Day : 1
Project Management :
Project :
Project is a Temporary endeavour undertaken to create unique product / Result / Services.
Program
A Program is a group of related projects managed in a co-ordinated way to obtain benefits and help to
achieve the Program Objective.
Portfolio
A Portfolio is a group of Projects, Program and Sub Portfolio that grouped together to achieve the
Organizational Objective.
L&T Ltd
North Region South Region
Construction Division EPC Division
8F Apartment Cons Villa Construction 32MW PG Solar Power Projects
Primavera
Release of Primavera :
Primavera Components :
Layers in Primavera
Road Map
Initiation
OBS
EPS
Project
Planning
Scheduling Costing
Baseline
Execution
Project Updation
Closing
Reports
Additional Topics :
Reflection
Filters
Layout
Constraints
Codes.
OBS
Eg :
CEO
Dir 1 Dir 2
SBU 1 SBU 2
PM 1 PM 2 PM3 PM 4
OBS Creation :
Enterprise menu --- OBS --- Select ADD – Rename (Create Parent OBS ) – Select the created Parent OBS and
add the list of required OBS.
EPS Creation :
Eg :
Thermax Ltd
EPS Creation :
Enterprise menu --- Enterprise Project Structure – Add – Rename (Create Parent EPS) – Select the created
parent EPS and ADD the list the required EPS.
Enterprise menu --- Enterprise Project Structure – Select the created EPS – Down Responsible Manager – Click
and Assign the Created OBS
Project Creation :
File Menu – New –Select EPS –Select the particular EPS – Give Project ID and Name – Select Project Start date
and Time – Don’t Give Must Finish by date – Select Responsible manager –- Select Rate type as Standard Rate
– Next & Finish.
Project Table – Select the Particular Project – right click – Select Open Project.
Calendar Creation :
Global Calendar
It is the common calendar which can be used across all the projects in Primavera.
Project Calendar
Resource Calendar
Shared Calendar
Personal Calendar
Calendar Creation :
Enterprise menu --- Calendar -- Add -- Select any one base calendar --- Rename -- Modify ---Select Total work hrs
per day --- Select Work week --- Give total no of working hrs from Sunday till Saturday --- Ok----Select Time
period --- give hours per day -- per week --per month ---per year ---ok -- Select Detailed Work hours/ day ---
Workweek --- Select working day --- Select Start time, break time and End time -- Ok --- To define holidays ---
Select the particular day on the calendar -- Select Non Work --- Ok.
Assigning Calendar to the Project :
Project Table – select the Particular project – Down select Defaults tab -- Calendar – Assign the created
calendar.
OBS
EPS
Project Creation
Calendar Creation
Day 2
WBS
“L3” Activities
Eg :
4F Apartment Cons
Piping works
Interior works
Exterior works
To Create WBS :
Step : 1 Project Table – Select the particular project – Right click open project –Project menu – Select WBS –
ADD – Add the list of required WBS.
Activities Creation
Activity table – View menu – Select Group & Sort by – Group by – Select WBS – Apply Ok
Project table – Select the particular project – Down Defaults tab – Auto numbering defaults –Do the
Modification –Press F5
The activity which is having zero duration will be considered as Milestone activity.
Activity Table – select the particular activity – Down General –Activity Type – Select Start Milestone or Finish
Milestone.
Duration
To modify duration label : Edit – User preferences –Time units – Duration – Do the modification
Relationship
Predecessors
The activity which controls start or finish of the another activity is called it as predecessor
Successors
The activity in which start or finish is depend on the start or finish of the another activity is called it as
successor activity.
Relationship :
Activity table --- Select the particular activity -- Down Relationship -- Predecessor -- Assign the Predecessor
activity - - to change the relationship type -- Go to Relations columns --- Change the relation type.
Day 3
It is the longest duration in the project where total float and free float should be zero.
Total Float :
The Particular activity can be delayed without affecting the Project duration is called it as Total float.
Free Float :
The Particular activity can be delayed without affecting the immediate successor in the project is called it as
Free Float.
Formula : ES EF
EF = ES(C)+D-1 LF = LS(S)-1
Or
F9 – Schedule.
Activity Table – View menu – Column – Duration – Select Total Float and Free Float – Apply Ok.
Lead and Lag :
Lead
Lead time is the amount of time whereby a successor activity can be advanced with respect to the
predecessor activity.
(-Ve) (Preponed)
Lag
Lag time is the amount of time whereby a successor activity is required to be delayed with respect to the
predecessor activity.
(+Ve) (Postponed)
Activity table –Select the particular activity –Down relationship –Predecessors -- Lag column –
Day 4
Resource Creation :
Eg :
Boiler Items
To create Resource :
Select the created parent resource – Down Details – Calendar (Assign the Project calendar)
--Currency (Assign the required Currency )
Assigning Currency to the Project : Edit –User Preferences – Currency – Assign the created
Currency]
Step : 2 Select the created Parent resource and Add the list of required resources
Step : 3 Select the created Resources – Down Details – Select Labor / Non Labor / Material
[To created New unit of Measure – Admin – Admin category – Unit of Measure – Add]
Resource Assignment :
4 lab/d 10d
Step : 1
Activity Table – View menu –Column – General – Select Duration Type – Apply Ok
Select the Particular activity – Change the duration type – Press shift key – Select all the activities –
Step : 2
Select the particular activity – Down resources – Add Resources –Select the particular resources –
Define the per day requirement in Budgeted Units/Time column.
Note : Only for material define the overall material requirement in Budgeted Unit column.
Roles Creation :
Eg :
Price/Unit 4 - Proficient
Price/Unit 5 - Inexperienced
Price/Unit
DE SE PM
Roles Creation :
Step : 2 Enterprise – Roles – Add (Create Parent Roles) – Add the list of required roles
Step : 3 Select the created Role – Down Prices – Define Price / Unit
Step : 4 Select the created Role – Down Resources – Assign – Select the resource person names
and select the proficiency.
Roles Assignment:
Activity table – Select the particular activity – Down Resources – Add Role – Select the required Role
Down Select Assign by Role option – Select the resource person names –Select No – Change the Rate
type column – Press Yes -- Cost will be recalculated
Day 5
Resource Analysing
Over Allocation
Under Allocation
Allocation
To analysis resource
Activity table – View menu – Show on bottom – select Resource Usage Profile – Select left side
display – Filter by – select Current project resources
Select Right side display –Uncheck show all projects options – Select resource usage profile option –
Select By date down – Actual and Remaining Early –Uncheck rest of the options
Select the particular resource – Click on the Over allocated bar – Select Down Time Period – we can
view over allocated activity on the activity table – Make a note of activity ID no.
Resource Levelling
(It will solve only Over allocation (It will solve both Over allocation and Under
With Float :
Utilizing the available float , the software will try to level the resources.
Without Float :
The O/A problem will get solved in without float, it will delay the O/A activity we will get huge
impact on the project duration.
To perform automatic levelling :
With Float :
Tools menu – Level resources – Select the option (Level resources only within activity total float ) –
Level
Without float :
Tools menu – Level resources – unselect the option (Level resources only within activity total float )
– Level
Press F9 – Schedule
Manual Levelling
Stretching Crunching
Note : When the maximum resource is fixed then we need to perform Stretching and Crunching.
Step : 2
Go to resource graph – Select the particular resources – Click the Over allocated bar – Select time
period – Note down Over allocated activity ID number
Step : 3
Activity Table – Select the particular activity – Down resources – Increase / Decrease the resources in
Budgeted Units/ Time column.
Optimistic Levelling
Note : When the schedule is Fixed then we need to perform Optimistic Levelling
To perform Optimistic Levelling
Step: 1
Go to resource graph – Select the particular resource –Make a note Utilization bar Start date and
Remaining early units
Step: 2
Go to resource sheet –Select the particular resource – Down Units & Prices Tab – Select the noted
dates in Effective date column and define the remaining early units in Max Units/Time column.