BACKGROUND
AMC consultants have been tackling some of the
most challenging modelling and engineering problems AMC are starting to see a trend emerge. More
facing the mining industry for over thirty years. companies are attempting to reduce risk and improve
As a long term customer of Datamine, AMC have their mine planning by combining recently captured
used Datamine software on hundreds of consulting “quality” data with older non-standard or sub-optimal
projects. historical data. Typically, these opportunities for
improvement have their own unique challenges and
One reason for AMC’s continued use of Datamine there isn’t a “one-size-fits-all” approach that works.
software is because it provides the ability to implement AMC’s experience coupled with their access to the
data modelling and engineering methodologies that power and flexibility of Datamine software enables
are highly specific to individual situations. Datamine maximum additional value to be derived from each
software comprises multiple packaged pieces of opportunity.
workflow but also allows experienced geologists and
engineers to manipulate data in the way they require
to successfully model unique situations.
CASE STUDY
This case study outlines a recent example of how AMC
were able to help improve the design and scheduling
Use of Historical Data
of a large underground mine by using sparse historical
With new mineral deposits becoming harder to find
data to construct a reliable geotechnical model
and develop, mining companies are doing whatever
containing RQD and Q’ derived values. The historical
they can to maximize the value of existing projects.
data was in the form of a database of hand written
Many operations have an abundance of historical data,
logs and contained no direct RQD measurements.
frequently stored in a variety of ill-defined formats,
that has not been used effectively to influence the
Using reliable geotechnical models can have a positive
design and extraction of their ore.
impact on mine planning and it’s now common practice
for sites to record RQD values during core logging.
Typically, a variety of Kriging is used on the recorded
values to estimate the RQD values throughout the
deposit and use these to influence the safe design
of stopes and determine the difficulty and timing of
their extraction.
Due to the fractured nature of the input data, AMC In the synthetic example constructed, 24 simulations
couldn’t use the E-type estimate. They turned to the were run against the distribution.
median and mode of the interpolated data set.
Not unexpectedly, 63% of the simulations returned
The median is derived through simple linear a RQD value of 90, while 29% returned a value of
interpolation, the intersection of a probability of 50% 60 and the remainder 20.
(from the ordinate axis – Y Axis) and the interpolated
cumulative probability line, to give the corresponding
RQD value from the abscissa (X-Axis).
THE RESULTS
Through imaginative use of a dozen or so Studio RM
processes, whilst working within the limitations of a
discrete dataset, AMC were able to convert previ-
ously unusable qualitative data into a defensible and
practical model that reasonably represented the de-
posit’s rock quality.