Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

A D R C A S E D I G E S T S

Arbitration Agreement Later, disagreements arose between the parties as arbitrate was beyond reasonable time as required by
BF CORP. V. CA regards their respective liabilities under the contract. the agreement.
[G.R. No. 120105. March 27, 1998.] Thus, upon SPI's initiative, the parties' respective CA: Reversed.
representatives met in conference but they failed to
FACTS: Petitioner BF Corporation and respondent come to an agreement. ISSUES:
Shangri-la Properties, Inc. (SPI) entered into an (1) W/N there was a binding arbitration agreement.
agreement. Barely two days later, petitioner filed with the RTC (2) W/N the offer to arbitrate was beyond
of Pasig a complaint for collection of the balance reasonable time.
Under the agreement, SPI engaged BF Corp. to due under the construction agreement.
construct the main structure of the “EDSA Plaza RULING: (1) YES. RA 876 provides for the formal
Project,” a shopping mall complex in the City of SPI and its co-defendants filed a motion to suspend requisites of an arbitration agreement as follows:
Mandaluyong. SPI proposed the re-negotiation of proceedings instead of filing an answer.
the agreement between them, after disagreements. Section 4. Form of arbitration agreement. — A
SPI: The formal trade contract for the construction contract to arbitrate a controversy thereafter
Consequently, petitioner and SPI entered into a of the project provided for a clause requiring prior arising between the parties, as well as a
written agreement denominated as "Agreement for resort to arbitration before judicial intervention could submission to arbitrate an existing controversy,
the Execution of Builder's Work for the EDSA Plaza be invoked in any dispute arising from the contract. shall be in writing and subscribed by the party
Project." Said agreement would cover the sought to be charged, or by his lawful agent.
construction work on said project as of that time BF CORP.: Denied the existence of the arbitration
until its eventual completion. clause primarily on the ground that the The making of a contract or submission for
representatives of the contracting corporations did arbitration described in section two hereof,
The Articles of Agreement have been duly signed by not sign the "Conditions of Contract" that contained providing for arbitration of any controversy,
President Rufo B. Colayco of Shangri-La Properties, the said clause. shall be deemed a consent of the parties of the
Inc. and President Bayani F. Fernando of BF and province or city where any of the parties
their witnesses, and was thereafter acknowledged RTC: Motion to Dismiss denied. resides, to enforce such contract of
before Notary Public Nilberto R. Briones of Makati, (1) The “Conditions of Contract” referred to, submission.
Metro Manila. contains the following provisions:
The formal requirements of an agreement to
The said Articles of Agreement also provides that Three copies of the Contract Documents arbitrate are therefore the following:
the “Contract Documents” therein listed “shall be referred to in the Articles of Agreement shall be (1) It must be in writing; and
deemed an integral part of this Agreement.” signed by the parties to the contract and (2) It must be subscribed by the parties or their
distributed to the Owner and the Contractor for representatives.
One of the said documents is the “Conditions of their safe keeping.
Contract: which contains an Arbitration Clause. There is no denying that the parties entered into a
Since the “Conditions of Contract” is not duly signed written contract that was submitted in evidence
However, the said “Conditions of Contract” is not by the parties on any page thereof, the RTC before the lower court. To "subscribe" means to
duly signed by the parties on any page thereof. entertains serious doubt whether or not the write underneath, as one's name; to sign at the end
arbitration clause found in the said Conditions of of a document. That word may sometimes be
It, however, bears the initials of BF's representatives Contract is “binding upon the parties to the Articles construed to mean to give consent to or to attest.
(Bayani F. Fernando and Reynaldo M. de la Cruz) of Agreement.”
without the initials thereon of any representative of Here, these requisites were complied with in the
Shangri-La Properties, Inc. (2) Assuming that the arbitration clause was valid contract in question. The articles of Agreement,
and binding, still, it was “too late in the day for which incorporates all the other contracts and
defendants to invoke arbitration” since it the offer to agreements between the parties, was signed by

CHRISTIAN S. TADURAN 1
A D R C A S E D I G E S T S

representatives of both parties and duly notarized. "Reasonableness" is a relative term and the
The failure of the private respondent's representative question of whether the time within which an act has Sulpicio thus filed a complaint with RTC. Steamship
to initial the 'Conditions of Contract' would therefor to be done is reasonable depends on attendant moved to dismiss and to refer case to arbitration
not affect compliance with the formal requirements circumstances. pursuant to Rule 47 of the 2005/2006 Club Rules.
for arbitration agreements because that particular
portion of the covenants between the parties was This Court finds that under the circumstances RTC: Denied the motion to dismiss, holding that
included by reference in the Articles of Agreement. obtaining in this case, a one-month period from the arbitration “did not appear to be the most prudent
time the parties held a conference on July 12, 1993 action considering that other defendants had
A contract need not be contained in a single writing. until private respondent SPI notified petitioner that it already filed their answers.”
It may be collected from several different writings was invoking the arbitration clause, is a reasonable
which do not conflict with each other and which, time. Indeed, petitioner may not be faulted for CA: Affirmed. The arbitration agreement in the
when connected, show the parties, subject matter, resorting to the court to claim what was due it under 2005/2006 Club Rules is not valid since it was not
terms and consideration, as in contracts entered the contract. However, we find its denial of the signed by the parties.
into by correspondence. existence of the arbitration clause as an attempt to
cover up its misstep in hurriedly ling the complaint ISSUE: W/N the arbitration agreement in the
A contract may be encompassed in several before the lower court. 2005/2006 Club Rules, referenced by the Certificate
instruments even though every instrument is not of Entry and Acceptance which was agreed to and
signed by the parties, since it is sufficient if the In this connection, it bears stressing that the lower accepted by Sulpicio, is binding.
unsigned instruments are clearly identified or court has not lost its jurisdiction over the case.
referred to and made part of the signed instrument Section 7 of RA 876 provides that proceedings RULING: YES. By entering its vessels in Steamship,
or instruments. Similarly, a written agreement of therein have only been stayed. Sulpicio also becomes a member of Steamship. A
which there are two copies, one signed by each of protection and indemnity club like Steamship is an
the parties, is binding on both to the same extent as After the special proceeding of arbitration has been association composed of shipowners for the
though there had been only one copy of the pursued and completed, then the lower court may purpose of providing insurance cover of its
agreement and both had signed it. confirm the award made by the arbitrator. members. A shipowner wishing to enter its fleet of
vessels to Steamship must fill in an application for
(2) NO. Private respondent SPI's initiative in calling Arbitration Agreement entry form and sign it. Steamship then issues a
for a conference between the parties was a step STEAMSHIP V. SULPICIO LINES Certificate of Entry and Acceptance of the vessels,
towards the agreed resort to arbitration. However, [G.R. No. 196072. September 20, 2017.] showing its acceptance of the entry.
petitioner posthaste filed the complaint before the
lower court. FACTS: Steamship Mutual insures its members- The certificate of entry and acceptance provides
shipowners against third party risks and liabilities. that coverage would be to the extent specified in the
Thus, while private respondent SPI's request for By-Laws and the Rules of the Club. Sulpicio’s
arbitration on August 13, 1993 might appear an Sulpicio Lines insured its fleet of vessels with acceptance of the Certificate of Entry and
afterthought as it was made after it had filed the Steamship, among which was MV Princess of the Acceptance manifests its acquiescence to all its
motion to suspend proceedings, it was because World, as evidenced by a Certificate of Entry and provisions. Its acceptance also operated as
petitioner also appeared to act hastily in order to Acceptance issued by Steamship. acceptance of the entire provisions of the Club
resolve the controversy through the courts. Rules.
MV Princess was gutted by fire while on voyage.
The arbitration clause provides for a "reasonable Sulpicio claimed indemnity from Steamship. When a contract is in 2 or more writings, the writings
time" within which the parties may avail of the relief should be read and interpreted together. The
under that clause. Steamship denied the claim and rescinded the Certificate of Entry does not contain the details of
insurance coverage on the ground that Sulpicio was the insurance coverage, which are in the Club Rules.
grossly negligent in conducting its business. The arbitration clause is in 2005/2006 Club Rules,

CHRISTIAN S. TADURAN 2
A D R C A S E D I G E S T S

Rule 47. Under Rule 47, any dispute concerning the Acceptance, is binding upon Sulpicio even though Petitioner filed a Motion to Dismiss/Suspend
insurance afforded by Steamship must first be there was no specific stipulation on dispute Proceedings and to Refer Controversy to Voluntary
brought by a claiming member to the Directors for resolution in this Certificate. Arbitration.
adjudication. If this member disagrees with the
decision of the Director, the dispute must be Arbitration Agreement PETITIONER: The alleged contract between the
referred to arbitration in London. Despite the CARGILL V. REGALA parties was never consummated because
member's disagreement, the Managers of [G.R. No. 175404. January 31, 2011.] respondent never returned the proposed agreement
Steamship may refer the dispute to arbitration bearing its written acceptance or conformity nor did
without adjudication of the Directors. This procedure FACTS: Respondent San Fernando Regala Trading, respondent open the Irrevocable Letter of Credit at
must be complied with before the member can Inc. was engaged in buying and selling of molasses, sight. The controversy between the parties was
pursue legal proceedings against Steamship. while petitioner Cargill Philippines, Inc. was one of whether or not the alleged contract between the
its various sources from whom it purchased parties was legally in existence and the RTC was not
In domestic arbitration, the formal requirements of molasses. the proper forum to ventilate such issue.
an arbitration agreement are that it must “be in
writing and subscribed by the party sought to be They entered into a contract, wherein it was agreed RTC: Motion to Dismiss DENIED. The suspension of
charged, or by his lawful agent." upon that respondent would purchase from the proceedings was not warranted, since the
petitioner 12,000 metric tons of Thailand origin cane Arbitration Law contemplates an arbitration
In international commercial arbitration, it is likewise blackstrap molasses at the price of US$192 per proceeding that must be conducted in the
required that the arbitration agreement must be in metric ton. Philippines under the jurisdiction and control of the
writing. RTC; and before an arbitrator who resides in the
The parties agreed that the delivery would be made country; and that the arbitral award is subject to
An arbitration agreement is in writing if it is in April/May 1997 and that payment would be by an court approval, disapproval and modification, and
contained: Irrevocable Letter of Credit payable at sight, to be that there must be an appeal from the judgment of
(1) In a document signed by the parties; opened upon petitioner's advice. the RTC.
(2) In an exchange of letters, telex, telegrams or
other means of telecommunication which The contract contained an arbitration clause, to wit: CA: Affirmed. In its Motion to Dismiss/Suspend
provide a record of the agreement; or proceedings, petitioner alleged, as one of the
(3) In an exchange of statements of claim and ARBITRATION grounds thereof, that the subject contract between
defense in which the existence of an agreement the parties did not exist or it was invalid; that the
is alleged by a party and not denied by another. Any dispute which the Buyer and Seller may not said contract bearing the arbitration clause was
be able to settle by mutual agreement shall be never consummated by the parties. Arbitration is not
The reference in a contract to a document settled by arbitration in the City of New York proper when one of the parties repudiated the
containing an arbitration clause constitutes an before the American Arbitration Association. existence or validity of the contract.
arbitration agreement provided that the contract is The Arbitration Award shall be final and binding
in writing and the reference is such as to make that on both parties. ISSUE: W/N the issue must be settled through
clause part of the contract. arbitration.
Petitioner, as seller, failed to comply with its
Thus, an arbitration agreement that was not obligations under the contract, despite demands RULING: YES. A contract is required for arbitration
embodied in the main agreement but set forth in from respondent. to take place and to be binding. Submission to
another document is binding upon the parties, arbitration is a contract and a clause in a contract
where the document was incorporated by reference Thus, respondent filed with the RTC of Makati City a providing that all matters in dispute between the
to the main agreement. The arbitration agreement Complaint for Rescission of Contract with Damages parties shall be referred to arbitration is a contract.
contained in the Club Rules, which in turn was against petitioner. The provision to submit to arbitration any dispute
referred to in the Certificate of Entry and

CHRISTIAN S. TADURAN 3
A D R C A S E D I G E S T S

arising therefrom and the relationship of the parties Supply and Purchase Agreement (PSPA or Respondent BATAAN filed a Complaint against
is part of the contract and is itself a contract. agreement). PEZA for specific performance before the RTC of
Pasay.
Doctrine of Separability Under the agreement, the respondent BATAAN
Applying the ruling in Gonzales v. Climax Mining Ltd. undertook to construct, operate, and maintain a PEZA: The refusal of the defendant to arbitrate is
(G.R. Nos. 161957 & 167994, January 22, 1997), power plant which would sell, supply and deliver justified considering that the provision on the pre-
an arbitration agreement which forms part of the electricity to petitioner PEZA for resale to business termination fee subject of the plaintiff's Request for
main contract shall not be regarded as invalid or locators in the Bataan Economic Processing Zone. Arbitration is invalid and unenforceable.
non-existent just because the main contract is
invalid or did not come into existence, since the Under Clauses 14.1 and 14.2 of the Agreement, the RTC: Granted respondent's Motion to Render
arbitration agreement shall be treated as a separate dispute shall be resolved through arbitration before Judgment on the Pleadings.
agreement independent of the main contract. an Arbitration Committee composed of one
representative of each party and a third member This Court hereby appoints, subject to their
To reiterate a contrary ruling would suggest that a who shall be mutually acceptable to the parties. agreement as arbitrators, retired Supreme
party's mere repudiation of the main contract is Court Chief Justice Andres Narvasa, as
sufficient to avoid arbitration and that is exactly the In the course of the discharge of its obligation, chairman of the committee, and retired
situation that the separability doctrine sought to respondent BATAAN requested from petitioner Supreme Court Justices Hugo Gutierrez, and
avoid. Thus, we find that even the party who has PEZA a tariff increase with a mechanism for Justice Jose Y. Feria, as defendant's and
repudiated the main contract is not prevented from adjustment of the cost of fuel and lubricating oil. plaintiff's representative, respectively, to the
enforcing its arbitration clause. arbitration committee. Accordingly, let the
PEZA did not respond to the requests. Request for Arbitration be immediately referred
Moreover, it is worthy to note that respondent filed to the Arbitration Committee so that it can
a complaint for rescission of contract and damages Citing a tariff increase which PEZA granted to the commence with the arbitration.
with the RTC. In so doing, respondent alleged that East Asia Utilities Corporation (EAUC), another
a contract exists between respondent and supplier of electricity in the Mactan Economic Zone, CA: Affirmed.
petitioner. It is that contract which provides for an respondent informed PEZA of a violation of its
arbitration clause which states that "any dispute obligation under Clause 4.9 of the PSPA not to give ISSUE: W/N the legality of the pre-termination fee
which the Buyer and Seller may not be able to settle preferential treatment to other power suppliers. clause of the PSPA is arbitrable.
by mutual agreement shall be settled before the City
of New York by the American Arbitration After the lapse of 90 days, respondent terminated RULING: YES. The Court reiterated its ruling in
Association. The arbitration agreement clearly the PSPA, invoking its right thereunder, and Gonzales, thus:
expressed the parties' intention that any dispute demanded P708,691,543.00 as pre-termination
between them as buyer and seller should be referred fee. We now hold that the validity of the contract
to arbitration. It is for the arbitrator and not the containing the agreement to submit to
courts to decide whether a contract between the PEZA disputed respondent's right to terminate the arbitration does not affect the applicability of
parties exists or is valid. agreement and refused to pay the pre-termination the arbitration clause itself. A contrary ruling
fee. would suggest that a party's mere repudiation
Arbitration Agreement of the main contract is sufficient to avoid
PEZA V. BATAAN Thus, respondent was prompted to request PEZA to arbitration. That is exactly the situation that the
[G.R. No. 179537. October 23, 2009.] submit the dispute to arbitration pursuant to the separability doctrine, as well as jurisprudence
arbitration clause of the PSPA. applying it, seeks to avoid.
FACTS: Petitioner Philippine Economic Zone
Authority (PEZA) and respondent Edison (Bataan) Petitioner PEZA refused to submit to arbitration.
Cogeneration Corporation entered into a Power

CHRISTIAN S. TADURAN 4
A D R C A S E D I G E S T S

Arbitration Agreement xxxx ISSUE: W/N the case should have first been brought
BENGUET V. DENR to voluntary arbitration before the POA.
[G.R. No. 163101. February 13, 2008.] 11.02 Court Action
RULING: YES. Petitioner having failed to properly
FACTS: Petitioner Benguet Corporation (Benguet) No action shall be instituted in court as to any appeal to the CA under Rule 43, the decision of the
and private respondent J.G. Realty and Mining matter in dispute as hereinabove stated, except MAB has become final and executory. On this
Corporation (J.G. Realty) entered into a Royalty to enforce the decision of the majority of the ground alone, the instant petition must be denied.
Agreement with Option to Purchase (RAWOP). Arbitrators.
Even if we entertain the petition, the decision and
Under the agreement, J.G. Realty was The Executive Vice-President of Benguet, Antonio resolution of the DENR-MAB should be maintained.
acknowledged as the owner of 4 mining claims N. Tachuling, issued a letter informing J.G. Realty
respectively named as Bonito-I, Bonito-II, Bonito- of its intention to develop the mining claims. However, on this issue, we rule for Benguet.
III, and Bonito-IV.
J.G. Realty, through its President, Johnny L. Tan, A contractual stipulation that requires prior resort to
The mining claims were covered by MPSA then sent a letter to the President of Benguet voluntary arbitration before the parties can go
Application No. APSA-V-0009 jointly filed by J.G. informing the latter that it was terminating the directly to court is not illegal and is in fact promoted
Realty as claimowner and Benguet as operator. RAWOP for Benguet’s failure to perform its by the State.
obligations thereunder.
Among others, Benguet obligated itself to: (1) Under Secs. 6 and 7 of RA 876, in the event a case
perfect the rights to the mining claims and/or Benguet reminded J.G. Realty that it should submit that should properly be the subject of voluntary
otherwise acquire the mining rights to the mineral the disagreement to arbitration rather than arbitration is erroneously filed with the courts or
claims; and (2) pay a royalty of 5% of net realizable unilaterally terminating the RAWOP. quasi-judicial agencies, on motion of the
value to respondent if the mining claims were placed defendant, the court or quasi-judicial agency shall
in commercial production by Benguet. J.G. Realty filed a Petition for Declaration of determine whether such contractual provision for
Nullity/Cancellation of the RAWOP with the Legaspi arbitration is sufficient and effective. If in
Secs. 11.01 and 11.02 of the RAWOP pertinently City MAB Panel of Arbitrators (POA), Region V. affirmative, the court or quasi-judicial agency shall
provide: then order the enforcement of said provision.
POA: Declared the RAWOP and its Supplemental
11.01 Arbitration Agreement cancelled and without effect. To state Compulsory vs. Voluntary Arbitration
that an aggrieved party cannot initiate an action J.G. Realty's contention, that prior resort to
Any disputes, differences or disagreements without going to arbitration would be tying one's arbitration is unavailing in the instant case because
between BENGUET and the OWNER with hand even if there is a law which allows him to do the POA's mandate is to arbitrate disputes involving
reference to anything whatsoever pertaining to so. mineral agreements, is misplaced.
this Agreement that cannot be amicably settled
by them shall not be cause of any action of any Benguet filed a Notice of Appeal. There is a clear distinction between compulsory and
kind whatsoever in any court or administrative voluntary arbitration. The arbitration provided by the
agency but shall, upon notice of one party to DENR-MAB: Affirmed. Benguet is in estoppel from POA is compulsory, while the nature of the
the other, be referred to a Board of Arbitrators questioning the competence of the POA to hear and arbitration provision in the RAWOP is voluntary, not
consisting of three (3) members, one to be decide in the summary proceedings J.G. Realty's involving any government agency.
selected by BENGUET, another to be selected petition, when Benguet itself did not merely move
by the OWNER and the third to be selected by for the dismissal of the case but also filed an Answer Thus, J.G. Realty's argument on this matter must
the aforementioned two arbitrators so with counterclaim seeking affirmative reliefs from fail.
appointed. the Panel of Arbitrators. MR denied.

CHRISTIAN S. TADURAN 5
A D R C A S E D I G E S T S

Are Quasi-Judicial Agencies Covered? In this factual milieu, the Court rules that the On the other hand, respondent bound himself to the
J.G. Realty's contends that the provisions of RA 876 jurisdiction of POA and that of MAB can no longer construct the first and second stories, together with
cannot apply to the instant case which involves an be questioned by Benguet at this late hour. the theater, within a 5-month period.
administrative agency.
What Benguet should have done was to immediately Dispute arose between the parties because of
Section 11.01 of the RAWOP states that: challenge the POA's jurisdiction by a special civil alleged failure of each party to comply with their
action for certiorari when POA ruled that it has obligations under the agreement.
[Any controversy with regard to the contract] jurisdiction over the dispute. To redo the
shall not be cause of any action of any kind proceedings fully participated in by the parties after Soledad F. Bengson filed an action for damages
whatsoever in any court or administrative the lapse of seven years from date of institution of against Mariano M. Chan and the sureties on his
agency but shall, upon notice of one party to the original action with the POA would be anathema performance bond.
the other, be referred to a Board of Arbitrators to the speedy and efficient administration of justice.
consisting of three (3) members, one to be Respondent Chan filed counterclaims for the
selected by BENGUET, another to be selected Arbitration Agreement balance due on the contract, the value of the
by the OWNER and the third to be selected by BENGSON V. CHAN materials in the construction yard, the
the aforementioned two arbiters so appointed. [G.R. No. L-27283. July 29, 1977.] reimbursement of the expenses for the demolition
of the old building, the value of his construction
There can be no quibbling that POA is a quasi- FACTS: Petitioner Soledad F. Bengson and equipment under Bengson's control and the
judicial body which forms part of the DENR, an respondent Mariano M. Chan entered into a contract payment of damages.
administrative agency. Hence, the provision on for the construction of a six-story building on
mandatory resort to arbitration, freely entered into Bengson's lot located at Rizal Avenue, San The respondents filed an amended answer wherein
by the parties, must be held binding against them. Fernando, La Union. they alleged as an additional affirmative defense
that the complaint states no cause of action
Issue on Estoppel The contract contains the following arbitration because Soledad F. Bengson did not first submit
We find that Benguet is already estopped from clause: the controversy for arbitration.
questioning the POA's jurisdiction for the following
reasons: "15. Any and all questions, disputes or TRIAL COURT: Complaint is DISMISSED.
(1) When J.G. Realty filed DENR Case No. 2000- differences arising between the parties hereto
01, Benguet filed its answer and participated in relative to the construction of the BUILDING PETITIONER: Causes of action do not involve
the proceedings before the POA, Region V. shall be determined by arbitration of two disputes relative to the construction of the building
persons, each chosen by the parties and, consequently, should not be submitted for
(2) When the adverse POA Decision was rendered, themselves. The determination of said arbitration. Paragraph 15 refers to disputes as to
it filed an appeal with the MAB and again arbitration shall be final, conclusive and "the technical process of putting up the building,"
participated in the MAB proceedings. binding upon both parties hereto, unless they meaning whether there was an adherence to the
choose to go to court, in which case the plans and specifications, and that her causes of
(3) When the adverse MAB Decision was determination by arbitration is a condition action for damages do not involve questions as to
promulgated, it filed a Motion for precedent for tasing any court action. The the construction of the building but refer to disputes
Reconsideration with the MAB. expenses of arbitration shall be borne by both "based on violation of the contract for construction."
parties equally."
(4) When the adverse MAB Resolution was issued, She pointed out that the contract for the
Benguet filed a petition with this Court pursuant In that contract, Soledad F. Bengson bound herself construction of the building and the construction of
to Sec. 79 of RA 7942 impliedly recognizing to pay Chan, the contractor, the sum of P352,000 the building are different concepts. A dispute
MAB's jurisdiction. for the materials, labor and construction expenses. relating to the construction contract is not
necessarily a dispute relative to the construction of

CHRISTIAN S. TADURAN 6
A D R C A S E D I G E S T S

the building. The parties did not have any dispute Arbitration Agreement pounds sterling which would commence on January
prior to the filing of the complaint, and that it was GENERAL INSURANCE V. UNION 1, 1960, and would terminate on December 31,
only after the filing of the case that a dispute arose [G.R. Nos. L-30475-76. November 22, 1989.] 1961.
between them.
FACTS: This case involves two consolidated cases: In Art. XII of the retrocession agreement:
ISSUE: W/N the issue is arbitrable. Civil Case No. 68558 and Civil Case No. 68559.
All differences of whatever nature arising out of
RULING: YES. We hold that the terms of paragraph Respondents Union Insurance Society of Canton, this Agreement shall be settled according to an
15 clearly express the intention of the parties that Ltd. and British Traders' Insurance Co., Ltd. are equitable rather than a strictly legal
ALL DISPUTES between them should first be insurance corporations organized and existing under interpretation of its provisions. Such
arbitrated before court action can be taken by the the laws of Great Britain and licensed to do business differences shall be submitted to a Court of
aggrieved party. in the Philippines. The other respondents are also Arbitration in London composed of two
engaged in insurance business and are mere independent Fire Insurance experts who shall
Bengson's interpretation of paragraph 15 as being subsidiaries of the Union Insurance Society of be Managers of Insurance or Reinsurance
limited to controversies with respect "to the joining Canton, Ltd. of Hong Kong. Companies of whom each party shall select
together of stones, steel, wood and other material one and of an Umpire to be chosen by the
to put up a building" has a sophistical flavor. Her In Civil Case No. 68558 the respondents and the Arbitrators prior to the hearing of the case and
superfine distinction between the contract for the petitioner General Insurance & Surety Corporation who has only to act in the event of a
construction of the building and the construction of entered into a First Surplus Reinsurance Agreement. disagreement between the Arbitrators.
the building is specious but not convincing.
The parties agreed on reciprocal reinsurance Both agreements were terminated on December 31,
However, although the causes of action in expressed and payable in pounds sterling between 1961, and on the said date the respondents claim
Bengson's complaint are covered by paragraph 15, the petitioners and respondent commencing on that there was due from the petitioner the sum of
her failure to resort to arbitration does not warrant January 1, 1959, and terminating on December 31, 4,784.5.1 (reinsurance) and 1,035.2.7
the dismissal of her complaint. We agree with her 1961. (retrocession).
alternative contention that arbitration may be
resorted to during the pendency of the case. In Art. XII of the reinsurance agreement: Respondents requested the petitioner to pay the
aforesaid sums in pounds sterling or in Philippine
In other words, under Sec. 6 of RA 876, the failure In the event of any dispute at any time arising pesos at the exchange rate prevailing on the date of
of Soledad F. Bengson to resort to arbitration may out of or in any way connected with or relating payment.
be regarded as a refusal to comply with the to this Agreement, whether before or after the
stipulation for arbitration. termination of notice under the Agreement the However, petitioner refused and insisted that it
same shall be referred to the decision of two should pay the said amounts in Philippine pesos at
And defendants' interposition of the defense that arbitrators … and it shall be a condition the old official exchange rate of P2.015 to $1.00.
arbitration is a condition precedent to the institution precedent that unless and until an award has
of a court action may be interpreted as a petition for been made neither party shall have any right of In view of the petitioner’s refusal to pay in the
an order that arbitration should proceed as action against the other. manner demanded by the respondents, the latter
contemplated in section 15. made a written formal demand upon petitioner to
In Civil Case No. 68559 the respondents and the proceed with the arbitration, which demand was
Therefore, instead of dismissing the case, the petitioner entered into a Retrocession Quota Share received by the respondent on August 18, 1966.
proceedings therein should be suspended and the Fire Pool Agreement.
parties should be directed to go through the motions Respondents filed the two civil cases, both praying
of arbitration at least within a sixty-day period. In said agreement the parties agreed on reciprocal for a declaration that a dispute exists between the
reinsurance arrangements expressed and payable in parties that is subject to arbitration.

CHRISTIAN S. TADURAN 7
A D R C A S E D I G E S T S

TRIAL COURT: A valid controversy existed and the established in the State of California, in order to None of these specifically requires that the party
petitioner was ordered to submit to arbitration. implement the objectives of this Agreement. seeking for the enforcement should have legal
capacity to sue.
PETITIONER: Admitted the existence of the Due to a series of events not mentioned in the
provision to refer to arbitration any dispute or petition, the licensees, including respondent ISSUE: W/N the dismissal was proper.
controversy arising from the reinsurance and the Kingford, withdrew from petitioner TPI and
retrocession agreements, but the said provision can correspondingly reneged on their obligations. RULING: NO. The Corporation Code of the
no longer be enforced 5 years after the termination Philippines expressly provides:
of both contracts on December 31, 1961. Petitioner submitted the dispute for arbitration
before the International Centre for Dispute Sec. 133. Doing business without a license. —
ISSUE: W/N the issues may submitted to arbitration Resolution in the State of California, United States No foreign corporation transacting business in
despite termination of the agreements. and won the case against respondent. the Philippines without a license, or its
successors or assigns, shall be permitted to
RULING: YES. The language of the reinsurance To enforce the award, petitioner TPI filed a Petition maintain or intervene in any action, suit or
contract on arbitration of any dispute between them for Confirmation, Recognition, and Enforcement of proceeding in any court or administrative
which may arise before or after the termination of Foreign Arbitral Award before the RTC of Makati agency of the Philippines; but such corporation
the agreement is clear. City. may be sued or proceeded against before
Philippine courts or administrative tribunals on
On the other hand, the retrocession agreement is Respondent Kingford filed a Motion to Dismiss, any valid cause of action recognized under
also clear that all differences of whatever nature which was denied. Philippine laws.
arising out of the agreement shall be submitted to a
court of arbitration. No restriction as to time was Respondent sought for the inhibition of Judge How do we reconcile the provisions of the
contemplated by the parties. Alameda and moved for the reconsideration of the Corporation Code of the Philippines on one hand,
order denying the motion. and the Alternative Dispute Resolution Act of 2004,
Further, the provision on arbitration is the remedy by the New York Convention and the Model Law on the
which the parties may resort to for disputes arising Judge Cedrick O. Ruiz, to which the case was re- other?
from the agreements. While the two agreements raffled, in turn, granted respondent's Motion for
have been terminated, the provision requiring Reconsideration and dismissed the petition on the As between a general and special law, the latter
arbitration remains as a remedy to settle any ground that the petitioner lacked legal capacity to shall prevail —generalia specialibus non derogant.
dispute/controversy arising from the agreements. sue in the Philippines.
Following the same principle, the ADR Act of 2004
Arbitration Agreement PETITIONER: It is entitled to seek for the recognition shall apply in this case as the Act is a law especially
TUNA PROCESSING V. PHILIPPINE KINGFORD and enforcement of the subject foreign arbitral enacted "to actively promote party autonomy in the
[G.R. No. 185582. February 29, 2012.] award in accordance with: resolution of disputes or the freedom of the party to
(1) RA 9285 (Alternative Dispute Resolution Act of make their own arrangements to resolve their
FACTS: Kanemitsu Yamaoka (LICENSOR) and 5 2004); disputes." It specifically provides exclusive grounds
Philippine tuna processors, namely, Angel Seafood (2) Convention on the Recognition and available to the party opposing an application for
Corporation, East Asia Fish Co., Inc., Mommy Gina Enforcement of Foreign Arbitral Awards drafted recognition and enforcement of the arbitral award.
Tuna Resources, Santa Cruz Seafoods, Inc., and during the United Nations Conference on
respondent Philippine Kingford, Inc. (LICENSEES), International Commercial Arbitration in In particular, the ADR Act of 2004 incorporated the
entered into a MOA. 1958(New York Convention); and New York Convention in the Act by specifically
(3) UNCITRAL Model Law on International providing:
The parties agreed to the establishment of petitioner Commercial Arbitration (Model Law).
Tuna Processors, Inc. (TPI), a corporation

CHRISTIAN S. TADURAN 8
A D R C A S E D I G E S T S

SEC. 42. Application of the New York petitioner or respondent have legal capacity to sue
Convention. — The New York Convention shall or be sued."
govern the recognition and enforcement of
arbitral awards covered by the said Convention. It is in the best interest of justice that in the
enforcement of a foreign arbitral award, we deny
It also expressly adopted the Model Law, to wit: availment by the losing party of the rule that bars
foreign corporations not licensed to do business in
Sec. 19. Adoption of the Model Law on the Philippines from maintaining a suit in our courts.
International Commercial Arbitration. —
International commercial arbitration shall be When a party enters into a contract containing a
governed by the Model Law on International foreign arbitration clause and, as in this case, in fact
Commercial Arbitration (the "Model Law") submits itself to arbitration, it becomes bound by
adopted by the United Nations Commission on the contract, by the arbitration and by the result of
International Trade Law on June 21, 1985." arbitration, conceding thereby the capacity of the
other party to enter into the contract, participate in
Sec. 45 of the Alternative Dispute Resolution Act of the arbitration and cause the implementation of the
2004 provides that the opposing party in an result.
application for recognition and enforcement of the
arbitral award may raise only those grounds that
were enumerated under Article V of the New York
Convention.

Clearly, not one of those exclusive grounds touched


on the capacity to sue of the party seeking the
recognition and enforcement of the award.

Rule 13.1 of the Special Rules provides that "Any


party to a foreign arbitration may petition the court
to recognize and enforce a foreign arbitral award."
The contents of such petition are enumerated in
Rule 13.5.32 Capacity to sue is not included.

Oppositely, in the Rule on local arbitral awards or


arbitrations in instances where "the place of
arbitration is in the Philippines," it is specifically
required that a petition "to determine any question
concerning the existence, validity and enforceability
of such arbitration agreement" available to the
parties before the commencement of arbitration
and/or a petition for "judicial relief from the ruling of
the arbitral tribunal on a preliminary question
upholding or declining its jurisdiction" after
arbitration has already commenced should state
"[t]he facts showing that the persons named as

CHRISTIAN S. TADURAN 9

You might also like