additional Coal handling Plant , Work in
TSGENCO 745.00 May 2018 Sep 18
KTPS , Chelpur , Bhupalpally – Progress
Telangna

Civil work of wagon tippler


Work in
complex : 3x660 MW CHP, stage – TRF limited 3500.00 Jun-16 Jun 18
Progress
I NPGC,Nabinagar , Bihar

Thermal Power plant - Civil work


Work in
of Wagon tippler , MCC building , Elecon
4200.00 Jan 15 Nov 18 Progress
TPs ,Stacker Reclaimer and Engineering
Finishing work of all buidling .
Projects Completed (1 of 6)
Amount Completion
Work Details Clients Start Date Status
(Lakh) Date

Civil Works of Additional CHP Energo


1259.00 Oct 15 Aug 17 Completed
& Wet Fly Ash Works Engineering

Talwandi Sabo Power plant -


Civil work of Flood Control
Vedanta 2000.00 July 16 Jan 18 Completed
System for Plant with Pond
Constructions

Balance Civil construction &


Architectural work for Ash
Melco India
Handling System at 3x660 1100.00 June 16 Feb 18 Completed
private Limited
MW Stage-I Unit# 1, 2 & 3
NTPC Barh, Patna, Bihar

Mechanised Earthwork in
SEZ,Gassification &
SIMP/ACIL/RIL/JA102
10.10.2013 2,517.54 2,503.19 Simplex
2517.00 Oct 13 Oct 15 Completed
LIMITED, JAM NAGAR New Infrastructure
Delhi Other Units of Phase III
Project of Jamnagar
Refinery B,Jamnagar, Gujarat

Civil Works of Fuel (Coal)


handling & Limestone
handling packages on Item
Rate Basis for Coal Based
Captive Power Plant at ThyssenKrupp 1544.00 July 14 May 16 Completed
Dahej, Gujarat for Dahej
Manufacturing Division
(DMD) — Reliance Industries
Limited.
Projects Completed (2 of 6)
Amount Completion
Work Details Clients Start Date
(Lakh) Date
,
Civil Works of CHP-2 x600 MW
Kalisindh Thermal Power project , RRVUNL 2183.00 Sep-13 Dec-15
Jhalawar , Rajasthan

Civil Work of Wagon Tippler


Complex- 2X500 MW Vindhyachal
NTPC LIMITED 2478.27 Feb-11 Dec-14
STPP(Stage-IV) Vindhayachal,
Singrauli , Madhya Pradesh

Construction Of Road ATPP Phase- Lanco Infratech


561.00 Mar-11 - Jun-11
1,2X600 MW Ltd.

Earth Work for Welspun Maxsteel Wespun Max steel


1116.00 Mar 10 Nov-10
Ltd. Ltd.

Rajashree Polyfil
Resurfacing and repairing of Bitumen
Umalla, Dist. 150.00 Feb 10 Apr 10
Road Helipad
Bharuch

Construction of Road, Helipad and


Jindal 50.00 Oct 09 Nov 09
othermisc jobs for Railway Wagon
Project, Karjan Dist. Baroda

MP Rural Road
Construction / upgradation of Rural
Development
Road under Pradhan Mantri Gram 1545.00 Jun 08 Mar 10
Authority
Sadak Yojna in MP State
PIU, Shahdol

Civil work of wagon tippler complex :


3x500 MW CHP, NTPC LIMITED 2603.00 Jun- 08 Jun -12
IGSTPP,Aravali,Jhajjar(Haryana)
Projects Completed (3 of 6)
Amount Start Completion
Work Details Clients
(Lakh) Date Date

Construction of Compound Wall for SEZ Jubilant


Project, for Jubilant Infrastructure Ltd., Infrastructure 310.00 Oct-08 Jan-09
Vilayat Ltd,Vilayat,Bharuch

Excavation for Pipe Line and other civil


construction works for Madhya Pradesh BHEL, Nagpur 336.00 Jan-07 Oct-07
Power Generating Co Ltd, Jabalpur

Construction of internal roads for Suzlon Suzlon Energy Ltd 145.00 Jan-07 Oct-07
Energy Ltd.

Construction Road within & outside


Battery limit for C3,C4 Project of O.N.G.C. Petron Civil Engg Pvt 353.00 Aug-06
Ltd, Mumbai Aug-07
at Dahej

Execution of earthwork in formation,


construction ofbridges, drains etc., at Rites Ltd 640.00 May 06 Jun-07
Birsinghpur, Distt.

Area grading and Earth work in Simplex Concrete


excavation at JERP site at Reliance Piles (I) Ltd New 1645.00 Apr-06 Oct-07
Petroleum Ltd, Moti Khavdi, Jamnagar. Delhi

Construction of Access Road, Well-site Premier Oil


and Camp Site for Drilling Program New Delhi 2200.00 Dec-05 Dec-07
Onshore India - Cachar (Silchar) Assam
Excavation & filling work at Railway Siding
and Construction of internal Roads at
Sponge Iron Project at Naharpali, Raigarh Monnet Ispat Ltd 1800.00 Sep-05 Dec-07
(CG).
Excavation for civil work for SGTPP 1 X TRF Ltd ,
500 MW at Birsinghpur-Palli, Dist Jamshedpur 250.00 Mar-05 Oct-07
Umeriya (MP).

Rajashree Polyfil (A
Repair and re-surfacing of existing roads Divof
at factory and colony of Rajashreenagar Century Enka 45.00 Oct-04 Dec-04
Ltd, Umalla

General Civil work (Steel Plant,


Platform, Land development) for Welspun India Ltd. 420,00 Jun-04 Oct-04
Welspun Ltd, Anjar

Excavation Works of Sanjay Gandhi Bridge & Roof 105.00 Jan-04 Jan-05
Thermal Power Station of MPSEB Co.
Projects Completed ( 4 of 6)
Amount Completion
Work Details Clients Start Date
(Lakh) Date

Excavation GSPL pipeline at Gammon India Ltd 50.00 Jan-04 Jun-04


Mora-Sajod Pipeline Project

Repair and re-surfacing of existing BASF Styrenics Pvt 50.00 Dec-03 Dec-04
roads Ltd Dahej, Gujarat

Land Development work (Earth work


in excavation, backfilling by
excavated and borrow area with Welspun India Ltd 1060.0 Nov-03 Dec-04
micro grading) at Anjar.

Site Clearance, Earth Work, Simplex Concrete


Embankment Work and Sub Base
work for Satara-KolhaPur Road Piles 682.00 Jul 05
Project (Package-II) Sep 03
India Ltd

Excavation & backfilling of Gas


pipeline at Dahej - Vijaypur Pipeline Punj Lloyd Ltd. 20.00 Jun-03 Mar-04
Project

Rehabilitation and upgrading of


existing
2 lane road to 4/6 lane road Simplex Concrete 2128.00 Feb-03 Mar-05
divided carriage-way configuration Ltd.
of Kavali to Ongle KM 222 to KM 291
of NH-5 in (A.P.) (Pack AP-12)

Hindustan Oil
Complete Civil works at drill site Exploration Co 39.00 Nov-02 Mar-03
Ltd.

Hard rock excavation of Platinum Jun-02 Apr-03


Park Plaza at MP Housing Board at JMC Projects (India) 50.00
Bhopal in MP

Land Development and Road


work and Construction of Tank Pad Bridge & Roof Co. 220.00 Apr-02 Dec-02
at BPCL, Mangalya

Excavation work at Narmada Dam Jai Prakash 20.00 Oct-01 Mar-02


Kewadia , Rajpipla Associates
Projects Completed (5 of 6)
Amount Completion
WorkDescription
Project Details Clients
Client Job Start DatePeriod
(Lakh)
Value Date
(lakh) Start Completion
Excavation and backfilling of GSPL Aban
pipeline Project Construction 80.00 Jun-01 Mar-02

Earthwork for pipe trenches at Jhanor, Jai hind Projects 25.00 Oct-00 Mar-01
Gujarat Ltd.

Civil works of Cement Plant and Jetty Sourashtra


work at Saurashtra Cement Ltd at Cement Ltd. 161.00 Jun-00 Mar-01
Porbandar Ranavav, Gujarat

Four laning of Ahmedabad - Mehsana JMC Projects


Road , ( earthwork and GSB work from (India) Ltd. 480.00 May-00 Oct-01
Km 59.20 to 70.60)

Earthwork and concrete breaking at Larsen & Mar-00 Jun-00


second Narmada Bridge on NH-8 Toubro Ltd. 50.00
Bharuch, Gujarat

Subhash
Earthwork for pipe trenches Projects & 60.00 Feb-00 Sep-00
Marketing Ltd.

Civil construction and complete EUPEC -


road work, earthwork at Dahej Welspun Pipe 117.00 Dec-99 Mar-00
(Gujarat) Coatings India
(P) Ltd,

National Highway work at Vadodara – NHAI 130.00 Aug-99 Dec-00


Halol Highway

Earthwork in excavation for pipeline Punj Lloyd Ltd. 70.00 Jun-99 Feb-00
project.

Civil construction, complete road


works, earth works etc. at Dahej Plant, Welspun Ltd. 150.00 Mar-99 Nov-99
Dahej

Earthwork in excavation in hard rock Reliance 280.00 Jun-98 Feb-99


with hydraulic rock breaker . Petroleum Ltd.
Projects Completed ( 6 of 6)
Amount Completion
Work Details Clients Start Date
(Lakh) Date

Construction of earthen Dyke for Ash Cost Co Pvt


disposal pond of CGSSTP Ropar Stage III Ltd 200.00 May-98 Jan-01
Unit 5&6 balance left out work.

Simplex
Earthwork in excavation & site clearance Concrete 30.00 Mar-97 Mar-98
Piles(I) Ltd

Simplex
Earthwork in excavation in soil, soft rock & Concrete
hard rock. 14.00 Jun-97 Dec-99
Piles(I) Ltd

Earthwork in excavation, filling etc. Simplex 14.00 Nov-96 Apr-97


Concrete
Piles(I) Ltd

Oriental Civil
Civil, road works & Engg. Co. 28.00 Jun-96 Jan-97
Ltd.

Earthwork in excavation, bank Simplex


protection CNS & rock blasting Concrete 65.00 Mar-96 Dec-97
Piles

Simplex
Earthwork in excavation, filling etc. Concrete 30.00 Dec-94 Jun-95
Piles (I) Ltd.

Road work (Stone soiling, WBM & ABB 20.00 Sep-93 Aug-95
carpeting)

Earthwork in excavation, area grading, Simplex


leveling road work (carpeting, seal coat Concrete 40.00 Sep-93 Aug-95
etc.) Piles , (I) Ltd.

Road work (Grouting seal coat & NTPC , Jhanor, Sep-93 Aug-95
carpeting) Gujarat 08.00
SNAPSHOTS OF PROJECTS (SHEET1 OF 11)

EXCAVATION WORK AT RELAINCE JAMNAGAR SITE


SNAPSHOTS OF PROJECTS (SHEET 2 OF 11)

GADARWARA THERMAL POWER PLANT , MADHYA PRADESH

WAGON TIPPLER CONSTRUCTION

CONVEYOR 2 A/B
SNAPSHOTS OF PROJECTS (SHEET 3 OF 11)

EARTH WORK AT NH-5 IN AP STATE

GSB work at NH-30

WMM Plant and WMM Laying


SNAPSHOTS OF PROJECTS (SHEET 4 OF 11)

STEEL & POWER


PLANT FOR WELSPUN
GROUP AT ANJAR,
GUJARAT
S N A P S H O T S O F P R O J E C T S ( S H E E T 5 O F 11 )

CONSTRUCTION WORKS AT RIG SITE AND ACCESS ROAD


SNAPSHOTS OF PROJECTS (SHEET 6 OF 11 )

CONSTRUCTION
OF POWER PLANT AT
JHAJJAR, HARYANA
SNAPSHOTS OF PROJECTS (SHEET 7 OF 11)

COAL HANDLING PLANT AT NTPC, JHAJJAR, HARYANA


SNAPSHOTS OF PROJECTS (SHEET 8 OF 11)

COAL HANDLING PLANT AT NTPC, JHAJJAR, HARYANA


SNAPSHOTS OF PROJECTS (SHEET 9 OF 11)

EXECUTION OF WAGON TIPPLER AND TRACK HOPPER RAFT


CASTING AT DVC, RAGHUNATHPUR, WEST BENGAL
SNAPSHOTS OF PROJECTS (SHEET 10 OF 11)

TEMPORARY STRUCTURE WORK OF TRACK HOPPER DOOSAN SITE


OBRA -C THERMAL POWER PLANT – UTTAR PRADESH – 2018

SOLDIER PILE INSTALLATION

WALLER BEAM INSTALLATION


SNAPSHOTS OF PROJECTS (SHEET 11 OF 11)

STACKER CIVIL WORK FOR DOOSAN FOR POWER PLANT


OBRA -C THERMAL POWER PLANT – UTTAR PRADESH – 2018

STACK RECLAIMER WORK FOR 2*660 MW PHASE – C POWER


PLANT
Values in Lakhs

PARTICULARS FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17

TURNOVER 3528.29 6588.78 5707.97 4439.27


GROSS PROFIT 219.43 93.08 145.92 198.29
FIXED ASSET 1648.08 1262.96 917.79 1047.17
SHARE CAPITAL 28.46 28.46 28.46 28.46
RESERVE & SURPLUS 975.28 867.65 967.12 1081.67

TURNOVER
7000
6588
6000
5707
5000
4439
4000
3528
3000
2000 TURNOVER
1000 Values in lakhs.

0
FY 2013-14

FY 2014-15

FY 2015-16

FY 2016-17
TURNOVER CERTIFICATE FROM AUDITOR FOR FY 2005-2014
Construction / Survey Equipment

Earthmoving Equipment

Road Construction Equipment

Mining Equipment

Miscellaneous Equipment
Equipment (1 of 2)
Sr.No Particulars Make/model Nos.

1 Excavator -215 2014-2018 15

2 Excavator -340 2014 3

3 Excavator -140 2014-16 3

4 Backhoe Loader ( 76 HP) 2014-2018 10

5 Backhoe loader (85HP) 2014-2018 3

6 Tipper (Dumper-2518) 2012-2018 20

7 Tipper(Dumper-2523) 2016 10

8 Transit Mixer(6CUM) 2012-2018 16

9 Transit Mixer (7CUM) 2012-2017 8

10 Concrete Pump (1405) 2014-2017 7

11 Rock Breaker 2014-2016 8

12 Vibrator Compactor 2014-2016 6

13 Hydraulic Crane –Hydra 2013-2016 10

14 Tower Crane (2418) 2014-2016 5

15 Motor Grader 2014-2016 2


Equipment (2 of 2)
Sr.No Particulars Make/model Nos.

16 Tandom Roller 2014-2016 3

17 Hot Mix plant/Paver 2014-2016 1/1

18 Boom placer (36Mts) 2018 2

19 Tata Trailer 2013-2017 5

20 Shantui Bull Dozer 2014 1

21 Bar Cutting Machine 2013-2017 18

22 Bar bending Machine 2013-2017 15

23 Welding Machine Set 2013-2016 10

24 Welding Rectifier 2013-2015 9

25 Total Station (Nikon) 2012-2017 9

26 Laboratory Set 2013-2017 6

27 Kirloskar DG set (62.5 to 2014-2018 7


125 KV)
28 Plate Compactor 2014-2016 8

29 Auto level 2013-2017 15

30 Porta Cabin (20*8 Feet) 2016-2017 10


OTHER INFORMATION

❑Our Specialties
❑ Recognition
❑Quality Control
❑Safety Control
❑Safety Appreciation from Clients
OUR SPECIALTIES

Earthwork in excavation on land and/or


under water in ordinary soil, soft/hard
rock (excavation in hard rock with
blasting and using hydraulic rock breaker).
----------------------------------------------
Civil work in coal handling plants ,
wagon tippler ,stacker , Conveyor belt etc .
----------------------------------------------
Hiring of the heavy earth-moving equipments/
vehicles on short/ long term basis.
------------------------------------------------
Infrastructure Developments
----------------------------------------------
Road Works
-----------------------------------------------
Industrial building works
RECOGNITION

SAFETY AWARDS DISTRIBUTED BY CLIENT AT RIG SITE


QUALITY & VALUES

Our Values

Our core values define the service that we want to provide you with.
we would like you to consider us as part of your team - working with
you to fulfil your aspirations in every way. Our corporate ideal is to
leave a mark of professionalism - whatever we deliver to you.
Four key values are offered through our service:
•Quality - There is no compromise possible when it comes to
maintaining training standards in the Construction industry.
•Innovation - In a fast moving industry, we readily understand the
importance of keeping one step ahead of anticipating our client’s
changing needs and providing solutions to satisfy them.
•Expertise - In an uncertain and fast changing world it makes sense to
rely on specialists; People who are experts in their field. People who lift
the burden, rather than add to it.
•Flexibility - We don’t make the mistake of assuming that one size fits
all. Often it is the differences that make life interesting. We work closely
with every client to identify those differences, refining our support
services to meet your requirements.
QUALITY CONTROL

FIELD TESTING
AT SITE
ACIL HSE Policy

Our HSE Policy is project oriented. We strive to achieve and meet HSE
requirements of our clients in both Public as well as Private sectors during
project implementation.

In recognition of our safe construction practices, and 3.63 Million Man Hours
of Lost Time Accident Free (LTA free) Site Management during past15
years, we enjoy a preferential treatment from our clients through repeat
orders.

We are conscious of our responsibility towards mother earth and


environment. We work in an e-environment while encouraging our employees
and other associates to minimize use of paper and optimize carbon emission
through sensible use of fuel and power in our operations.

We strictly adhere to HSE compliance enforced by Statutory


Authorities under Central as well as State Governments from time to time.
SAFETY APPRECIATION FROM CLIENT
SAFETY APPRECIATION FROM CLIENT
SAFETY AWARENESS

SAFETY TRAINING
AT SITE
SAFETY AWARENESS

SAFETY TRAINING
AT SITE
SAFETY

OUR GOAL: ZERO ACCIDENTS : SAFETY IS A VALUE THAT IS


FUNDAMENTAL TO OUR CULTURE.

ACIL has earned an industry-leading record of achieving zero lost-time


incidents on projects worldwide. Year after year, our zero accidents
philosophy helps put our safety performance right at the top of the
industry.

At ACIL, we believe that every accident, and therefore every injury, is


preventable, and we embed that philosophy into every project through a
combination of technical field procedures and ongoing training programs.
Every employee has stop-work authority—if it's not safe, don't do it. We
also ask our subcontractors and partners to adopt our commitment to
safety and health.

The result is exceptional safety performance, even in hazardous work


environments, severe weather, and remote locations. Our dedication to
safety helps keep workers safe, and it also pays off for our customers. Their
operating costs go down and productivity goes up because less
time is lost to accidents. And our people go home to their families safely at
the end of each day.
ANEJA CONSTRUCTIONS INDIA LIMITED

Head Office:
V-21,2nd floor Rajouri Garden
New Delhi-110027
Tel: 011-45525648,Fax:011-45520699
E-mail : Delhi@acil.co.in

Committed to Excellence
Branch Office:
4,5 ,Vinay complex
Bharuch,Gujarat-392001
Tel:02642-227323, Fax: 02642-245232
E-mail: bharuch@acil.co.in